Responses to Questions for W911S8-17-R-0002
1) Attachment 4/TE-1 – Work Price List, the list does not include any pricing to base the coefficient multiplier off of. Can you provide the price list?
RESPONSE: Complete and submit Attachment 4/ TE-1 (Revision 1) with your offer.
See Amendment 0001
2) Attachment 4/TE-1 – Work Price List, do the estimated quantities represent the base and all option years or each individual year?
RESPONSE: Attachment 4/TE-1 represents estimated quantities including the base and all option periods.
3) Work Price list shows quantity but no price?
RESPONSE: Complete and submit Attachment 4/ TE-1 (Revision 1) with your offer.
See Amendment 0001
4) In Section L an M, item A - Proposal Submittal and Inquiries – indicated proposal shall be submitted by email, but in the preparation instruction indicated be in 3 volumes, and each volume need one original + 1 electronic copy. So should we submit by email or deliver with original +1 Electronic copy?
RESPONSE: Offerors shall send original and (1) electronic copy of EACH Volume (3 volumes total) to:
| Mission and Installation Contracting Command |
| Attn.: Scott Byrd |
| Bldg 2015, Room 222 |
| Joint Base Lewis-McChord, WA 98433 |
5) Should electronic copy be in CD or USB?
RESPONSE: CD only.
6) If original + 1 electronic copy needs, be by FEDEX freight or hand deliver in, what is the correct street address?
RESPONSE: See Response to Question #4
7) In Section L and M, item C - Proposal in volume I, II, III, the paragraph description not in line with the table list. It seems the table list to be more correct one, please confirm.
RESPONSE: Refer to the information table.
See Amendment 0001
8) At page 20 of 43 – doing the calculation for prices BYP JBLM and BYP YTC, a bit of confuse in the paragraph, saying about Section J but not finding Section J. Saying about in Section L, Table 3, but not finding Table 3. Is that same as Technical Exhibit 1(TE-1)?
See Response to Question #1
9) Could I please request the previous bid item results for this project W911S8-17-R-0002..
Any pricing information about the prior contract should be obtained through the Freedom of Information Act.
10) I see the solicitation is listed as “Set Aside: Woman Owned Small Business”. Forgive me for my lack of knowledge in regards to this, but does this mean to bid this project as a Prime Bidder you need to be a Woman Owned Small Business?
Response: Status as an EDWOSB concern or WOSB concern eligible under the WOSB Program is determined in accordance with 13 CFR part 127 and IAW 19.1503 (b), All contractors must submit documents verifying its eligibility AT THE TIME OF INITIAL OFFER to the WOSB Program Repository. The contract shall not be awarded until all required documents are received. See FAR Clause 52.219-30 for further information