Solicitation W911RP-18-R-0023
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The U.S. Army Contracting Command - Pine Bluff Arsenal Contracting Off ice requests a proposal to provide construction and installation of an HX Mix Production Line at Building 31-630 at Pine Bluff Arsenal, White Hall, AR 71602.
All w ork is to be done in accordance w ith Technical Specification JMPB-TS-2018-ET-01 ("Statement of Work") and all referenced draw ings, attachments, exhibits and references therein. This Request for Proposal is issued as a 100% Small Business Set Aside. All contractors submitting a proposal must be registered and current in System for Aw ard Management (SAM).
In accordance w ith FAR 36.206, Disclosure of Magnitude of Construction Projects, the magnitude for this project is betw een $500,000.00 and $1,000,000.00.
A MANDATORY pre-construction site visit is scheduled to commence at 9:30 A.M. CST on 13 June, 2018, at the Plainview Gate Pass & ID Off ice, Pine Bluff Arsenal. E-Mail gareth.c.hyndman.civ@mail.mil to register. Please review FAR Clause 52.236-27 included herein for additional important information.
Wage Decision Number AR180036 - 01/05/2018 AR36 is applicable and attached.
Deadline for submission of Proposals is to be COB, 5 July 2018.
GARETH C. HYNDMAN, II 870-540-3014
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
07-Jun-2018
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______14 calendar days and complete it w ithin ________220 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________2 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________05 Jul 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
ARMY CONTRACTING COMMAND - ROCK ISLAND
PINE BLUFF ARSENAL CONTRACTING OFFICE
10-020 KABRICH CIRCLE, BLDG 17-120
ATTN: CCRC-AEP
PINE BLUFF AR 71602-9500
W911RP
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
04:30 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
(870) 540-4090FAX:TEL: (870) 540-3020 TEL: FAX:
W911RP18R0023 50
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W911RP18R0023
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
HX Production Facility (Bldg 31-630)
FFP
Design, fabrication, testing, installation, acceptance, and training to provide Pine Bluff Arsenal (PBA) with a refurbished HX mixing and canister pressing facility at Building 31-630. The work to be performed under technical specification JMPB- TS-2018-ET-01, dated January 2018, ("the Specification") consists of facility preparation, moving, installing, and restoring to operation the government furnished equipment and furnishing all other materials, equipment, supplies, labor and transportation to complete and make fully operational the production process within the facility. Work required by this contract shall be performed in strict accordance with specifications and drawings. Final acceptance will be based on the systems performance after installation at PBA and shall be evaluated on the acceptance criteria hereafter referenced. Operator and maintenance training shall be provided by the contractor for this system after acceptance. Project shall be completed 220 days after receiving Notice to Proceed. The unit price for this CLIN shall be calculated by totalling all of the sub-CLINs (0001AA-0001AE).
NET AMT
0001AA 1 Lot Demolition and Construction
FFP
Contractor shall provide FFP for tasks listed under paragraph 3.1.3 and 3.3.8 of the Specification for demolition and construction to Bldg 31-630.
FOB: Destination
PSC CD: Z2EC
0001AB Lot Refurbishment of GFE
CPFF
Contractor shall provide refurbishment of Government Furnished Equipment (GFE) listed under paragraph 3.1.4(A) of the Specification. US Government estimates that the cost to complete the refurbishment will not exceed $60,000.
Contractor to provide a fixed fee to perform this task.
PSC CD: J030
ESTIMATED COST
FIXED FEE
TOTAL EST COST + FEE
0001AC 1 Lot Contractor Furnished Equipment
FFP
Contractor shall provide the major components listed listed under paragraph 3.1.4(B) of the Specification as contractor furnished equipment. Title to this equipment will pass to the US Government upon acceptance.
PSC CD: 3693
0001AD 1 Lot Installation, Setup and Training
FFP
Contractor shall provide FFP for all labor, materials and equipment necessary for the design, installation, set-up and training for the HX Mix Facility Production Line in accordance with section 3.2 of the Specification.
PSC CD: N036
0001AE 1 Lot Contract Data Requirements List
FFP
Contractor shall provide FFP for seven (7) Contract Data Requirements as listed in the Specification, Appendix III.
