This document is a request for proposal for a job order contract to provide real property sustainment, restoration, and modernization minor construction services at Fort Polk, Louisiana. The contract will have a base period of 12 months with four 12-month option periods and an estimated value between $25-50 million. Task orders will range from $2,000 to $1 million. The solicitation closes on January 24, 2022. It is a 100% small business 8(a) set-aside for North American Industry Classification System code 236220. Questions are due by January 7, 2022. The awardee will provide typical job order contract services including site work, demolition and rebuild, mechanical system replacement and controls, infrastructure preservation, renovation, and finish replacement.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911RX22R0001
Section SF 30 - BLOCK 14 CONTINUATION PAGE
AMD 2 - SUMMARY OF CHANGES
The purpose of this Amendment (AMD) 0002 is to:
1. Provide Government response to Industry Questions.
2. Provide Revised Documents.
a. Attachment 3, Past Performance Questionnaire, Rev2
b. Attachment 4, Notional Task Order, Rev2
3. Provide Attachment 8, Solicitation W911RX-22-R-0001 Ft Polk JOC
4. Extend the following due dates:
a. Past Performance Questionnaires due date NLT 4:00 CST, 4 February 2022.
b. Proposal due date NLT 4:00 CST, 4 February 2022.
Q & A RESPONSES
Solicitation W911RX-22-R-0001, FT Polk Job Order Contracting (JOC), Industry Questions & Answer
Q1. In reference to Volume II - Technical Acceptability, Subfactor (b) - Proposed Staffing; would the Government consider removing the limitation of four (4) active projects within a 10 minute travel radius for the Superintendent and SSHO? This requirement will unnecessarily drive up overhead costs that will ultimately pass through to the Government.
Response: See revision to Volume II - Technical Acceptability, Subfactor (b) - Proposed Staffing. The Site Safety and Health Officer (SSHO) position has been omitted.
Additionally, in response to the limitation of four (4) active projects within a 10 minute travel radius. There will be no change to this requirement. NOTE: Superintendence of the job can be supplemented with competent job site foremen who are knowledgeable and experienced in the type of work being performed on the site.
Q2. The historical workload data provided with the solicitation documents seems inconsistent with a JOC of this magnitude; a $50M ceiling over a five year period if all options are exercised. Typically a JOC of this magnitude would have 150-200 task orders over the 5-year contract term, rather than 165 over a nine and a half year period as historically indicated. What is the volume of task orders anticipated for the proposed JOC so that offeror's can staff and price the contract accurately?
Response: The volume of task orders is anticipated to be in the 150-200 range. The historical figure of 165 task orders over a nine and a half year period was the result of contracts that had limits of $5M per year, which limited the number of task orders that could be awarded.
Q3. RFP Page 18, Subfactor (b) lists the following positions as Key Personnel: Project Manager, Superintendent, Quality Control Plan Manager and Estimator. However, under the Minimum Qualifications paragraph following this statement, a Site Safety and Health Officer (SSHO) is listed. Please clarify as to whether the SSHO is or is not considered Key Personnel.
Response: The Site Safety and Health Officer (SSHO) is not considered a Key Position.
See revision to Volume II - Technical Acceptability, Subfactor (b) - Proposed Staffing. The Site Safety and Health Officer (SSHO) position has been omitted.
Q4. RFP Page 16, C.2.a states: "A PDF file format is allowable for Volumes I, II, and III only." However, Section 00010 (Solicitation Contract Form) that is required in Volume IV - Price has been provided to Contractors in a pdf format. Please provide Section 00010 in a format other than pdf.
Response: See Attachment 8, W911RX-22-R-0001, FT POLK JOC. This document is in Microsoft Word format.
Q5. With both the Christmas holiday and New Year's holiday limiting the amount of manpower available to complete the bid requirements, as well as the RFP requiring 6 proposals submitted in less than 30 days from time of RFP release to due date, we respectfully request an extension of two (2) weeks (to February 7, 2022) to ensure we can properly prepare a top quality proposal for this contract.
Response: See www.sam.gov for all updates to proposal due dates.
Q6. The solicitation documents identify key personnel for each project. Is the intent that SSHO personnel be used for every project? This could be a cost savings metric for the government's consideration if the Superintendent is allocated for this as a dual role position.
