This document summarizes a draft request for proposal for an Army Modernization Priorities Multiple Award Indefinite Delivery Indefinite Quantity contract. The Army seeks proposals for research and development services in support of modernization priorities across multiple technical areas, with an emphasis on mission overmatch capabilities. Offerors should request a copy of the performance work statement by email no later than a specified date. An industry day virtual meeting will be held on March 17, 2022 to address questions; requests for access are due by March 10 with attendee details. The anticipated contract value is $800-900 million awarded to 6-9 contractors. Research and development task orders will be cost-plus-fixed-fee or firm-fixed price. Evaluation factors include technical approach, management, past performance, small business participation, and cost.

View the file

Other files for this federal contract opportunity

Other files attached to Army Modernization Priorities (AMP) MAC IDIQ, newest first.
File Type Posted
AMP Industry Day Capabilities Chart.pdf PDF
AMP Question and Answer.pdf PDF
AMP Industry Day Technical Slides.pdf PDF
W911NF-22-R-0001 DRAFT RFP.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Army Modernization Priorities (AMP)

Industry Day

UNCLASSIFIED

Niko Georgakopoulos Chris Justice

Contracting Officer 17 March 2022

Welcome/Administrative Remarks/Rules of Engagement

History of the Requirement

Draft RFP

Small Business Subcontracting and Participation Plans

Vision and Mission Requirement/Technical Areas

Expected length of briefing: 3hrs

2ACC-APG

UNCLASSIFIED

AGENDA

Administrative Remarks

3ACC-APG

• Introduction of Government Representatives

• Address CUI and proposal submission (will be specifically identified in final RFP release)

• All attachments will be released with final RFP – PLEASE

READ INSTRUCTIONS IN FINAL RFP REGARDING

ACCESS TO THE PWS

• NOTE: The final solicitation, when posted to betaSAM, supersedes any information discussed during this Industry Day. Proposers should read the final solicitation when posted.

Rules of Engagement

4ACC-APG

5ACC-APG

• Government Presenters Niko Georgakopoulos – Contracting Officer, ACC-APG-

RTP Div, RTP, NC Chris Justice – Contracting Officer, ACC-APG-RTP Div, RTP, NC

Mitch Wathen – Electrical Engineer, ARL Sensors and

Electron Devices Directorate (SEDD), Adelphi, MD Steven Murrill – Electronics Engineer, ARL Sensors and

Electron Devices Directorate (SEDD), Adelphi, MD David Christ/Darryl Seegars/Anne Carman - Small

Business Programs Army DEVCOM-- RTP, NC

• 15 minute breaks in between each presentation

6ACC-APG

• NOTE: The final RFP, when posted to betaSAM, supersedes any information discussed during this Industry Day. Proposers should read the final solicitation when posted.

• Type questions into the “Live event Q&A” and a moderator will review and document questions.

• Depending on timing, the Government will attempt to answer as many questions as possible during the industry day

Industry Representation

7ACC-APG

• The Government has documented a list of interested vendors who applied for the Industry Day, with a total of roughly 180 vendors.

• A subsequent request has been made to all vendors who registered for the industry day requesting information such as business size status, CAGE code, capabilities with regards to the PWS, and interest in being a prime or subcontractor looking to team up with other vendors.

• With approval to release this information from vendors, a list will be posted to the Industry Day announcement in betaSAM.

Historical Information

8ACC-APG

Past and Present

9ACC-APG

• ARL is currently carrying out similar actions under the AEWD Program (MAC IDIQ), however there are differences in the scope of the AMP IDIQ Requirement.

• The technical brief will discuss in more detail the differences between the two requirements and the types of task orders expected under the AMP IDIQ.

• For informational purposes, the AEWD MAC IDIQ has issued 74 task order requests over the past 6+ years.

This may not be an accurate depiction of the AMP IDIQ in the future.

Future

10ACC-APG

Name of Contractor IDIQ Ceiling

Army Modernization Priorities (AMP) MAC IDIQ

Anticipated 6-9

Contractors

TBD

$800M- $900M (At

Award)

Vision & Mission Requirement/Technical

Areas

11ACC-APG

Draft RFP Highlights

12ACC-APG

DRFP Highlights

• NAICS Code: 541 – Professional, Scientific, and Technical Services, 541715– Research and Development in the Physical, Engineering, and Life Sciences (except Biotechnology)

• While the NAICS code associated with task orders will also be 541715, the specific PSC code associated with individual task orders may span across different R&D and service PCS codes.