PSC CD: L035
Section C - Descriptions and Specifications
EXECUTIVE SUMMARY
EXECUTIVE SUMMARY
1. The U.S. Army Contracting Command - Rock Island, Pine Bluff Arsenal Contracting Office requests proposals for the construction and installation od an HX Mix Production Line at Building 31-630 at Pine Bluff Arsenal, White Hall, AR 71602. All work is to be done in accordance with the Technical Specification JMPB-TS-2018-ET-01, dated January 2018, ("Statement of Work" or "SOW").
2. This Request for Proposal (RFP) is issued as a 100% Small Business Set Aside. It is anticipated that a single Firm Fixed Price (FFP) type contract will be awarded to the responsive, responsible offeror whose technically acceptable proposal represents the lowest total evaluated price.
3. Notice to potential offerors: In order to align with current requirements of DoD Federal Acquisition Regulation Supplemental (DFARS) 201.304 and Army Federal Acquisition Regulation Supplemental (AFARS) 5101.304, there has been a change to the format of ACC-RI soliciations (and resultant contracts). This notice is to inform you of that format change and to advise you to review the entire soliciation thoroughly.
4. The Government anticipates price competition, therefore, certified or other than certified cost data is not required to be submitted with the offerors' proposal. However, the Government reserves the right to request appropriate price and cost data in the event price competition does not exist.
5. Offerors are cautioned to ensure their proposals are fully complete, including all fill-ins. Any offeror submitting a proposal agrees by submission that their proposal and the prices contained therein will be valid for 60 days after receipt of proposals.
6. This soliciation is issued subject to availability of funds; therefore this soliciation is currently unfunded. The Government reserves the right to not fund any or all of the CLIN(s) listed in this soliciation, see FAR 52.232-18.
7. Offerors should note the provision at FAR 52.215-1, "Instructions to Offerors - Competitive Acquisition". The Government intends to award a contract resulting from this RFP without discussions with offerors (except clarficiations described in FAR 15.306(a)). Therefore, offerors initial proposals should contain the best terms. The Government does however, reserve the right to request clarifications or conduct discussions if determined necessary by the Contracting Officer.
8. The prevailing Davis-Bacon Act for wage determination will be incorporated into the resultant contract and will be in effect for the entire performance period of the resultant contract. The most recent wage determination can be found online at https://www.wdol.gov/dba.aspx or see included Davis Bacon Wage Determination.
9. Please note Local Information in Section H of the Solicitation. The contractor will be responsible for these requirements.
10. Contractor questions regarding solicitation and work contained in the Solictation, SOW, and all related documentation are due to the soliciation POC no later than ten (10) days prior to close of the date and time for submission of offers in order to assure that all Contractor questions can be answered and posted for all Contractors knowledge prior to solicitation closing.
11. Contractor proposal submission may be completed by drop off in person to the POC listed below located in the Pine Bluff Arsenal Contracting Office, Building 17-120, 10-020 Kabrich Circle, Pine Bluff Arsenal, White Hall, AR 71602-9500 or by certified or overnight mail.
12. A pre-construction site visit will be held for this project at 9:30 A.M. Central Standard Time on 13 June, 2018
Commencing at the Plainview Gate Pass & ID Office, Pine Bluff Arsenal, White Hall, AR 71602.
RESERVATIONS FOR THIS SITE VISIT ARE MANDATORY AND IT IS RECOMMENDED THAT THEY
ARE REQUESTED AT LEAST 24 HOURS IN ADVANCE OF THE SITE VISIT.
13. This executive summary is provided as an administrative convenience and is not intended to alter the terms and conditions of the soliciation in any way. Any inconsistencies between this executive summary and other solicitation provisions shall be resolved in favor of the other soliciation provisions.
14. The Government representative for the RFP is Gareth Hyndman, (870) 540-3014. Comments or questions should be directed in writing to him at gareth.c.hyndman.civ@mail.mil.