Response: See revision to Volume II - Technical Acceptability, Subfactor (b) - Proposed Staffing. The Site Safety and Health Officer (SSHO) position has been omitted.
Q7. Is there any opportunity to tour the base and gain insight to the conditions of existing infrastructure?
Response: The Government will not facilitate a tour of the installation. Potential offerors interested in touring the installation may coordinate directly with the Fort Polk Visitor Center. The process of gaining access to the installation IS NOT the responsibility of DPW or the Contracting Team.
Information on gaining access to the installation can be found at:
https://home.army.mil/polk/index.php/about/visitor-information
Q8. Are projects identified under this task order to be Design Build projects?
Response: No.
Q9. Does the government intend to utilize RS Means solely?
Response: Yes.
Q10. Will a project scheduler be required for each project and require P6 schedule updates with task flow logic?
Response: Polk interprets P6 schedule to reference Primavera software. A Gantt chart with dates in either Acrobat or Excel will be sufficient for schedules.
Q11. With regards to past experience, is a teaming partner allowed to designate experience for JOC? If so, is there a specific percentage that must be performed by the prime?
Response: No, the Prime Contractor is responsible for meeting the requirements of the contract, therefore, is responsible for meeting the past experience requirement.
Q12. Page 46 of original solicitation 252.219-7009 SECTION 8(A) DIRECT AWARD (OCT 2018) Please confirm that contractors with SBA BOS in other states are permitted.
Response: DFARS Clauses 252.219-7009 has been deleted from this solicitation. This requirement is a competitive 8(a) set-aside acquisition. Additionally, competition will be limited to only 8(a) firms located within the area serviced by the Louisiana SBA District Office and other 8(a) construction firms with a bona fide place of business within the geographical competitive area.
Q13. FYSA - EO 14026 will likely be in effect upon contract award. Contractor assumes wage increases will be handled at task order level.
Response: The Government acknowledges the pending EO 14026.
Q14. Page 5 of Amendment 1: Table 2. Is the total page count for Volume II 75 pages or is the total Volume page count 150 - 75 pages for everything except subfactor c plus 75 pages for subfactor c?
Response: No, the total page count for Volume II is 150 pages.
Technical Acceptability = 75 pages max and Subfactor (c) Notional Task Orders = 75 pages max.
Q15. Page 5 of Amendment 1 part a. The RFP states, "File names shall be provided in the format of "Volume #, Company Name - Initial" for the first submission." What does the Government mean by "initial"?
Response: The term "initial" will be used for the initial (i.e. first submission of the Offerors proposal); subsequent submissions will be numbered accordingly.
Q16. Can we submit CPAR evaluations with our proposal, versus PPQ's?
Response: No. The Government will utilize BOTH CPAR evaluations and Past Performance Questionnaire (PPQ's) as a means of evaluating Factor 2 - Past Performance.
Q17. Can the Superintendent also serve the duties of Site Safety & Health Officer if the Superintendent has the required EM 385 1-1, First Aid/CPR & OSHA safety training?
Response: See revision to Volume II - Technical Acceptability, Subfactor (b) - Proposed Staffing. The Site Safety and Health Officer (SSHO) position has been omitted.
Q18. Can a Superintendent manage more than 4 task orders that are less than $100,000 each?
Response: See Volume II, Subfactor (b) - Proposed Staffing. Superintendent
Q19. Can the SSHO manage more than 4 task orders that are less than $100,000 each?
Response: See revision to Volume II - Technical Acceptability, Subfactor (b) - Proposed Staffing. The Site Safety and Health Officer (SSHO) position has been omitted.
Q20. Please confirm that the cost of all the field management team (PM, QC Manager, Superintendent & SSHO) must be included in the coefficient?
Response: See Factor 3 - Price.
Q21. The task orders reference specifications, but we can't seem to find them in the attachments. Are there specifications to follow for the Task Orders?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q22. On task order #1, it listed to install carpet tile. Is there a certain weight of carpet tile required?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement.
Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q23. For task order #2, is test and balance and commissioning required? Does this task order require a new gas and water meter?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement.
Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q24. For task order #4, what size footing is required for fence posts? Is concrete testing required?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement.
Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q25. Are we to use the bare cost line item cost or the OH&P line item cost from RS Means?
