Contractor Questions
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SynopsisofAward.pdf | ||
| Abstract_of_Bids_W911RZ-14-B-0001.pdf | ||
| Electricallightinglevels.pdf | ||
| QALog2Jun14.pdf | ||
| GenDecisionNumCO14000605232014CO6.pdf | ||
| AsbuiltsB1525.pdf | ||
| ElectricalUnitSpecSheetorEQUAL.pdf | ||
| ElectricalGTSATSorEQUAL.pdf | ||
| SiteVisitMinutes.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Company POC Date Received Question
# Question Submitted to DPW Answer
Received Posted to
FBO
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 1
1.) During the site visit the Architect indicated that the New Foam Roof would be part of a concurrent but separate project. If the New Foam Roof is part of a separate project, will this contractor be responsible for the following items associated with the work shown on Sheet A-11.0 Roof Plan;
a. Patching of new roof @ note item 6 (existing air handling unit to be removed) , item 7 (existing condensing unit to be removed) and item 17 (remove existing exhaust fan). Several locations.
b. Patching of new roof @ note item 20 (equipment frame supports @ new roof top HVAC units). 16 locations.
The roof patch work will need to be installed by the same contractor to maintain the new roof warranty.
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 2
2.) During the site visit the Architect indicated that there is a layer of terrazzo floor beneath the VCT that will need to be removed as part of the VCT removal. Is this present through out the VCT removal area or can you provide specific areas that this is present.
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 3 3.) During the site visit the Architect indicated that the slope of floor @ existing floor drains to be plugged do not need to be leveled. Please confirm.
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 4 4.) During the site visit the Architect indicated that the existing epoxy floor coating will need to be removed. Please provide locations of epoxy flooring to be removed. I was not able to locate this in the drawings.
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 5
5.) During the site visit the Architect indicated that paint striping on existing concrete floor in back corridor will need to be removed before floor is stained and resealed. Please provide information on extend of painted striping to be removed as this is shown in drawings.
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 6 6.) Demolition drawing A-1.0 indicates removal of steel guard rail that is attached to existing brick wall. Will the bolt holes in brick to remain need to be patched? Note 14 on drawing A-3.0 indicates no changes to existing brick wall.
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 7
7.) Demolition drawing A-1.0 indicates removal of several existing bollards. These bollards go below slab on grade. Do we need to remove a portion of the slab to allow complete removal of the bollards and possible foundation or can bollards be cut off even with top of slab?
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 8
8.) Drawing E 2.0 indicates all lighting through out building. Can you provide existing as built drawings in order for contractor to determine quantity of light fixtures to be removed. Note 18 on sheet A – 8.0 indicates light fixtures and switches to remain in Area 5. This conflicts with notes in this area on sheet E 2.0.
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 9
9.) During the site visit it was noted that there is mechanical equipment in Mechanical equipment room @ approximately grid lines and 4. Please provide as built drawings or information for this area or other areas of mechanical equipment removal inside the building.
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 10
10.) During the site visit the Architect indicated that the chain link fence enclosure on south end of building would need to be removed. This is not indicated in drawings.
Please provide more information on extent of chain link fence removal. Will the landscaping in this area need to be repaired?
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 11
11.) Drawing C- 2.0 indicates a typical water main installation detail with a concrete patch of 8’ wide. The existing PIV is close to a joint in the concrete that are typically on a 15’ spacing. Is it acceptable to only remove an 8’ width of concrete (or the minimum width required) or will the concrete need to be removed back to the next existing joint? Does this concrete contain rebar or welded wire fabric?
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 12
12.) Drawing C-2.0 water main installation detail indicates backfill above sand bedding to be flowfill. Due to the size of the trench this require over 100 CY of flowfill. Would it be acceptable to use structural fill or existing removed material compacted to 95% in lieu of flowfill.
Native American Services Corp 2270 La Montana Way, Ste 101 Colorado Springs CO 80918
Jim Field, Estimator 719 265-6670 ext
5/12/2014 13 13.) Is the existing fire line going to the building at this PIV encased in flowfill? How far away from existing water line do we need to stay.
Southwestern Dakotah, Inc. 3148 S. Chrysler Ave Tuscon, AZ 85713
Tricia Yager, Project Administrator (520)663-0989
5/14/2014 14
14.) At the site visit, it was brought up by the architect that the “new foam roof system” address in the plans was for reference only. It was stated that per this solicitation there is no applicable roofing work, except where in it deals with putting HVAC equipment on the roof. Please advise if this is correct because per the plan sheets, it states that the “new foam roof system” is to be included.
Southwestern Dakotah, Inc. 3148 S. Chrysler Ave Tuscon, AZ 85713
Tricia Yager, Project Administrator (520)663-0989
5/14/2014 15 15.) 2. Please confirm the construction duration of the separate roofing contract? It was brought up at the site visit that the roofing portion is a separate project, and that this project will run simultaneously with the roofing project.