TECHNICAL SPECIFICATIONS
TECHNICAL SPECIFICATION JMPB-TS-2018-ET-01, dated January 2018, for HX PRODUCTION FACILITY 31-630NS, including all referenced drawings, exhibits and attachments are hereby incorporated by reference into this solicitation as the Statement of Work.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A N/A 0001AA Destination Government Destination Government 0001AB Destination Government Destination Government 0001AC Destination Government Destination Government 0001AD Destination Government Destination Government 0001AE Destination Government Destination Government
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
0001AA 220 dys. ANP 1 TRANS OFC M F PROPERTY OFC
(W41G26)
US ARMY, PINE BLUFF ARSENAL
CENTRAL SHIPPING RECEIVING PORT
(CSRP)
BLDG 53-990, 506TH STREET
PINE BLUFF AR 71602.9500
W41G26
0001AB 220 dys. ANP (SAME AS PREVIOUS LOCATION)
0001AC 220 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0001AD 220 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0001AE 220 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
Section H - Special Contract Requirements
LOCAL INFORMATION
SECURITY VETTING REQUIREMENTS
The Pine Bluff Arsenal (PBA) Vetting Program is being changed to comply with installation access requirements identified in AR 190-13, HSPD-12 and DTM 09-012. Access policy requires all unescorted persons entering DOD installations to have a valid purpose to enter, have their identity verified and vetted to determine the fitness of the individual requesting and/or requiring access to the installation, and be issued or in possession of an authorized and valid access credential. They also require local passes only be issued to non-DOD cardholder personnel who have successfully passed an NCIC check.
The Directorate of Law Enforcement and Security (D/LE&S) requires background checks to be conducted on all individuals 16 years of age or older who do not possess a valid DOD Identification (ID) credential (i.e. CAC, Military Id) prior to being granted access onto PBA. This change includes 100% of contractors, vendors, commercial carriers, visitors, Natural Resources customers, MWR customers and CYS customers.
The following criteria will prevent access to PBA: Violent Offense Conviction within the last ten (10) years, Felony or Misdemeanor Class A Conviction within the last five (5) years, Current Pending Charges, Active Warrant or Convicted Sex Offender. Habitual Offenders with three (3) or more criminal convictions may also be denied access at the mutual discretion of two Certified ACIC/NCIC Operators. In addition, the following criteria will prevent hunting on PBA: Felony Conviction, Domestic Violence Conviction, DUI/DWI Conviction within the last five (5) years or Active Order of Protection.
AMC-LEVEL PROTEST PROGRAM
If you have complaints about this procurement, it is preferable that you first attempt to resolve those concerns with the responsible contracting officer. However, you can also protest to Headquarters, AMC. The HQ, AMC-Level Protest Program is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forum, rather than filing a protest with the General Accounting Office or other external forum. Contract award or performance is suspended during the protest to the same extent, and within the same time periods, as if filed at the GAO. The AMC protest decision goal is to resolve protests within 20 working days from filing. To be timely, protests must be filed within the periods specified in FAR 33.103. If you want to file a protest under the AMC-Level Protest Program, the protest must request resolution under that program and be sent to the address below. All other agency-level protests should be sent to the contracting officer for resolution.
Headquarters U.S. Army Materiel Command Office of Command Counsel-Deputy Command Counsel 4400 Martin Road
RM: A6SE040.001
Redstone Arsenal, AL 35898-5000
Fax: (256) 450-8840 or e-mail: usarmy.redstone.usamc.mbx.protests@mail.mil Packages sent by FedEx or UPS should be addressed to:
Headquarters U.S. Army Materiel Command Office of Command Counsel-Deputy Command Counsel 4400 Martin Road
RM: A6SE040.001
Redstone Arsenal, AL 35898-5000 Fax: (256) 450-8840 or e-mail: usarmy.redstone.usamc.mbx.protests@mail.mil AMC-Level Protest Procedures are located on the Internet. If Internet access is not available, contact the contracting officer or HQ, AMC to obtain the AMC-Level Protest Procedures.
http://www.amc.army.mil/pa/COMMANDCOUNSEL.asp
OSHA STANDARDS
Contractor must comply with all applicable OSHA standards.
INSPECTION AND ACCEPTANCE
a. The work will be conducted under the general direction of the Contracting Officer and is subject to inspection by his appointed inspectors to insure strict compliance with the terms of the contract. No inspector is authorized to change any provision of the specifications without written authorization of the Contracting Officer, nor shall the presence or absence of an inspector relieve the contractor from any requirements of the contract.
b. The Contracting Officer shall designate individuals to act as the Contracting Officer’s Representative (COR) under any resultant contract. Such representative will be designated in writing by the Contracting Officer with a copy of designation to the contractor. The COR will represent the Contracting Officer in the technical phases of the work, but will not be authorized to change any of the terms and conditions of the contract.
c. The COR will act in a liaison capacity to coordinate activities between the contractor and the Government as required in the performance of work under the contract.