13ACC-APG

Draft TFP Highlights

14ACC-APG

• Contract Type: $800-$900M Multiple Award (MA) Indefinite Delivery Indefinite Quantity (IDIQ) CPFF and FFP Task Orders (TO)

• Fixed Fee on CPFF will be negotiated at TO level

• Profit on FFP will be negotiated at the TO level

• Subcontractor Fee limited to 5% for small business subcontractors and 3% for large business subcontractors

• NO FEE on equipment & travel costs

• Several questions/comments were received regarding this. That feedback will be considered with the intent of making fee restrictions more transparent in the final RFP.

Section B Highlights

15ACC-APG

Section B Highlights

16ACC-APG

• CLIN Structure:

CLIN 0001: R&D performed on a CPFF basis CLIN 0002: R&D performed on a FFP basis CLIN 0003: Service Contract Reporting (SCR) CLIN 0004: Contract Data Requirements List (CDRL) NSP

• All task orders will be issued by ACC-APG-RTP Contracting Division ONLY

Section C Highlights

17ACC-APG

Section C – PWS Highlights

18ACC-APG

• Process for receiving the PWS will be streamlined and timelines included in the final RFP release. Vendors are still encouraged to request the final PWS even if they have received a previous version, and the contracting office will work with the requiring activity to ensure all vendors receive the PWS at the same time and timely enough to adequately prepare proposals.

Section H Highlights

19ACC-APG

Section H – Highlights TOR Process

20ACC-APG

• Ordering Process

• The Government will conduct market research as part of the task order process to identify small business capabilities to perform task orders. The Government also anticipates notifying IDIQ holders of potential upcoming Task Order Requests (TOR) when possible.

• Once TOR is released, the Government anticipates a 30 day response time for proposals, but this is subject to individual requirements.

• TORs will include proposal instructions, PWS, evaluation criteria, and any other applicable attachments/information needed for task order proposal preparation.

Section H – Highlights On/Off Ramps

21ACC-APG

• Numerous questions were received in response to the Draft RFP regarding On/Off Ramping for the AMP program.

• Acquisition planning is still ongoing and industry feedback provided in response to the Draft RFP will be considered in final acquisition planning and final RFP language.

Section J Highlights

22ACC-APG

Section J - List of Documents, Exhibits and Other Attachments

23ACC-APG

• The Government does not anticipate using a sample task or TOR 1 associated with the final RFP

• All applicable attachments will be provided once the final RFP is released in betaSAM

Sections L & M Highlights

24ACC-APG

Highlights

25ACC-APG

• The PWS describes the Government’s requirement;

Section L outlines the proposal submission instructions;

Section M outlines the evaluation and selection process

• Make sure to read each of the sections in detail, as well as the entirety of the RFP, as you prepare your proposals

• There will be a question and answer period during the open RFP time, during which the Government will accept questions and post responses to betaSAM.

Basis For Award

26ACC-APG

Awards will be made based on the best overall value proposals that are determined to be the most beneficial to the Government, with appropriate consideration given to the five (5) evaluation factors:

• Technical,

• Management,

• Past Performance,

• Small Business Participation,

• Cost.

Basis For Award

27ACC-APG

• 6 to 9 Contract Awards are anticipated as a result of the Final RFP (but reserves the right to award more or less)

• It is the Government’s objective to maximize practicable opportunities for small businesses

• The Government intends to reserve 2 or more of the Awards exclusively for Small Businesses

• Market Research on going May adjust number of Small and Large Business Awards

Two Phase Process

28ACC-APG

Phase I - Pre-Evaluation Screening Compliance

Phase II - Evaluation of Volumes 1-5

Phase I-Pre-Evaluation Screening Compliance

29ACC-APG

Phase II - Competitive Range Evaluation

30ACC-APG

As set forth in FAR 52.215-1 (f)(4), the Government intends to award without discussions, except clarifications as described in FAR 15.306(a), Clarifications and award without discussions.

