W911NF-16-R-0007 Amendment 5 Questions and Answers
Q1. In accordance with amendment 004, do companies that have submitted a proposal on the 26th of September need to resubmit?
A1. An Offeror who has submitted a proposal does not need to resubmit, but may choose to do so if need be.
Q2. Can a company that has already submitted a proposal on the 26th of September only submit volume 5 and the new SF 33; or is an entire package required to be resubmitted?
A2. If an Offeror has previously submitted a proposal and wishes to change Volume 5, only Volume 5 and the SF33 need to be resubmitted.
Q3. In light of amendment 004, can anyone submit a proposal or is this amendment only for those that have already met the previous deadlines?
A3. Amendment 4 extended the proposal due date allowing anyone to submit a proposal.
Q4. The differences between amendment 002 and 004 indicate that past performance can be submitted from a subcontractor – is that correct?
A4. Yes, In Section L.2.5.1 Past Performance information may include; PP as Prime Contractor, Subcontractor, and/or as an Established Joint Venture Agreement.