INSURANCE RQUIREMENTS
The following insurance is required as a minimum in accordance with the Federal Acquisition Regulation and the appropriate clause in Section I:
a. Legally Required Insurance: When certain laws apply, such as state laws governing workman's compensation and employer's liability coverage, etc., the contractor, prior to commencement of work, shall furnish the Contracting Officer a written statement that such laws have been complied with and that compliance will continue throughout the period of contract performance. Minimum coverage of $100,000.00 is required.
b. Comprehensive General Liability and Automobile Liability:
Per Property Each Person Occurrence Damage
Comprehensive None $500,000 None General Liability
Automobile Liability $200,000 $500,000 $20,000
DELIVERY OF MATERIALS
It is the responsibility of the contractor or subcontractor to inform their vendors or truck drivers of the prime contractor's name, contract number and work site. Pine Bluff Arsenal is a controlled access installation therefore, subcontractors, vendors, or delivery persons who do not possess the above information and other proper identification as required by the Security Office may be denied access to Pine Bluff Arsenal. Any delay caused by such denial will be at the contractor's expense and no time extensions for such delays will be allowed. Contractors will provide escorts for suppliers' trucks from the perimeter gates to job site when required.
NOTICE OF POSSIBLE DELAYS
During the time a contractor is working on the Arsenal he may, from time to time, be working in an area where munition test exercises are conducted. While it is not the Arsenal's policy to interfere with a contractor during these test exercises, delay may occur. These delays may involve contractor personnel being withdrawn from an area or being denied access for a period of time. The length of time and frequency of these delays will be held to a minimum. No claim shall be submitted for less than five (5) man-hours per month. Claims may be submitted under the Changes Clause of the contract.
BURIED CABLES AND LINES
The contractor shall submit a Pine Bluff Arsenal Request to Mark Utility Lines and submits the same to the Contracting Officer's Representative (COR) three (3) working days prior to commencing any digging on the Pine Bluff Arsenal. Blank forms will be issued at the Post Award Meeting. If the Contractor fails to provide notification, the Contractor shall be liable for any damages to any buried telephone cables or utility lines regardless of care exercised or drawings followed.
The Government shall not grant time extensions nor pay additional costs incurred because of delays, unless the Contractor has properly notified the Government one working day in advance of the desired digging date.
DISMISSALS
The Contracting Officer may require the contractor to suspend or dismiss from work any employee or employees whose retention is deemed to be not in the public interest, because of the misconduct of the employee or for reasons of security, subject, however, to appeal under the provisions of Articles entitled "Disputes" for reinstatement of such employees.
SUBMITTALS
Should the contractor desire to furnish the brand name and models set forth in the specification, submittals will not be required; however, a certification for the contractor will be required stating the brand name and model which will be used in the performance of this work. Contractors shall be required to furnish samples or descriptive literature on "or equal" products as set forth in the specifications.
SECURITY REQUIREMENTS
During the time that the contractor performs work on post, he is expected to be aware that Pine Bluff Arsenal is a controlled access installation. Specific security requirements as they apply to the project site will be noted during a post –award conference. The contractor will exercise care to prevent unauthorized intrusions by locking gates, closing and locking doors/windows, and performing similar actions. In the event that a breach of security occurs notwithstanding the contractor’s efforts to prevent it, he shall immediately notify the Pine Bluff Arsenal Security Police (540-3505), reporting the occurrence and explaining the nature of the violation.
UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT PERSONNEL
a. The contractor will not accept any instructions by any person employed by the U.S. Government or otherwise other than the Contracting Officer, or the designated Contracting Officer’s Representative (COR) acting within the limits of his authority. Contracting Officer’s Representative will be so designated in writing to the contractor and the scope of his authority will be set forth therein.
b. No information, other than that which may be contained in an authorized modification to this purchase instrument duly issued by the Contracting Officer, may be considered a valid obligation. Information received from any other person employed by the U.S. Government will not be considered grounds for deviation from any stipulation of this purchase instrument or referenced drawings and/or specifications.