Response: The Offeror shall determine which cost to select and ensure that Government is not double charged.
Q26. The instructions tell us to apply the City Cost Index (CCI) to Section 1, Division Summary, Section 2- Totaling Components and Section 3 Line Item estimate. What is the correct/current CCI to use on the Notional Task Order proposals we submit?
Response: The correct City Cost Index (CCI) is Lake Charles, LA.
Q27. Technical Exhibit A - Ft Polk JOC Statement of Work, and Technical Exhibit F-Division 01 General Requirements are identical documents. Is this an error or intentional?
Response: Intentional.
Q28. Technical Exhibit A - Ft Polk JOC Statement of Work, Clause 16.2.b references JOC Technical Specifications. Can this document be provided for review?
Response: Specific JOC Technical Specification are unique for the associated task order. Specifications will be provided with each task order. In the absence of specific guidance in the JOC Technical Specifications, industry standards shall be utilized.
Q29. Technical Exhibit A - Ft Polk JOC Statement of Work, Clause 16.2.e references JOC Standard Operation Procedures. Can this document be provided for review?
Response: No, the JOC Standard Operation Procedures (SOP) is a Government ONLY document and will not be provided to offerors. Pertinent information from this document will be provided to the contractor with the associated task order, if applicable.
Q30. Technical Exhibit A - Ft Polk JOC Statement of Work, Clause 16.2.f references JOC Guide. Can this document be provided for review?
Response: No, the JOC Guide is a Government ONLY document and will not be provided to offerors. Pertinent information from this document will be provided to the contractor with the associated task order, if applicable.
Q31. Technical Exhibit A - Ft Polk JOC Statement of Work, Clause 17.3 Drawings; indicates that the Contractor is to convert the Governments SOW and sketches into CAD drawings and that the cost is to be included using the appropriate line items from the UPB. Does this requirement apply to any of the Notional Task Orders? If so, which Task Orders?
Response: Yes, the Statement of Work (SOW) applies to all Notional Task Orders.
Q32. Notional Task Order 1, Repair Architectural Finishes in Police Station, Division 9-Finshes
a. SOW Item 9.1, Will floor leveling/patching be required prior to installation of the carpet. If so, please provide approximate area, thickness and type?
| b. SOW Item 9.4, Please provide the size, type and weight of the new carpet tile? |
| c. SOW Item 9.5, Please provide the type of paint and number of coats? |
| d. SOW Item 9.6, Please provide the type of paint and number of coats? |
| e. SOW Item 9.6, Will both the interior and exterior of the doors and frames be |
painted?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q33. Notional Task Order 2, Repair HVAC Bldg. 90033
a. Please provide details indicating the construction of the roof structure (metal deck on steel joists, concrete deck on steel beams, etc.) and the approximate height above finished floor of the bottom of the structure? Please also provide the method of hanging the mechanical equipment (beam clamps with threaded rods, metal straps, etc.)?
b. Please provide a ceiling plan for the existing construction to include ceiling types and heights?
c. Will test and balance be performed as part of this scope of work? If so, are their qualification requirements for the performing company and will it be performed on the entire HVAC System or just the newly installed equipment?
d. Will commissioning be performed as part of this scope of work? If so, please provide a specification or the specific requirements for performing a commissioning?
e. Please provide the type and thickness of the pipe insulation for the chilled water and hot water piping? Will the insulation be jacketed? If so, please provide the type of jacketing?
f. Sheet ED-101 & ED-102, Some of the motors indicated for demolition are missing a horsepower indication. Can a minimum horsepower be assumed for these motors?
If so, what is the minimum horsepower?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
g. Sheet ED-101 & ED-102, the symbol legend indicates that the conduit and wiring is to be retained for new installation; however, General Note 2 indicates that all conduit and wire is to be removed. Additionally, General Note 6 indicates existing conduit can be reused. Please clarify whether the existing conduit and wire is to be removed or be reused?
Response: See revision to Notional Task Order 2, Repair HVAC Bldg. 90033. Conduit will be removed and replaced.
