0011171433
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of Amendment 2 is to answ er Contractor questions, update Attachment 2 - Specifications, and Attachment 4 - Wage Determination.
POC: Jamie Gregar, jamie.j.gregar.civ@mail.mil
1. CONTRACT ID CODE PAGE OF PAGES
1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 31-May-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911SA18B2010
X 9B. DATED (SEE ITEM 11)
02-May-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
30-May-2018
CODE
MICC - FT MCCOY
BLDG 1108 SOUTH R ST
FORT MCCOY WI 54656-5153
W911SA 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911SA18B2010
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 05-Jun-2018 02:30 PM to 14-Jun-2018 02:30 PM.
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been modified:
SUPPLEMENTAL INFORMATION
1) GOVERNMENT POC INFORMATION:
Contract Specialist: Jamie Gregar Email: jamie.j.gregar.civ@mail.mil Phone: 608-388-1007
Contracting Officer: Steven M. Bailey Email: steven.m.bailey2.civ@mail.mil Phone: 608-388-6077
2) CONTRACTOR POC INFORMATION:
Name: _____________________________________
E-mail _____________________________________
DUNS______________________________________
CAGE CODE________________________________
TAXPAYER ID #_____________________________
3) CONTRACT INFORMATION
a. CONTRACT TYPE: This will be a single award Firm Fixed Price type contract.
b. SUBMISSION DEADLINE FOR QUESTIONS: Any questions, concerns, verification or clarification of information on the documents included in the solicitation package shall be submitted in writing to the Government POC’s NLT 10:00 AM CST on 15 May 2018. Include in the subject line of the email the Government’s solicitation number.
4) SITE VISIT
a. A site visit is scheduled for 10 May 2018 at 10:00 AM local time at building 1108 Fort McCoy, Wisconsin.
This will be the only site visit conducted, requests for additional site visits will be denied. Please plan accordingly. POC for this site visit is the Contract Specialist listed above.
The conference will begin promptly without considerations for late or lost bidders; no subsequent site visits will be considered. Remarks, explanations and answers provided by Government representatives before, during and after the site visit shall not change or qualify any of the terms or conditions of the solicitation.
The solicitation can only be changed by a formal written amendment issued by the Fort McCoy Contracting Office.
5) REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF BIDDERS
SYSTEM for AWARD MANAGEMENT (SAM) REGISTRATION: SAM Registration is required of all Department of Defense contractors. SAM registration enables electronic funds transfer of contract payments. If your company is not already registered, please register in the SAM database at https://www.sam.gov/
A DUNS number is required for SAM registration. If your company does not have DUNS #, obtain one by calling 800-333-0505.
In accordance with DPAP changes to reporting requirements under FAR 52.223-2, Affirmative Procurement of Bio-based Products under Service and Construction Contracts, contractors are now required to submit annual bio-based reports to the new reporting module in the System for Award Management (SAM). SAM can be accessed at https://www.sam.gov.
The “Equal Employment Opportunity Is the Law” notice (poster) referenced in FAR clause 52.222-26(b) (3), Equal Opportunity, is located at http://www.dol.gov/ofccp/regs/compliance/posters/ofccpost.htm
In accordance with FAR 22.404-10, the contractor must post a copy of the wage determination and Department of Labor Form WH-1321 in a prominent place where employees working on federal construction contracts can easily see it. The applicable wage determination is incorporated into the contract at Section H. The WH-1321 poster is located at http://www.dol.gov/compliance/guide/index.htm
6) BONDING/BID GUARANTEE
a. A Bid Bond/Guarantee is required if the bid amount exceeds $150,000 and shall be provided in the amount of twenty percent (20%) of the bid price or $3,000,000, whichever amount is less. (Bidders must use the Standard Form (SF) 24 if providing a bid bond as the bid guarantee)
b. The successful offeror will be required to provide Performance and Payment bonds. Contract Awardee will have ten days after issuance of the contract to provide the required Bonds to the contracting office.
The contracting office has five days to complete the review and notify the contractor if the bonds are not sufficient. Actual work on site may not begin until bonding approval has been received by the contractor.
If bonds are returned because of contractor error, performance dates will not be revised.
7) REQUIREMENTS/DELIVERABLES
Completed SF1442 with acknowledgement of all amendments Bid Bond/Guarantee
8) CONTRACT MAGNITUDE: The magnitude of this contract is between $1,000,000 and $5,000,000.