INSTRUCTIONS FOR PAYMENT OF SUBCONTRACTORS
Offerors are advised that in accordance with regulations, prime contractors shall (if applicable) include on payment requests a certification that sub-contractors have been paid from previous payments and that payments will be paid to subcontractors from payments being requested. The preceding is applicable to procurement documents awarded, renewed or which have options exercised on or after April 1, 1989. Additionally, prime contractors shall make payment to their subcontractors (if performance is satisfactory) seven (7) days after the Government pays the prime.
Prime contractors are to pay interest to their subcontractors for late payments.
SAFETY REQUIREMENTS
The contractor will comply with the following factors:
a. Applicable portions of Department of Labor, Occupational Safety and Health Administration (OSHA)
Standards 29 CFR 1910 and 1926; etc.; Army Regulation (AR), Department of Army Pamphlets (DA PAM);
Pine Bluff Arsenal Regulations (PBAR); PBA Policy Letters; EM 385-1-1; General Safety Requirements (latest issue), whichever is the most stringent. The contractor shall be required to comply with any provisions of the Act/Manual pertaining to this operation. Any violation noted by the Contracting Officer or PBA Safety Officer must be corrected.
b. Where the work requires, the contractor will be required to furnish all personnel, equipment, marking, etc., necessary for the safe movement and flow of traffic at the job site as determined by the Contracting Officer.
c. Warning and Safety Signs – The Contractor shall install warning and safety signs at all strategic locations on the work site. Signs and barricades shall be constructed in accordance with OSHA standards.
d. Illumination – If night operations are carried on, the contractor will be required to furnish all plant, equipment, and labor necessary to insure adequate illumination. Prior to commencing night operations the contractor shall submit a plan to the Contracting Officer for approval showing the illumination layout he proposes to use.
Adequate illumination as used herein shall be construed as the minimum lighting required to provide safe working conditions for contractor and Government personnel wherever work on this contract is in progress.
There shall be sufficient light to permit the work to be performed in accordance with the plans and specifications and to permit complete inspection of all the work.
e. In certain specified areas, matches, lighters, or other flame producing devices will not be allowed. Smoking is absolutely prohibited in any of the restricted areas, buildings, or in cars and trucks except as authorized by the Contracting Officer.
f. Safety Briefing – The contractor shall allow for a 45 minute, mandatory, Safety briefing for all employees conducted at the Pine Bluff Arsenal Pass and ID office.
g. Notice of Required Seat Belt Use – As a means to increase safety, the Commander, Pine Bluff Arsenal, has established a policy that all occupants of a vehicle on the Pine Bluff Arsenal shall wear a seat belt. This policy extends to contractors and/or sub-contractors. Failure to use seat belts may result in the issuance of a citation or loss of driving privileges on the Pine Bluff Arsenal.
h. The contractor shall provide evidence that the company has a Safety & Occupational Health Plan.
i. The Contractor and Contracting Officer's Representative (COR) will document any hazardous work to be accomplished on the Hazardous Work Permit (Form PBA 387-7) in accordance with PBAR 385-31.
j. The General Contractor is responsible for assuring their sub-contractors comply with the safety items above.
MAGISTRATE SYSTEM
Contractors are hereby notified that in accordance with the United States Code, the Federal Magistrate System has been enacted at Pine Bluff Arsenal. Persons issued a citation on Pine Bluff Arsenal are subject to fines and may be required to appear before a Federal Magistrate in Little Rock, Arkansas.
ORDER AND SCHEDULING OF WORK
a. Unless otherwise expressly provided in the specifications, the contractor shall work only the normal working hours of Pine Bluff Arsenal, 7:00 a.m. to 4:30 p.m., Monday through Thursday and 7:00 a.m. to 3:30 p.m., every other Friday. However, contractor shall coordinate Friday work with the Contracting Officer or Contracting Officer’s Representative, on Government Holidays or days that are observed in lieu of Government holidays or other days that are declared non-work days by the commanding Officer of Pine Bluff Arsenal or official of higher headquarters. Deviations from this requirement must be requested in writing and be approved by the Contracting Officer prior to the proposed extra working hours or work days.
b. Government holidays are as follows:
New Year’s Day Independence Day Labor Day Thanksgiving Day Christmas Day Memorial Day Veteran’s Day Columbus Day Presidents’ Day Martin Luther King’s Birthday
When one of the above designated holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday by U.S.
