CONTRACT LINE ITEM PRICING SCHEDULE
| ITEM NO. |
| DESCRIPTION |
| EST. |
QTY
| UNIT |
| UNIT PRICE |
| ESTIMATED AMOUNT |
BASIC ITEMS
All work complete for Repair Digester, Fort McCoy Wisconsin in accordance with the plans and specifications excluding Items No. 0002 – 0006 and Items below
Job
XXX
All work complete for initial cleaning of tanks
Job
All work complete to repair cracks in tanks
LF
All work complete to repair water control joints in tanks
LF
All work complete to repair concrete spalls above rebar in tanks
SF
All work complete to repair concrete spalls below rebar in tanks
SF
TOTAL BASIC AMOUNT $_____________________________
Offerors should provide pricing for the following CLINs as provided in Notes 1-5 below. These items may be awarded at a later date, via unilateral modification, if deemed necessary by the Government. Work shall only be performed when funded and a unilateral modification is provided to the awardee. These items will be evaluated as part of the award decision.
All work complete for coating of existing Digester Tank (Structure 60), including all associated surface preparation not included in Basic Items above
0007A
Additional cost for Surface Coating System #34 Modified, Epoxy Mortar 125 mils DFT Mortar
Job
0007B
Surface Coating System #33 Modified, Polymide Primer and Polyurea Coating in lieu of Item 0007A, See NOTE 5 below
Job
All work complete for coating of existing Sludge Holding Tank (Structure 62), including all associated surface preparation not included in Basic Items above
0008A
Additional cost for Surface Coating System #34 Modified, Epoxy Mortar 125 mils DFT Mortar
Job
0008B
Surface Coating System #33 Modified, Polymide Primer and Polyurea Coating in lieu of Item 0008A, See NOTE 5 below
Job
TOTAL AMOUNT $_________________________________
TOTAL AMOUNT (BASIC PLUS 0007 & 0008) $_________________________________
NOTES:
1. The Government reserves the right to fund 0007 within 30 calendar days after initial cleaning of existing Digester Tank (Structure 60) and 0008 within 30 calendar days after initial cleaning of existing Sludge Holding Tank (Structure 62).
2. Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. In case of variation between the lumpsum prices and the total amount, the lumpsum prices will be considered the price submitted. In case of variation between the unit prices and the extensions, the unit prices will be considered the price submitted.
3. A modification to a proposal which provides for a single adjustment to the total amounts, should state the application of the adjustment to each respective lumpsum price and unit price affected.
4. Quantities for unit priced items are estimated only and the respective unit price will prevail in the event of an overrun or underrun subject to General Conditions (Contract Clauses) Clause “Variation in Estimated Quantities”.
5. For Items 0007 and 0008:
If the coating system described in sub-item B costs less than coating system described in sub-item A, enter the difference between the coating systems as a negative number for the estimated amount corresponding to sub-item B. In this case, show the amount for sub-item B in parentheses as follows ($_______) and deduct this amount from the amount shown for sub-item A when figuring the total amount.
Evaluation Notes: Award will be made to the overall lowest bid of all the above items 0001-0008. The intent is to award all of the basic items (0001 to 0006) listed above during the initial award. Items 0007 - 0008 may be awarded at a later date, via unilateral modification, if deemed necessary by the Government. Work shall only be performed when funded and a unilateral modification is provided to the awardee.