Q34. Notional Task Order 3, Replace Power Poles in Various Locations
a. Please clarify whether the new power poles are to be installed adjacent to the existing pole prior to demolition of the existing pole or the existing pole is to be removed and the new pole is to be installed in the same location?
b. Please provide the assumed embedment depth of the new 45' power poles and the soil type?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q35. Notional Task Order 4, Replace Fence at Storage Building
a. What is the configuration of the current fencing (i.e. 4 sides, 3 sides, etc.)?
b. Is the existing fencing on level ground or rough terrain?
c. Are the current fence posts in concrete?
d. What is the type of soil in the surrounding area? Will rock excavation be required for installation?
e. What is the type and size of the line posts, corner posts, vehicle gate posts, man gate posts, top rail and brace rail? Will the bottom of the fence require a bottom rail or a tension wire? Please provide type and size of rail or gage of wire?
f. Is the 3-strand barbed wire required on both sides (interior and exterior) or only one
g. Please provide the desired gage of the chain-link fence fabric?
h. Are grounding rods required? If so, please provide detail (diameter of rod, length of rod, wire type and size, etc.)?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q36. Notional Task Order 5, Emergency Roof Replacement
a. Per SOW, Item #1 the contractor is to core existing system to determine existing material depth. Since there will not be a site visit, what is the depth to be assumed?
b. Per SOW, Item #2 the contractor is to remove existing 40 mil roofing system, however, in the build-back, item #4 states to dens deck over existing system. Is contractor to the demo to existing system or roof over existing?
c. Per SOW, there are areas of flat roof and areas of pitched roof. The provided drawings only include a minimal footprint without this detail. Please provide drawing depicting area and dimension of both roof planes with arrows indicating the direction of the pitch and the pitch ratio?
d. Per SOW, Item #7 indicates the installation of "prefabricated flashings around all curbs and deck penetrations in accordance with roofing specifications." Please provide drawing depicting locations and dimensions of curbs, parapet walls, scuppers, quantity of penetrations and sizes?
e. What material is to be used to cap parapet walls?
f. Please provide detail of the elevation above finished floor of the existing roof?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q37. Section 00100-Bidding Schedule Instructions to Bidders.
In Section 00100-Bidding Schedule/Instructions to Bidders on page 22, the Government references submitting Volume IV - Price in MS Office Excel format only, yet also states that the Price Volume contain both a Bondability letter and Section 00010 Solicitation Contract Form. Is it the Government's intention that Offerors submit an MS Office Word file containing the Bondability letter and Solicitation Contract Form as well as an MS Office Excel file containing the Government's three Excel pricing worksheets (Attachments 5, 6 and 7)? Please clarify.
Response: See Revised Volume IV - Price All information relating to the proposed cost/price data must be submitted in electronic format. Electronic versions of the Cost/Price proposal (Attachments 5, 6, 7) shall be submitted in MS Office Excel format only, and shall NOT be read only or password protected. All formulas, lookup tables, and links shall be intact, and no links shall exist to files not included with the submission. Excel workbooks should not contain hidden spreadsheets. PDF or flat files will not be acceptable.
| - | Bondability Letter may be submitted in PDF Format or Microsoft Word Format. |
| - | Section 00010 may be submitted in PDF Format or Microsoft Word Format. |
| - | Coefficients (Attachments 5, 6, 7) - shall be submitted in MS Office Excel format only, and shall NOT be read only or password protected. |
Q38. Attachment 4 - Notional Task Order Requirements, Task Order #2 Will the Government please provide equipment specifications of existing HVAC equipment or allow contractor a site visit to ensure proper repair or replacement if required of existing equipment?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q39. Attachment 4 - Notional Task Order Requirements, Task Order #3 Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q40. Attachment 4 - Notional Task Order Requirements, Task Order #4 No drawings are available for the requirement. Will the Government consider a site visit or provide clarification for the type of footer required? Does the Government require electric gates or manual open gates?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q41. Attachment 4 - Notional Task Order Requirements, Task Order #5
Statement #1 states contractor may vary roof depth by coring and repair during project site visit; however, it has been noted elsewhere in the solicitation that site visits will not take place. Consequently, can roof depths be provided for estimating purposes or are there As-Built drawings or any references for the contractor to use when preparing an estimate for the work? Will the Government verify if a staging area is available for demolition?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q42. Attachment 4 - Notional Task Order Requirements, Task Order #5 Statement #6. The roofing plan does not designate which roof is shingle or metal standing seam pitched. Will the Government please clarify?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q43. Attachment 4 - Notional Task Order Requirements, Task Order #5 Statement #8. The roofing plan does not designate the height or location(s) of the Parapet wall. Will the Government please clarify?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q44. Attachment 4 - Notional Task Order Requirements, Task Order #5
Statement #10. Will the Government provide a detailed drawing to install a 4-inch PVC fascia bar with tan cover to terminate the membrane roofing system around the perimeter of the building?