Southwestern Dakotah, Inc. 3148 S. Chrysler Ave Tuscon, AZ 85713
Tricia Yager, Project Administrator (520)663-0989
5/14/2014 16
16.) 3. At the site visit, it was brought to the attention by an attendee that in the existing coolers there is a substantial amount of epoxy flooring that will need to be demoed in order to expose the raw concrete. Please provide the square footage of epoxy flooring that will need to be demoed as it is not on the plan sheets
Southwestern Dakotah, Inc. 3148 S. Chrysler Ave Tuscon, AZ 85713
Tricia Yager, Project Administrator (520)663-0989
5/14/2014 17
17.) 4. At the site visit, the flooring in the coolers was brought up, as in needing to level out the concrete where the floor is currently bowed towards the drains, that this issue would not need to be corrected, only the drains needed to capped and filled. Please confirm there will be no leveling needed in the areas where the cooler drains are capped and filled.
Southwestern Dakotah, Inc. 3148 S. Chrysler Ave Tuscon, AZ 85713
Tricia Yager, Project Administrator (520)663-0989
5/14/2014 17
14.) At the site visit, it was brought up by the architect that the “new foam roof system” address in the plans was for reference only. It was stated that per this solicitation there is no applicable roofing work, except where in it deals with putting HVAC equipment on the roof. Please advise if this is correct because per the plan sheets it states that the “new foam roof system” is to be included
Southwestern Dakotah, Inc. 3148 S. Chrysler Ave Tuscon, AZ 85713
Tricia Yager, Project Administrator (520)663-0989
5/14/2014 18 18.) 5. In the south end of the building, area 5 unassigned area, there are bollards that were mentioned needed to be removed. Per the specifications and plans this work is unassigned. Please confirm whether these will need to be removed or not.
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 19
19.) During the Pre-Bid Meeting we noticed plywood square covers secured to floor at existing retail area. Please advise as to:
What is the function of these covers?
Is the scope of work is intended to include elimination of these covers?
What are the conditions below the covers?
Is repair or remediation required as part of this contract?
If repair/remediation is required please provide information as to the method.
If repair will be part of this contract please provide a count of how many of these areas exist.
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 20
20.) Is there any concern that noise generated by demolition and other activities may affect operations at the existing CIF?
Are there limitations on sound levels transmitted to the CIF that the Contractor must observe?
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 21
21.) During the previous phase of renovation of the CIF significant areas of floor area required leveling prior to applying carpet and vinyl floor finishes. Will floor leveling be required to be included in the Contractors Offer or be treated as a Contract Modification?
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 22 22.) During the Pre-Bid Meeting the question was asked if floors sloping to existing floor drains (other than those noted on P1.0) will require leveling. Our understanding was that leveling would not be required. Is our understanding correct?
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 23 23.) During the Pre-Bid Meeting it was our understanding that the Note #14, (New 21” Dia Light Tube) on Sheet A-11.0, are not applicable to this Offer. Is our understanding correct that those Light Tubes are not to be included in our offer?
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 24
24) During the Pre-Bid Meeting it was our understanding that the Notes #10, #11 & #12 (New Spray Foam Roof) on Sheet A-11.0, are not applicable to this Offer. Is our understanding that the New Spray Foam Roof is not to be included in our offer.
Please confirm our understanding is correct. If it is correct, please provide anticipated milestone dates related to your roofing contract, that will interface with roof activities included in the scope of work associated with Solicitation Number
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 25
25) If the New Spray Foam Roof is to be applied by others; will the Contractor performing that work be required to coordinate the sequence of his activities with the successful Offerer for this solicitation so that work performed by both Contractors are executed in a logical sequence to assure maximum quality and efficiency. It seems imprudent to have a new foam roof put on, and then subject it to significant foot traffic (with work boots) and then make apprx. 100 penetrations that will require repair.
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 26 26) Are references to dry stack stone to be interpreted as “cultured stone”?
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 27
27) References are made to Note 24, Sheet A-17.0, which we do not find. Is the intention to set the Split Chair Rail at the height indicated on A.12.0, Section 2 and set stone below and drywall/paint above?
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 28
28) Sheet A-6.0 Notes 37, 38, 39 & 40 reference disassembly and reassembly of Audiology Booths. Is the cost of this work to be included in Contractors offer? If so please provide additional information pertaining to manufacturer and model numbers.
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 29
29) Based on instructions at the Pre Bid walk-through it was our understanding that the building central boiler in the existing Mechanical Room is to be dismantled and removed. This work is not shown in the demo notes on Sheet A-1.0. Please clarify if the removal of that boiler is to be part of the Contractors Offer.
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 30
30) Will electrical power be provided for the successful Contractor or will it be metered and paid for by the Contractor?
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 31 31) Are existing fire sprinkler drawings available for review to anticipate new modifications?
CMS of Colorado Springs 176 Talamine Court Colorado Springs CO 80907-
Tom Perkins, Project Manager (970)846-
5/14/2014 32 32) Is the removal of the heavy epoxy floor coating at the Deli Prep Area to be included in the Contractors Offer?
Q&A Log