However, the Government reserves the right to conduct discussions if the Source Selection Authority later determines them to be necessary. A competitive range will be established in the event that discussions are determined to be necessary.

Phase II – Evaluation of Volume 1-5 continued

31ACC-APG

Volume I: Technical

Volume II: Program Management

Volume III: Past Performance

Volume IV: Small Business Participation

Volume V: Cost

Phase II – Evaluation of Volumes 1

32ACC-APG

Volume I: Technical – Aspects of the technical evaluation include:

(a) Capability to provide, quick reaction, wide-ranging specialized services

(b) Capability to provide specialized services relevant to MDO overmatch

(c) Demonstrated capabilities in required Mission Areas

(d) Demonstrated capabilities in required Technical Areas

NOTE: THE GOVERNMENT DOES NOT INTEND TO BREAK DOWN

FACTOR ONE INTO SUBFACTORS. THE EVALUATION APPROACH

WILL BE CLEARLY ARTICULATED IN THE FINAL RFP RELEASE.

REVIEW THE FINAL RFP FOR SPECIFIC PROPOSAL SUBMISSION

INSTRUCTIONS AND EVALUATION CRITERIA.

Phase II Volume II – Program Management

33ACC-APG

The Management Approach Factor will be evaluated to determine if the Offeror as an entity (Prime contractor, joint venture, teaming partners and all proposed major subcontractors) clearly meets the requirements as described in Section L for the following components; Management Plan Narrative, Key Personnel, Personnel Reliability Program, Security Clearance, and Telecommuting Plan.

REVIEW THE FINAL RFP FOR SPECIFIC PROPOSAL

SUBMISSION INSTRUCTIONS AND EVALUATION

CRITERIA.

Phase II Volume III – Past Performance

34ACC-APG

• Each Offeror’s past performance will be reviewed to determine relevancy and confidence assessment.

• Offerors shall provide three (3) contracts that are currently active or that have been physically completed in the last twenty-four (24) months that represent relevant experience in relation to the PWS, as well as those that most closely resemble the magnitude and contract type of this requirement.

At least two of the examples shall be from the prime contractor offeror for this requirement.

Continued

35ACC-APG

36ACC-APG

Phase II Volume IV – Small Business Participation

• The extent of Small Business Participation will be evaluated for Small Business and other than Small Businesses.

• All Offerors (both U.S. small business and other than U.S.

small businesses) shall submit a Small Business Participation Commitment Document Worksheet with their proposal as a separate document (xxxxSBPCDxxxx.xlsx) in order to identify the extent to which U.S. small businesses will participate in the performance of the proposed acquisition relative to the Government's small business objectives. Offerors are required to utilize and complete the proposal format depicted in the RFP Attachment 000X - Small Business Participation Commitment Document Worksheet.

ACC-APG 37

• The Offeror’s proposed Small Business Participation Commitment Document Worksheet will be incorporated as an attachment in the awarded contract to reflect the contract’s minimum contractual requirements in terms of Small Business Participation.

• It is the Government’s expectation that the Offeror will meet or exceed at least 95% of the proposed level of small business participation in all categories. Failure to do so may result in negative Contractor Performance Assessment Reporting System ratings and/or contract default procedures.

ACC-APG 38

39ACC-APG

Phase II Volume V – Cost

• The resulting award will be an Indefinite Delivery Indefinite Quantity (IDIQ) contract using Cost Plus Fixed Fee (CPFF) and Firm Fixed Price (FFP) Task orders. Cost realism and cost reasonableness in accordance with FAR 15.404-1 will be utilized in the evaluation of Cost Reimbursable efforts.

• The total evaluated cost to be used in the award determination (subject to cost realism adjustments) will be the total identified in the offerors xxxx COST MMDDYY.xls file. The objective of the proposal analysis is to ensure all proposed costs are fair, reasonable, and realistic.

• The Government noted numerous questions received from industry as a result of the Draft RFP and will take those considerations into account for development of the final RFP to ensure transparency.