Response: See Volume II, Subfactor (c) - Notional Task Order Requirement. Attachment 4 and 4a provides a fictional workload scenario of five (5) notional Task Order projects that are typical of a JOC. These scenarios do not represent actual construction workload. Offerors are expected to apply those principles, processes and knowledge required herein to prepare a detailed proposal for each of the notional Task Orders. Responses must incorporate all roles and responsibilities, means and methods, and the requirements at TE A, Division 1, General Requirements of this solicitation. The Unit Price Book discussed at TE A Division 1, General Requirements shall be utilized to provide line items, take-off quantities, unit prices, etc., to support proposed task order prices. All requirements normally associated with actual Task Order proposal requests should be considered in the response. All five Task Order proposals must be supported by the Offeror's rationale for selection of line items, critical path milestones, etc., in order to be acceptable for evaluation and consideration for award. Additionally, industry standards shall be utilized.
Q45. KTR has multiple concerns regarding Attachment 5 - Coefficient. Specifically:
| o The information provided and instructions on bidding the price proposal seems unfairly slanted towards the incumbent contractor and/or contractors currently working at Fort Polk. Contractors who have not worked at Fort Polk seem to be at a disadvantage as they would not have the same local data as the incumbent contractor and/or contractors who have a current or past presence on Post and surrounding areas. |
| o For the same reason, the bid method seems to place an undue burden on small business contractors who have not worked at Fort Polk. As this project is 100% 8(a) set aside, we question the fairness of this bid methodology. |
| Please provide an explanation detailing how a non-local contractor should bid this contract or provide current and relevant data for the bidding process. |
| In addition, due to potential legal protests regarding the exclusionary and discriminatory methods mentioned above, we respectfully request the Government perform a thorough re-examination of Attachment 5 to determine appropriateness for this contract. |
Response: This contract is a follow-on effort and, as stated in FAR 19.203, "if a requirement has been accepted by the SBA under the 8(a) Program, it must remain in the 8(a) Program unless the SBA agrees to its release in accordance with 13 CFR parts 124, 125, and 126". Attachments 5, 6 & 7 (Coefficient Developments) are the standard for coefficient development and provide great flexibility to anyone desiring to send in a price proposal. The use of a Unit Price Book ensures everyone is equal when it comes to construction costs. It is up to each company to evaluate their own way of doing business and provide their best pricing proposal for this effort. The coefficient, also referred to as the "multiplier" or "factor", is the markup or markdown (discount) applied to the base IDIQ price to arrive at the contractor's price. Additionally, it is considered "fully loaded" and includes all costs including general conditions, overhead and profit. For Job Order Contracts and coefficients, see AFARS 5152.237-9000.
Q46. Attachment 5: Instructions Tab, 4.b.3.a: contractors are instructed that "subcontractor overhead will not be accounted for in the value of the UPB not in the contractor markup."
However, Line #31 - Coefficient, Bullet #9 states that the coefficient will contain "Subcontractor overhead and profit." Please clarify.
Response: Tab, 4.b.3.a: states: "3.The total contractor markup, the costs including prime contractor profit being covered by the coefficient (CCC). (a) The Cost Covered by the Coefficients (CCC) shall be inclusive of all Division 00 Adjustment Factors including, but not limited to, overhead, profit, taxes, etc. Note subcontractor overhead and profit will be accounted for in the value of the UPB not in the contractor markup." Line 31 "COEFFICIENT: The Offerors coefficient shall contain all costs other than the pre-priced unit prices and shall include, but not be limited to: 9. Subcontractor overhead and profit" is stated correctly.
Q47. Attachment 5: Instructions Tab, Line 14, Item #2 states:
The basis for any assumptions regarding the expected "awards volume." (T.O. Awards) As this item is the most critical factor in developing the coefficient and the most difficult to predict, please provide historical data for task order dollar amounts as a percentage of the total allocated funding for the current contract.