9) ATTACHMENTS: All referenced documents for this solicitation are available at the Government Point of
Entry at http://www.fedbizopps.gov. Potential bidders are encouraged to subscribe for real-time e-mail notifications when information has been posted to the website for this solicitation.
Attachments listed below will be incorporated into the resultant contract.
W911SA-18-B-2010 Attachment 1 - ATOPSEC
W911SA-18-B-2010 Attachment 2 - Updated Specifications 5-31-18 W911SA-18-B-2010 Attachment 3 - Drawings W911SA-18-B-2010 Attachment 4 - Wage Determination W911SA-18-B-2010 Attachment 5 - SF 24
EVALUATION OF BIDS
BASIS OF AWARD
This requirement shall be awarded utilizing Sealed Bidding Procedures in accordance with Federal Acquisition Regulation (FAR) Part 14, as supplemented by the Defense Federal Acquisition Regulation Supplement (DFARS), and the Army Federal Acquisition Regulation Supplement (AFARS). Award will be made with reasonable promptness to the responsible bidder submitting the lowest responsive bid in accordance with requirements and provisions herein.
The Government will evaluate proposed prices for balanced and reasonable pricing, using price analysis techniques.
Proposed prices evaluated as unreasonable or unbalanced may be grounds for eliminating the bid from award eligibility.
EVALUATION CRITERIA
The Government will evaluate bids received in response to this solicitation solely on the basis of price and price related factors.
a. Evaluations will be conducted on the total amount of CLIN 0001 & CLIN 0002.
b. RESPONSIVENESS OF BID. For a bid to be determined responsive and considered for award, the bid must comply in all material respects with the invitation for bids. Such compliance enables bidders to stand on an equal footing, and maintain integrity of the sealed bidding system (Subpart 14.301).
In order to be considered responsive the Bidder:
Properly signed SF 1442, with Original Signature Acknowledgement (if any) of all Material Amendments, Shall not qualify the terms and conditions of the solicitation in the submitted bid Shall comply with the instructions of the solicitation.
A Bid Bond/Guarantee is required and shall be provided in the amount of twenty percent
(20%) of the bid price or $3 Million whichever is less. (Bidders must use the Standard Form (SF) 24 if providing a bid bond as the bid guarantee)
Shall submit a complete sealed bid package prior to the cutoff for receipt of bids
Non-Responsive bids will not be considered for contract award.
INSTRUCTIONS TO BIDDERS
1. BID SUBMISSION
a. Bid shall be submitted prior to offeror due date and time as identified on the Standard Form 1442 Block 13, to the following address:
Mission and Installation Contracting Command (MICC) – Ft. McCoy ATTN: Jamie Gregar 1108 South R Street Fort McCoy, WI 54656
b. Bid shall be submitted in a sealed envelope with the following information on the outside: Solicitation Number, Contract Specialist Name, Date and Time of Bid Opening, and bidders name and address. Please do not count the shipping/mailing envelope/box as your sealed envelope. Shipment packaging shall be able to be removed and still maintain the integrity of the sealed bid package.
c. Bids MUST be submitted via mail or hand carried to the MICC – Ft. McCoy Office to be received and time stamped prior to the due date and time listed on the Standard Form 1442 Block 13. Bids received after this date and time, or bids received via fax or email will be considered ineligible for award.
d. The bidder’s failure to include information required by this solicitation may result in the bid submission being found non-responsive and may therefore be ineligible for award.
2. BID PREPARATION INSTRUCTIONS
a. The bidder’s documentation specified below will constitute the Bidder's acceptance of the terms and conditions of the IFB, proposed contract type, and concurrence with the Specifications and other applicable documents.
b. All referenced documents for this solicitation are available at the Government Point of Entry at http://www.fedbizopps.gov. Potential bidders are encouraged to subscribe for real-time e-mail notifications when information has been posted to the website for this solicitation.
c. The bidder shall provide one (1) hard copy and one (1) electronic copy of all submission requirements.
Electronic copy shall be submitted on a CD-ROM. The documents may be in Microsoft Word, PowerPoint, Excel and/or Adobe PDF format.
3. SUBMISSON OF OFFER CONTENT
The Bid Package shall be organized as follows:
TAB A - Standard Form 1442, Solicitation Offer and Award. The Contractor shall acknowledge any amendments to the IFB in accordance with the instructions on the SF 1442. The bidder shall provide the name, title and telephone number of the company/division point of contact regarding decisions made with respect to your submission and who can obligate your company contractually. Also, identify those individuals authorized to negotiate with the Government.