ACC-APG 40

Section M Basis For Award

41ACC-APG

• Formal Source Selection Procedures will be utilized IAW FAR 15.3, Source Selection, as supplemented by the

DFARS & AFARS

• Best Value Evaluation Factors (Trade-Off Process)

• The Government will rely on the criteria in Section M for evaluation purposes, along with the instructions in Section L and the PWS.

Q&As on Draft RFP

42ACC-APG

• The following slides will address some of the common questions received from industry. The Government as documented and will take into account ALL questions and comments received for consideration in the final RFP.

43ACC-APG

Q: Can the Government provide the attachments listed in the Draft RFP?

A: The PWS has been provided to all parties who requested it. Other Attachments/Exhibits are not included as part of the Draft RFP but will be included in the final RFP release.

Q: Please confirm Total Price Evaluated will be CPFF labor only. (p 60-61, L.2).

A: Per the Draft RFP, the Government anticipates evaluating total cost of 1 FTE for each of the labor positions identified, as well as indirect rates and fee on a CPFF basis. This will be clarified in the final RFP.

44ACC-APG

Q: 2nd to last sentence in Paragraph 8 states: Proposals shall not contain any classified data or information. Question: The PWS is classified as CUI and our response will likely be CUI. Does CUI fall into the category of "classified data"? (p. 51)

A: CUI does not fall into the category of “classified data”. However, the submission process and protection of CUI will be clarified in final RFP Release.

Q: Is it the government's intent when referring to "Prime Contractor" in the RFP to limit competition on this contract to only those potential prime offers who, alone, believe they can do the entire PWS, or, is the intent to allow for maximum competition by defining "Prime Contractor" to include the offerer's comprehensive team? (Background)

A: Per the draft RFP, evaluation of capability will consider the ability of the entity (Prime contractor, joint venture, teaming partners and all proposed major subcontractors). This will be more clearly defined further in the release of the final

RFP.

45ACC-APG

Q: Is the customer looking for Prime companies who can develop solutions against the scope of work, or for a Program Management Office to act as a clearinghouse to manage the letting of task orders to a consortium of subcontractors?

A: The Government is not looking for a Program Management Office to let task orders.

Please review the RFP for details regarding expected capabilities of Prime Contractors and their proposed teams/subcontractors.

Q: Draft RFP mentions the first task order will be issued concurrently with contract award – what is the scope of that task order? (Para. G.4)

A: The Government anticipates awarding a minimum required amount to all awardees as a first task order. The Government anticipates this being a $2500 task order to cover kickoff meetings and subsequent deliverables. This will be detailed in the first task order issued to each awardee. Unless otherwise noted in the final RFP, the Government is not expecting proposals to address a specific Task Order requirement.

46ACC-APG

Q: If an IDIQ awardee has multiple businesses with unique CAGE codes, does the Government intend to award task orders directly to the performing business, or only to the CAGE code that received the IDIQ? We recommend keeping open the option of issuing a task order award to any business unit within a corporation. This promotes efficiency and keeping the best team directly supporting the task order.

A: The Government can only award task orders to the unique entity/CAGE code that received the overall IDIQ award.

Q: The stated intent of the IDIQ includes providing ‘…a quick-reaction contracting vehicle…’ What is the anticipated PALT for TOR under AMP?

A: As a general practice, the Government anticipates allowing 30 days for task order proposal submission, and an additional 30-60 days for award. This is subject to variation depending on the individual task order.

47ACC-APG

Q: The government discusses the relevant weighting of each factor. How will the government assess each individual element within a given factor? For example, will all four elements under the technical factor be weighted equally?

A97: The Government does not intend to break down Factor One into subfactors.

The evaluation approach will be clearly articulated in the final RFP release.

Q: In the draft RFP, you state that the Government will only accept one (1) proposal from each Corporation. Do you legally delineate a “Corporation” by the organization’s CAGE code or DUNS number, or by some other method?

A: The Government anticipates only allowing one proposal per company, regardless of the number of individual entities/CAGE codes associated with that company. It will be up to the company to decide which specific entity is best fit to submit the proposal as the Prime Contractor, even if other entities within that company may receive work as subcontractors under task orders. This will be considered and made more transparent in the final RFP release.