Response: As required by DFARS 236.204, the estimated magnitude of this project is $50,000,000.00. Historical data is provided, see Technical Exhibit C - Fort Polk Historical Workload.
Q48. The RFP and SOW have conflicting information regarding Key Personnel. Statement of Work, Section 8.1 states:
o Key personnel include the Program Manager, Project Manager or/Designated Site Superintendent, Quality Control Manager (QCM) and Estimator.
However, RFP, Page 18 states:
o The Government considers the following key positions to be the absolute minimum acceptable level of management staffing requirements: Project Manager, Superintendent, Quality Control Plan Manager and Estimator.
Also, RFP, Page 25 Subfactor (b) - Proposed Staffing states:
o To be considered technically acceptable, proposals shall consider the following positions to be the absolute minimum management staffing requirements: Project Manager, Superintendent, Quality Control Plan Manager, and Estimator.
Lastly, the Minimum Qualifications paragraph in that same RFP section references a Site Safety and Health Officer (SSHO) which is not included in either of the other three RFP and SOW staffing references.
Please provide clarification as to which positions are considered Key Personnel.
Response: See revision to Volume II - Technical Acceptability, Subfactor (b) - Proposed Staffing. The Site Safety and Health Officer (SSHO) position has been omitted.
Q49. RFP, Page 18 Subfactor (b) - Proposed Staffing states:
Any arrangements proposed shall be sanctioned by the Small Business Administration, and the KO will validate the eligibility of those arrangements as part of this subfactor.
Regarding the term "sanctioned" - Does the Government intend for contractors to submit official/legal teaming agreements to the SBA before proposal submission?
Does the Government require Teaming Agreements to be included in the proposal?
Response: Yes, under this small business set-aside, Offerors are free to propose teaming arrangements, mentor/protégée agreements, partnerships, and joint ventures so long as they are official business arrangements allowable under the Small Business Act. Any arrangements proposed shall be sanctioned by the Small Business Administration, and the KO will validate the eligibility of those arrangements as part of this subfactor.
Q50. RFP, Page 20 states:
Past Performance information described herein is required on the Offeror and all subcontractors, teaming partners, and/or joint venture partners proposed to perform.
Contractors will be utilizing many trades on this contract thereby employing numerous subcontractors/vendors.
Does the Government intend for Contractors to submit past performance information for ALL subcontractors/vendors? Or only those major subcontractors who will be performing a larger percentage of the work and/or multiple trades?
Response: SEE Volume III - Past Performance The Government will perform a Confidence Assessment of the Offeror's past performance to arrive at a confidence rating. The Confidence Assessment represents the evaluation of an Offeror's past work record to assess the Government's confidence in the Offeror's probability of successfully performing as proposed. Past Performance information described herein is required on the Offeror and all subcontractors, teaming partners, and/or joint venture partners proposed to perform. In addition, the Offeror shall detail the percentage of work performed by each subcontractor or partner based on the total proposed price.
AMD 1 - SUMMARY OF CHANGES
The purpose of amendment (AMD) 1 is to:
1. Correct Section 00100, Instructions to Offerors.
a. Past Performance Questionnaires (Attachment 3) are to be returned no later than 4:00 pm CST, 24 January 2022.
2. Revise Attachment 3, Past Performance Questionnaire.
a. See Attachment 3, Past Performance Questionnaire Revision 1.
b. Past Performance Questionnaires are to be returned no later than 4:00 pm CST, 24 January 2022.
The hour and date specified for receipt of offers is NOT EXTENDED.
Section 00010 - Solicitation Contract Form
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
JOC Normal Working Hours - Base Period
FFP
Base Period Coefficient Normal Working Hours are Monday through Friday, 7:30 a.m. to 4:30 p.m.
local time (excluding Federal Holidays).
The value inserted here is transferred from Attachment 5, Development of Coefficient for Normal Working Hours.
FOB: Destination
PSC CD: Z2JZ
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
JOC Other Than Normal - Base Period
Base Period Coefficient Other Than Normal Working Hours are anytime Monday through Friday, after 4:30 p.m. local time, on weekends, and/or Federal Holidays when work is required to be performed on an emergency basis, or at the Government's convenience to minimize the impact on ongoing military operations.
