Questions and Answers PT 2.xlsx

XLSX spreadsheet 10 KB Posted

Attached to
Monument Sign - Natick Soldiers Systems Center
Solicitation number
W911QY-26-R-MONU
Issued by

About this file

This is a Questions and Answers document that addresses contractor inquiries regarding solicitation W911QY-26-R-MONU for a monument sign project at Natick Soldiers Systems Center. The Q&A clarifies key requirements including that no formal bid document is required for submission, but bid bonds, payment bonds, and performance bonds are mandatory (SF 24, 25, and 25a). The sign is an externally illuminated LED design that does not require building or electrical permits, though it must connect to an existing electrical circuit and timer in the housing area. The government is offering two site visit opportunities on 07/28/2026 and 07/29/2026 at 0930, requiring advance email confirmation, and will not disclose the estimated project cost per regulation.

This Q&A document serves as an amendment attachment providing clarification on frequently asked questions from potential offerors prior to the 08/07/2026 proposal submission deadline. The responses address technical specifications, bonding requirements, permitting, site access, and electrical connections, supporting contractors in preparing compliant proposals for this small business set-aside contract involving sign removal, construction, installation, and warranty of the new monument sign structure.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionsAnswers
Is there a formal solicitation bid document to fill out?No, there is no formal solicitation document to fill out.
Is a bid bond required?Yes, a bid bond, a payment bond, and a performance bond will all be required. SF 24, 25, and 25a have been attached to this amended solicitation. FAR clauses 52.228-1 and 52.228-15 are being incorporated into this solicitation.
Is this an internally illuminated LED sign?No, this will be an externally illuminated sign. Please refer to Page 2 paragraph "Electrical" of the SOW.
Is there an electrical permit required?A building or electrical permit is not required.
Are site visits available?The government is offering two separate site visits at this time. 07/28/2026 @0930 and 07/29/2026 @0930. Please email ahead of time to confirm the visit and any further access requirements.
Is there an EC requirement?If referring to Electrical circuit (EC), the answer is yes. To connect the exterior light to the electrical circuit and timer located in the housing area.
Does the government have an estimated cost for this project?Per regulation we cannot give out the governments estimated cost.