Government agencies.
c. In the event the Contractor wishes to perform work outside the normal work hours, he shall submit his request through the technical representative to the Contracting Officer for approval. If such request is approved, the Contractor may be required to reimburse the Government for the cost of having an inspector at the work site.
INSURANCE LIABILITY
a. Workers' compensation and employer's liability. Contractors are required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statues, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so co-mingled with a contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 is required, except in states with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.
b. General Liability. Bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence is required.
c. Automobile Liability. Automobile liability insurance written on the comprehensive form of policy is required.
The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on the policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.
KEY PERSONNEL
The contractor shall notify the Contracting Officer prior to making any changes in key personnel. Key personnel are defined as follows:
a. Personnel identified in the proposal as key individuals to be assigned for participation in the performance of the contract;
b. personnel whose resumes were submitted with the proposal; or,
c. individuals which are designated as key personnel by agreement of the Government and the contractor during negotiations.
The contractor must demonstrate that the qualifications of prospective personnel are equal to or better than the qualifications of the personnel being replaced. Notwithstanding any of the foregoing provisions, key personnel shall be furnished unless the contractor has demonstrated to the satisfaction of the COR that the qualifications of the proposed substitute personnel are equal to or better than the qualifications of the personnel being replaced.
PAYMENT INSTRUCTIONS
Follow WAWF clause 252.232-7006 Wide Area Workflow Payment Instructions located in the contract.
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions NOV 2013 52.203-2 Certificate Of Independent Price Determination APR 1985 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-11 Certification And Disclosure Regarding Payments To
Influence Certain Federal Transactions
SEP 2007
52.203-12 Limitation On Payments To Influence Certain Federal Transactions
OCT 2010
52.203-13 Contractor Code of Business Ethics and Conduct OCT 2015 52.203-15 Whistleblower Protections Under the American Recovery and
Reinvestment Act of 2009
JUN 2010
52.203-16 (Dev) Preventing Personal Conflicts of Interest (APR 2018) (Deviation 2018-O0013)
APR 2018
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
APR 2014
52.203-18 Prohibition on Contracting With Entities That Require Certain Internal Confidentiality Agreements or Statements-- Representation
JAN 2017
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements
JAN 2017
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-7 System for Award Management OCT 2016 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2016
52.204-13 System for Award Management Maintenance OCT 2016 52.204-14 Service Contract Reporting Requirements OCT 2016 52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.204-21 Basic Safeguarding of Covered Contractor Information
Systems
JUN 2016
52.204-22 Alternative Line Item Proposal JAN 2017 52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.209-7 Information Regarding Responsibility Matters JUL 2013 52.209-9 Updates of Publicly Available Information Regarding
Responsibility Matters
JUL 2013
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.211-13 Time Extensions SEP 2000 52.215-2 Audit and Records--Negotiation OCT 2010 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.215-19 Notification of Ownership Changes OCT 1997
52.215-22 Limitations on Pass-Through Charges--Identification of Subcontract Effort
OCT 2009
52.215-23 Limitations on Pass-Through Charges OCT 2009 52.219-6 Notice Of Total Small Business Set-Aside NOV 2011 52.219-8 Utilization of Small Business Concerns NOV 2016 52.219-14 Limitations On Subcontracting JAN 2017 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards- Overtime
Compensation
MAY 2014
52.222-6 Construction Wage Rate Requirements MAY 2014 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records MAY 2014 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-22 Previous Contracts And Compliance Reports FEB 1999 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-35 Equal Opportunity for Veterans OCT 2015 52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-37 Employment Reports on Veterans FEB 2016 52.222-38 Compliance With Veterans' Employment Reporting
Requirements
FEB 2016
52.222-40 Notification of Employee Rights Under the National Labor Relations Act
DEC 2010
52.222-41 Service Contract Labor Standards MAY 2014 52.222-50 Combating Trafficking in Persons MAR 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.223-21 Foams JUN 2016 52.225-10 Notice of Buy American Requirement--Construction
Materials
MAY 2014
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.225-25 Prohibition on Contracting with Entities Engaging in Certain
Activities or Transactions Relating to Iran-- Representation and Certifications.