48ACC-APG

Q: What should we expect regarding when the first task order(s) arriving after awarding IDIQ contracts? For example, should we anticipate some task orders arriving concurrently with IDIQ award? Can you say if task orders will issue on a regular or irregular timing?

A: The Government anticipates awarding a minimum required amount to all awardees as a first task order. The Government anticipates this being a $2500 task order to cover kickoff meetings and subsequent deliverables. Additionally, the schedule of potential task orders not known. TORs will be issued as requirements are known based on the requiring activities’ needs.

Q&As on DRFP

49ACC-APG

Q: Does the unclear statement regarding offerers falling within 5% of their proposed level of small business participation possibly resulting in a poor CPARS rating mean that offerers are to exceed their small business participation goals by greater than 5% or risk receiving a poor CPARS? (Vol. IV Small Bus.)

A: No. This statement means that the awardee must meet at least 95% of their proposed level of small business participation in each SB category. For example, if the offeror proposed 5% in the WOSB category then they must achieve at least 4.75%. In this example if the offeror does not achieve 4.75% the government will consider in accordance with consider appropriate actions including but not limited to appropriate adjectival ratings in CPARS annual reports, cure notices or other corrective actions.

Q: At what level (contract or TO) will SB utilization/participation goals be enforced?

A: Base contract (IDIQ) level.

Q: H.13 (1): SB Participation Goal is 15% of total contract value, but “Target/Goal” is “90% of SB participation.” Please clarify.

A: The Government will not consider offloading as a remedy to underperformance in Small Business Participation. Rather underperformance will be appropriately annotated in CPARS and as appropriate liquidated damages may be considered.

However, the government will consider offloading for Small Participation reporting.

The RFP will be revised accordingly

Q: Small Business Participation Commitment Document Worksheet was not attached Where is the worksheet?

A: The Government will attach it with the final RFP; it was missing in error. It will be added

Q: GENERAL INSTRUCTIONS 2. INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS When will the government evaluate the contractor’s SB participation? Will compliance be evaluated at the end of the contract?

A85: Small business participation will be evaluated at the conclusion of the base 5 year period and each subsequent option period for the base contract (IDIQ). The Government will track compliance semi-annually (CDRL will be attached to final RFP with semi-annual due dates; it was missing in error). If an offeror is failing to meet at least 95% of 1 or more of their SB category’s proposed level of small business participation at the conclusion of the base 5-year period and/or subsequent option periods, the Government will consider negative CPARS ratings and/or contract default procedures. Moreover, if an offeror is failing to meet at least 95% of one or more of their SB and socio-economic categories, the government reserves the right to not exercise option periods without acceptable justification as considered by the government.

15 Minute Break

52ACC-APG

Slide Number 1
AGENDA
Administrative Remarks
Rules of Engagement
Rules of Engagement
Rules of Engagement
Industry Representation
Historical Information
Past and Present
Future
Vision & Mission Requirement/Technical

Areas

Draft RFP Highlights
Slide Number 13
Draft TFP Highlights
Section B Highlights
Section B Highlights
Section C Highlights
Section C – PWS Highlights
Section H Highlights
Section H – Highlights TOR Process
Section H – Highlights On/Off Ramps
Section J Highlights
Section J - List of Documents, Exhibits and Other Attachments
Sections L & M Highlights
Highlights
Basis For Award
Basis For Award
Slide Number 28
Phase I-Pre-Evaluation Screening Compliance
Phase II - Competitive Range Evaluation
Phase II – Evaluation of Volume 1-5 continued
Phase II – Evaluation of Volumes 1
Phase II Volume II – Program Management
Phase II Volume III – Past Performance
Phase II Volume III – Past Performance Continued
Phase II Volume III – Past Performance Continued
Phase II Volume IV – Small Business Participation
Phase II Volume IV – Small Business Participation Continued
Phase II Volume IV – Small Business Participation Continued
Phase II Volume V – Cost
Section M Basis For Award
Q&As on Draft RFP
Q&As on Draft RFP
Q&As on Draft RFP
Q&As on Draft RFP
Q&As on Draft RFP
Q&As on Draft RFP
Q&As on Draft RFP
Q&As on DRFP
Q&As on DRFP
Q&As on DRFP
15 Minute Break

File details come from the government source that posted it. Updated .