Exhibit_One_Pricing_Table_-_Environmental_Chamber_Maintenance_16-R-0006 _DPG_30_AUG_2016.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Chamber Maintenance
Solicitation number
W911S6-16-R-0006
Issued by

About this file

Exhibit one pricing table

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Quoted Rates

Please complete the following table for all labor categories that you wish to propose.
Labor CategoryHourly Rate
Base YearOY1OY2OY3OY4
Please complete the following table for all Material Handling rates that you wish to propose.
Material Handling RateMaterial Handling Rate
Base YearOY1OY2OY3OY4
MH Rate
**For informational purposes, a historical usage of hours on this contract has included approximately 300 hours for a Senior HVAC Technician, 200 hours for an HVAC Technician, and 50 hours for a Junior HVAC Technician/Maintenance Assistant.

Evaluation Example

Labor: Example Evaluation - Contractor will fill out the rate table below.
Labor CategoryHourly Rate
Base YearOY1OY2OY3OY4
Senior HVAC Technician$ 80.00$ 81.20$ 82.42$ 83.65$ 84.91
HVAC Technician$ 70.00$ 71.05$ 72.12$ 73.20$ 74.30
Junior HVAC Technician$ 60.00$ 60.90$ 61.81$ 62.74$ 63.68
To evaluate the costs consistently among offerors, the Gov't will multiply each hourly rate by 100 hours per year. The total for the evaluation would be $108,199.00.
Labor CategoryBase YearHoursTotalOY1HoursTotalOY2HoursTotalOY3HoursTotalOY4HoursTotalGrand Total
Senior HVAC Technician$ 80.00100$ 8,000.00$ 81.20100$ 8,120.00$ 82.42100$ 8,242.00$ 83.66100$ 8,366.00$ 84.91100$ 8,491.00$ 41,219.00
HVAC Technician$ 70.00100$ 7,000.00$ 71.05100$ 7,105.00$ 72.12100$ 7,212.00$ 73.20100$ 7,320.00$ 74.30100$ 7,430.00$ 36,067.00
Junior HVAC Technician$ 60.00100$ 6,000.00$ 60.90100$ 6,090.00$ 61.81100$ 6,181.00$ 62.74100$ 6,274.00$ 63.68100$ 6,368.00$ 30,913.00
Totals$ 21,000.00$ 21,315.00$ 21,635.00$ 21,960.00$ 22,289.00$ 108,199.00
Parts: Example Evaluation - Contractor will fill out the rate table below.
Material Handling RateMaterial Handling Rate
Base YearOY1OY2OY3OY4
MH Rate5.0%5.2%5.4%5.6%5.8%
To evaluate the costs consistently among offerors, the Gov't will multiply each MH rate by $10,000 per year. The total for the evaluation would be $52,700.00.
MH RateBase YearOY1OY2OY3OY4Grand Total
Parts Cost$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 50,000.00
MH Rate5.0%5.2%5.4%5.6%5.8%n/a
MH Subtotal$ 500.00$ 520.00$ 540.00$ 560.00$ 580.00$ 2,700.00
MH plus Parts Totals$ 10,500.00$ 10,520.00$ 10,540.00$ 10,560.00$ 10,580.00$ 52,700.00
The total amount to be evaluated from these proposed numbers would be $160,899.00.

File details come from the government source that posted it. Updated .