TAB B – Bid Bond/ Guarantee. This tab shall include the bid bond.
Only the Awardee will be required to provide Performance and Payment (P&P) Bonds, as is stated in this solicitation, P&P Bonds are not required to accompany the contractors bid.
TAB C – Additional/Supplemental Information. This tab shall contain all other required information requested throughout this solicitation and any additional supplemental information. This includes but is not limited to Fill- In Provisions/Clauses and any additional supporting documentation the bidder provides at their discretion.
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
QUESTIONS & ANSWERS
Q1: Attached is the design guide and brochure for our vertical platform lift. Will you accept this as an approved alternate for the Fort McCoy 2000 upgrades project?
A1: As this is a sealed bid requirement, we do not evaluate equals. If the materials you can provide meets the required specifications in the solicitation, it can be used.
Q2: Solicitation pg. 7 of 34. For hand carried bids, how much time should the Prime leave to get through the main gate in order to hand carry to MICC? Does the Prime need to get badging prior to going into the MICC?
A2: The Government would suggest planning 15 minutes to get through the main gate.
Typically security requires someone without a CAC/Government card to obtain a pass at the main gate during entry. Note that late submissions will not be accepted should the carrier have to spend more time at the gate.
Q3: 01000-3. In regards to the CAC requirement, with the project being over 6 months, should we expect that all tradesmen personnel will need to submit for CAC cards? Or will CAC mainly be required for the prime's management personnel?
A3: The contractor will not be issued a CAC for this contract. All contractors may obtain access passes through DES in advance.
Q4: 01000-4. Is there a wait time at the gate for material deliveries or construction vehicles?
Could the MICC provide a brief synopsis of the wait time or approximately how much time is required in the queue that would be part of non-productive hour of the job i.e. wait is approximately 15 minutes.
A4: Wait time at the gate depends on what is going on at Fort McCoy and how many people are entering the gate at any given time.
Q5: 01000-4. Is there a licensed sanitary landfill or recycling center in accordance with NR500 that is located within the Ft. McCoy campus? Are there any types of dumping that is permitted within the gated area of the base? Is there a charge for using the Fort McCoy Recycling Facilities per 01000-4.O.1.?
A5: Yes, there is a licensed sanitary landfill/recycling center on post. It is not known if it is in accordance with NR500. Dumping is not permitted within the gated area of the base. No, there is not a charge to use the recycling facilities.
Q6: Could you please state the order of precedence for your RFP/solicitation documents for contractual and administrative changes to the project; i.e. (1) specs (2) drawings (3) 1442 B-M contract documents etc. ///The purpose for this question is that some Government Owners have drawings and their verbiage and place the language over specs when there is a discrepancy in documents. Please advise.
A6: Please refer to FAR 52.236-21
Q7a: 01000-7. Please state the closest DEMAR area to this job site and telecom utility provider required to make these connections on-site.
A7a: The Government is not familiar with DEMAR. Temporary Telephone: see section 1000, par 1.04 D. Network Enterprise Command (NEC) will make final connection through conduit installed by contractor. Contractor is responsible for all telecommunication and data in the building, providing terminal(s) that NEC can connect to.
Q7b. Secondly, will the prime contractor be required to access MICC websites/servers etc.
through hard lines or will Wi-Fi be acceptable?
A7b: Contractors can use their own WI-FI.
Q8: 01000-8. Please verify that NTP is provided once the prime executes the Preconstruction Conference or if none is held that the Initial Project Execution Schedule (IPES) is approved by the COR or does NTP start at the COR's discretion.
A8: The notice to procced will be provided by the Contracting Office upon receipt of all required submissions.
Q9: 01000-10. Please confirm that the Migratory Bird Nesting requirement from 1 May to 30 August is not a requirement of this project. We will have structural demo and minor clearing of threes around the BLDG 2000 facility. We assume that there is no nesting in this immediate area?
A9: Migratory bird nesting season applies to this project. The Government cannot determine if there will be nesting at the time of construction.
Q10: Is the end of the period of performance for MICC?
A10: The Government does not understand this question. The period of performance will be 300 days from the notice to proceed.
Q11: Please state the number of calendar days that MICC will need to review and approve submittals for this project. Is there a separate duration for MEP or life safety submittals?
A11: Submittals are be sent to COR as described in section 1300. Schedule for submittals is located at end of section 1000. There is not a separate duration for MEP or life/safety submittals.
Q12: Please clarify that Kenneth Hahn Architects, Inc is the Designer of Record for this project.