OCT 2015
52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014
52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-1 Payments APR 1984 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-17 Interest MAY 2014 52.232-18 Availability Of Funds APR 1984 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
52.233-1 Alt I Disputes (May 2014) - Alternate I DEC 1991 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.236-28 Preparation of Proposals--Construction OCT 1997 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.242-17 Government Delay Of Work APR 1984 52.243-4 Changes JUN 2007 52.243-6 Change Order Accounting APR 1984 52.244-5 Competition In Subcontracting DEC 1996 52.244-6 Subcontracts for Commercial Items NOV 2017 52.245-1 Government Property JAN 2017 52.245-9 Use And Charges APR 2012 52.246-4 Inspection Of Services--Fixed Price AUG 1996 52.246-12 Inspection of Construction AUG 1996 52.246-21 Alt I Warranty of Construction (Mar 1994) - Alternate I APR 1984 52.246-25 Limitation Of Liability--Services FEB 1997 52.248-3 Value Engineering-Construction OCT 2015 52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7003 Agency Office of the Inspector General DEC 2012 252.203-7004 Display of Hotline Posters OCT 2016 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
NOV 2011
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A System for Award Management Alternate A FEB 2014 252.204-7006 Billing Instructions OCT 2005 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
OCT 2016
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
MAY 2016
252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Country that is a State Sponsor of Terrorism
OCT 2015
252.211-7005 Substitutions for Military or Federal Specifications and Standards
NOV 2005
252.211-7007 Reporting of Government-Furnished Property AUG 2012 252.215-7008 Only One Offer OCT 2013 252.215-7012 Requirements for Submission of Proposals via Electronic
Media.
JAN 2018
252.222-7006 Restrictions on the Use of Mandatory Arbitration Agreements DEC 2010 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.225-7048 Export-Controlled Items JUN 2013 252.226-7001 Utilization of Indian Organizations and Indian-Owned
Economic Enterprises, and Native Hawaiian Small Business Concerns
SEP 2004
252.232-7003 Electronic Submission of Payment Requests and Receiving Reports
JUN 2012
252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.236-7007 Additive or Deductive Items DEC 1991 252.236-7009 Option for Supervision and Inspection Services DEC 1991 252.236-7013 Requirement for Competition Opportunity for American Steel
Producers, Fabricators, and Manufacturers
JUN 2013
252.243-7002 Requests for Equitable Adjustment DEC 2012 252.245-7002 Reporting Loss of Government Property DEC 2017 252.246-7003 Notification of Potential Safety Issues JUN 2013 252.246-7004 Safety of Facilities, Infrastructure, and Equipment for
Military Operations
OCT 2010
CLAUSES INCORPORATED BY FULL TEXT
52.203-14 DISPLAY OF HOTLINE POSTER(S) (OCT 2015)
(a) Definition.
United States, as used in this clause, means the 50 States, the District of Columbia, and outlying areas.
(b) Display of fraud hotline poster(s). Except as provided in paragraph (c)--
(1) During contract performance in the United States, the Contractor shall prominently display in common work areas within business segments performing work under this contract and at contract work sites--
(i) Any agency fraud hotline poster or Department of Homeland Security (DHS) fraud hotline poster identified in paragraph (b)(3) of this clause; and
(ii) Any DHS fraud hotline poster subsequently identified by the Contracting Officer.
(2) Additionally, if the Contractor maintains a company website as a method of providing information to employees, the Contractor shall display an electronic version of the poster(s) at the website.
(3) Any required posters may be obtained as follows:
Poster(s) Obtain from http://www.dodhotline.dodig.mil/Hotline/posters.cfm
(i) Appropriate agency name(s) and/or title of applicable Department of Homeland Security fraud hotline poster);
and
(ii) The website(s) or other contact information for obtaining the poster(s).)
(c) If the Contractor has implemented a business ethics and conduct awareness program, including a reporting mechanism, such as a hotline poster, then the Contractor need not display any agency fraud hotline posters as required in paragraph (b) of this clause, other than any required DHS posters.
