Questions_and_Answers_Solicitation_W911QX-16-T-0004.docx
DOCX document 12 KB Posted
- Solicitation number
- W911QX-16-T-0004
About this file
Questions and answers for W911QX-16-T-0004
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A07_-_Solicitation_(Amendments).docx | DOCX document | |
| A07_-_Solicitation_Q As.xlsx | XLSX spreadsheet | |
| A01_-_Salient_Characteristics.doc | DOC document | |
| A07_-_Executive_Summary_Solicitation.docx | DOCX document | |
| A07_-_Solicitation_(Amendments).docx | DOCX document | |
| A01_-_DD1423.doc | DOC document | |
| A01_-_Salient_Characteristics.doc | DOC document | |
| A07_-_Evaluation_Criteria_(LPTA).doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers Regarding Solicitation W911QX-16-T-0004
Question 1: Paragraph 5: The supply pressure given for different gases, like argon and carbon gas, is given as 30 psi. Is this psig (gauge pressure) or psia? (absolute pressure)?
Answer: This is psig.
Question 2: Paragraph 13: A reference is given to "input lines as detailed in C.1.5". To which document is this reference made?
Answer: C.1.5 was changed to paragraph 5.
Question 3: CLIN 0004 Option: Emergency power (UPS). Is the intention that the complete system, including the heating system, should be supplied during a powerfailure?
Answer: It is the intention that the UPS powers the control system so that it can return to a safe state. It is not the intention to power the heating system.