Please clarify if MICC is the final reviewer of construction submittals or if Hahn Architects has been retained to provide consultancy review for this project. Lastly, please clarify if the A/E has reviewed and approved of the specifications or if these are base templated specs utilized on most Ft. McCoy projects.
A12: Fort McCoy (COR) is final reviewer of submittals. Specifications were developed by the firm under the direction of Fort McCoy. The specifications were approved by Fort McCoy.
Q13: 01300-2. Please clarify that electronic submittals must go through the email ending in mail.mil and that there is no requirement for a cloud based submittal deliverable site such as Submittal Exchange. Is it advantageous for Ft. McCoy to have a clouded software where submittals can be reviewed and stamped and submitted securely or is email the standard protocol?
A13: Submittals are be sent to COR as described in section 1300. Schedule for submittals is located at end of section 1000.
Q14: 01400-2. Please confirm that the project on-site superintendent can also act as the SSHO, if properly trained and educated, and can also be the QC System Manager/Quality Control Manager for the project? Or does the MICC required separate hats and that more than one Prime manager is expected on the job-site. Please advise.
A14: This is the Prime Contractors discretion.
Q15: 156-019. Please clarify who owns the role as CxA and as CxR for this project. There is a large cost impact depending on CxA by contractor (3rd party) vs. by the owner/DPW/MICC or their retained Commissioning Agent. We have read 01 91 00 and seems like commissioning is a requirement, but by who.
A15: Commissioning is a contractor requirement. See spec section 2308 00.
Q16: 011400-2. Please describe the end of the Period of Performance (PoP) of the contract; is it at Substantial Completion, Final Acceptance, Beneficial Occupancy?
A16: The period of performance ends at final acceptance.
Q17: 01 33 29-2. Language in 01 33 29-1 lines 5 - 9 and the language over the remainder of the specification seem contradictory. Please verify the Prime Contractors LEED coordination requirements. We assume that the base or the A/E have paid the appropriate fees for any USGBC/GBCI requirements and that the prime contractor has supplemental submittal requirements. If LEED coordination is required as the A/E updated the 2009 LEED version to incorporate the new standards?
A17: The LEED requirements for this project have been waived, see section 01 33 29.
Q18: 02 01 00. Is the prime required to furnish a soils report by an approved stamped engineer.
The cost for a Geotechnical Engineer can be high. Is there a requirement for the depth and number of borings to ensure that the structural integrity of the building is not a risk of the prime contractor. Please elaborate on the expectations of the prime.
A18: YES, a licensed engineer is required to provide report, See SECTION 02 01 00, SUBSURFACE EXPLORATION, It states:
A. GENERAL
Subsoil investigations have not been made, therefore, the footings have been designed for the assumed bearing pressure specified on the Structural Drawings. The Contractor shall utilize the services of a Geotechnical Engineer (as described in Sections 01 40 00, 31 10 00 and 31 10 10) to inspect the subgrade and conduct sufficient testing to verify the adequacy of the foundation system shown and make recommendations on footing and slab subgrade preparation. If the foundation system shown is inappropriate, the Contractor shall notify the Contracting Officer for further instructions.
Q19: This project utilizes a Honeywell interface to other Army installations. Johnson Controls will not bid the project because that would allow Honeywell access to proprietary information that Johnson Controls does not want to divulge. Please advise. (Note from Contracting: I am assuming this is referring to the specifications starting in section 23 09 00. Does
A19: The specifications for this project have been revised. Please see the updated specifications.
Q20: Wrapping existing wood posts with gypsum board. The extent of applying gypsum board to existing wood posts that I can see is at the perimeter/exterior walls of the Gaming room/Cyber Center detail 7/A401 and possibly the wood post at the snack bar detail 2/A701, and detail 1/A- 604 EE at the vestibule. Do the other posts that are not on the perimeter walls in the game room get wrapped with gypsum board? Do the perimeter post in the library get wrapped with gypsum board. Are there any other areas where the posts get wrapped with gypsum board?
A20: Also, see details 1(Q/P/CC)/A-603 in library. Also, see note 29 on sheet G-003 and General Demolition Plan Notes #5 on sheet DA100.
Q21: What is required for tile backer board in the restrooms?
A21: See Section 09029 00-2, use same Gypsum Board as is specified for ceramic wall tile if recommended by approved Porcelain product manufacturer. If approved Porcelain product manufacturer recommends another backer board product then use product recommended by manufacturer.
(End of Summary of Changes)