The value inserted here is transferred from Attachment 6, Development of Coefficient for Other Than Normal Working Hours.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
JOC Non-PrePriced - Base Period
Base Period Coefficient The total Non-PrePriced line items allowable under this program SHALL NOT EXCEED 10% of the total contract value. The value inserted here is transferred from Attachment 7, Development of Coefficient for Non-PrePriced Line Items.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
| OPTION |
| JOC Normal Working Hours - OY1 |
FFP
JOC Normal Working Hours - OY1 Option Year 1 Coefficient Normal Working Hours are Monday through Friday, 7:30 a.m. to 4:30 p.m. local time (excluding Federal Holidays).
The value inserted here is transferred from Attachment 5, Development of Coefficient for Normal Working Hours.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
| OPTION |
| JOC Other Than Normal - OY1 |
FFP
JOC Other Than Normal - OY1 Option Year 1 Coefficient Other Than Normal Working Hours are anytime Monday through Friday, after 4:30 p.m. local time, on weekends, and/or Federal Holidays when work is required to be performed on an emergency basis, or at the Government's convenience to minimize the impact on ongoing military operations.
The value inserted here is transferred from Attachment 6, Development of Coefficient for Other Than Normal Working Hours
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
| OPTION |
| JOC Non-PrePriced - OY1 |
FFP
JOC Non-PrePriced - OY1 Option Year 1 Coefficient The total Non-PrePriced line items allowable under this program SHALL NOT EXCEED 10% of the total contract value. The value inserted here is transferred from Attachment 7, Development of Coefficient for Non-PrePriced Line Items.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
| OPTION |
| JOC Normal Working Hours – OY2 |
FFP
JOC Normal Working Hours – OY2 Option Year 2 Coefficient Normal Working Hours are Monday through Friday, 7:30 a.m. to 4:30 p.m. local time (excluding Federal Holidays).
The value inserted here is transferred from Attachment 5, Development of Coefficient for Normal Working Hours.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
| OPTION |
| JOC Other Than Normal – OY2 |
FFP
JOC Other Than Normal – OY2 Option Year 2 Coefficient Other Than Normal Working Hours are anytime Monday through Friday, after 4:30 p.m. local time, on weekends, and/or Federal Holidays when work is required to be performed on an emergency basis, or at the Government's convenience to minimize the impact on ongoing military operations.
The value inserted here is transferred from Attachment 6, Development of Coefficient for Other Than Normal Working Hours.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
| OPTION |
| JOC Non-PrePriced – OY2 |
FFP
JOC Non-PrePriced – OY2 Option Year 2 Coefficient The total Non-PrePriced line items allowable under this program SHALL NOT EXCEED 10% of the total contract value. The value inserted here is transferred from Attachment 7, Development of Coefficient for Non-PrePriced Line Items.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
| OPTION |
| JOC Normal Working Hours - OY3 |
FFP
JOC Normal Working Hours - OY3 Option Year 3 Coefficient Normal Working Hours are Monday through Friday, 7:30 a.m. to 4:30 p.m. local time (excluding Federal Holidays).
The value inserted here is transferred from Attachment 5, Development of Coefficient for Normal Working Hours.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
| OPTION |
| JOC Other Than Normal - OY3 |
FFP
JOC Other Than Normal – OY3 Option Year 3 Coefficient Other Than Normal Working Hours are anytime Monday through Friday, after 4:30 p.m. local time, on weekends, and/or Federal Holidays when work is required to be performed on an emergency basis, or at the Government's convenience to minimize the impact on ongoing military operations.
The value inserted here is transferred from Attachment 6, Development of Coefficient for Other Than Normal Working Hours.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
| OPTION |
| JOC Non-PrePriced - OY3 |
FFP
JOC Non-PrePriced – OY3 Option Year 3 Coefficient The total Non-PrePriced line items allowable under this program SHALL NOT EXCEED 10% of the total contract value. The value inserted here is transferred from Attachment 7, Development of Coefficient for Non-PrePriced Line Items.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Job
| OPTION |
| JOC Normal Working Hours - OY4 |
FFP
JOC Normal Working Hours - OY4 Option Year 4 Coefficient Normal Working…