(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in all subcontracts that exceed $5.5 million , except when the subcontract--
(1) Is for the acquisition of a commercial item; or
(2) Is performed entirely outside the United States.
(End of clause)
52.204-17 OWNERSHIP OR CONTROL OF OFFEROR (JUL 2016)
(a) Definitions. As used in this provision--
Commercial and Government Entity (CAGE) code means—
(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity;
or
(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code.
Highest-level owner means the entity that owns or controls an immediate owner of the offeror, or that owns or controls one or more entities that control an immediate owner of the offeror. No entity owns or exercises control of the highest level owner.
Immediate owner means an entity, other than the offeror, that has direct control of the offeror. Indicators of control include, but are not limited to, one or more of the following: Ownership or interlocking management, identity of interests among family members, shared facilities and equipment, and the common use of employees.
(b) The Offeror represents that it [ ___ ] has or [ ___ ] does not have an immediate owner. If the Offeror has more than one immediate owner (such as a joint venture), then the Offeror shall respond to paragraph (c) and if applicable, paragraph (d) of this provision for each participant in the joint venture.
(c) If the Offeror indicates ``has'' in paragraph (b) of this provision, enter the following information:
Immediate owner CAGE code:
Immediate owner legal name: ___
(Do not use a ``doing business as'' name)
Is the immediate owner owned or controlled by another entity?:
[ ___ ] Yes or [ ___ ] No.
(d) If the Offeror indicates ``yes'' in paragraph (c) of this provision, indicating that the immediate owner is owned or controlled by another entity, then enter the following information:
Highest-level owner CAGE code:
Highest-level owner legal name:
(Do not use a ``doing business as'' name)
(End of provision)
52.204-20 Predecessor of Offeror (JUL 2016)
Commercial and Government Entity (CAGE) code means--
(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity;
or
(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code.
Predecessor means an entity that is replaced by a successor and includes any predecessors of the predecessor.
Successor means an entity that has replaced a predecessor by acquiring the assets and carrying out the affairs of the predecessor under a new name (often through acquisition or merger). The term “successor” does not include new offices/divisions of the same company or a company that only changes its name. The extent of the responsibility of the successor for the liabilities of the predecessor may vary, depending on State law and specific circumstances.
(b) The Offeror represents that it [____] is or [____] is not a successor to a predecessor that held a Federal contract or grant within the last three years.
(c) If the Offeror has indicated “is” in paragraph (b) of this provision, enter the following information for all predecessors that held a Federal contract or grant within the last three years (if more than one predecessor, list in reverse chronological order):
Predecessor CAGE code: ____ (or mark “Unknown”).
Predecessor legal name: ____.
(Do not use a “doing business as” name).
52.209-2 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS--
REPRESENTATION (NOV 2015)
(a) Definitions. Inverted domestic corporation and subsidiary have the meaning given in the clause of this contract entitled Prohibition on Contracting with Inverted Domestic Corporations (52.209-10).
(b) Government agencies are not permitted to use appropriated (or otherwise made available) funds for contracts with either an inverted domestic corporation, or a subsidiary of an inverted domestic corporation, unless the exception at 9.108-2(b) applies or the requirement is waived in accordance with the procedures at 9.108-4.
(c) Representation. The Offeror represents that--
(1) It [ ___ ] is, [ ___ ] is not an inverted domestic corporation; and
(2) It [ ___ ] is, [ ___ ] is not a subsidiary of an inverted domestic corporation.
52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS (OCT 2015)
(a)(1) The Offeror certifies, to the best of its knowledge and belief, that-
(i) The Offeror and/or any of its Principals-
(A) Are ( ) are not ( ) presently debarred, suspended, proposed for debarment, or declared ineligible for the award of contracts by any Federal agency;
(B) Have ( ) have not ( ), within a three-year period preceding this offer, been convicted of or had a civil judgment rendered against them for: commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State, or local) contract or subcontract; violation of Federal or State antitrust statutes relating to the submission of offers; or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, tax evasion, violating Federal criminal tax laws, or receiving stolen property (if offeror checks “have”, the offeror shall also see 52.209-7, if included in this solicitation); and
(C) Are ( ) are not ( ) presently indicted…