RFP_W911N2-19-R-0011.pdf

PDF 497 KB Posted

Attached to
LIGHTNING PROTECTION SYSTEM (LPS) SERVICE
Solicitation number
W911N2-19-R-0011
Issued by

About this file

Request for Proposal (RFP) W911N2-19-R-0011

View the file

Other files

File Type Posted
Amendment__2_W911N2-19-R-0011.pdf PDF
Amendment__1_W911N2-19-R-0011.pdf PDF
LPS_PWS_W911N2-19-R-0011.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W911N219R0011 06-Jun-2019

b. TELEPHONE NUMBER

717-267-8938

8. OFFER DUE DATE/LOCAL TIME

04:00 PM 20 Jun 2019

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA X ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W911N29. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

KEVIN DUFFY

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

SEE SCHEDULE

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

LETTERKENNY ARMY DEPOT

LETTERKENNY CONTRACTING OFFICE - ACC

1 OVERCASH AVENUE, ATTN: CCAM-ALK, BLDG 2S

CHAMBERSBURG PA 17201-4150

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE W25G1R 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

LETTERKENNY MUNITIONS CENTER

MONICA R DEAN

BLDG 3315

1 OVERCASH AVE

CHAMBERSBURG PA 17201-4150

TEL: 717.267.9577 FAX:

717-2679834FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$15,000,000

NAICS:

238290

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF54

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W911N219R0011

Section SF 1449 - CONTINUATION SHEET

NOTES

1. System for Award Management (SAM): In accordance with FAR 4.1102, Offerors must be registered in the SAM database in order to be eligible for contract award. No award will be made to an Offeror not registered.

Registration can be accomplished at https://www.sam.gov/portal/public/SAM/ . Registration in this database must be kept current.

2. Annual Representations and Certifications: In accordance with FAR 4.1201, Offerors shall complete electronic annual representations and certifications within SAM as part of required registration. Registration in this database must be kept current and can be accessed at https://www.sam.gov/portal/public/SAM/.

3. Questions: Questions regarding this solicitation shall be submitted to the Contracting Officer, in writing, at least 10 calendar days prior to the closing date. Questions submitted after this time will be answered at the discretion of the Contracting Officer. The POC for this action is Kevin Duffy, kevin.a.duffy4.civ@mail.mil.

4. Award without Discussions: The Government intends to award without discussions; therefore Offerors should submit their best prices in their initial offer. If FAR Provision 52.212-2, Evaluation-Commercial Items, is included, Offerors must submit all information requested therein in order for the Government to determine technical acceptability.

5. Amendments: The Offeror shall submit to the Contracting Officer signed copies of all amendments issued to this solicitation. Failure to comply may cause your proposal to be rejected.

6. Payment: Payment for this action will be made by Electronic Funds Transfer (EFT) through the Defense Finance and Accounting Services (DFAS) utilizing Wide Area Work Flow (WAWF). See 252.232-7006 for more information.

7. Period for Acceptance of Offers. The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers.

8. Type of Contract: The type of contract resulting from this solicitation is specified in FAR Provision 52.216-1, Hybrid Firm Fixed Price, Time & Materials.

9. Proposals: Proposals shall be signed by an authorized individual in accordance with FAR 4.102, Contractor’s Signature. Failure to comply may cause your proposal to be rejected. Offerors should mark each page of their proposal as "Proprietary Information" if they want it treated as Proprietary Information under the Procurement Integrity Act.

10. Set- Aside: The proposed contract is 100% set-aside for small business concerns.

11. Contact Information : A Contracting Officer's Representative (COR) will be appointed at the time of award.

The successful Offeror will be furnished the COR name and contact information at the time of contract award.

12. Wage Determination: No.: 2015-4253 Revision No.: 10; dated 05/06/2019 and is hereby incorporated. Wage Determination can be viewed at http://www.wdol.gov.

13. Insurance (Fixed Price Contract). Pursuant to the requirements of FAR clause 52.228-5 Insurance-Work on a Government Installation, the contractors shall obtain and maintain at least the following kinds of insurance and minimum liability coverage during any period of contract performance:

a. Workmen’s Compensation and occupational disease coverage as required by law except that, if this contract is to be performed in a state which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such state will be satisfactory. The required

Workman’s Compensation Insurance shall extend to cover employers’ liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.

b. Comprehensive General Liability Insurance in the minimum limit of $500,000 per occurrence for bodily injury liability.

c. Comprehensive Automotive Liability Insurance with minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury, and a minimum limit of $20.000 per occurrence for property damage.

14. Insurance (Cost Reimbursement):Pursuant to the requirements of FAR Clause 52.228-7- Insurance Liability to third persons, the contractor shall obtain and maintain at least the following kinds of insurance and minimum liability coverage during any period of contract performance:

a. Workmen's Compensation and occupational disease coverage as required by law except that, if this contract is to be performed in a State which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such State will be satisfactory. The required Workmen's Compensation Insurance shall extend to cover employers' liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.

b. Comprehensive General Liability Insurance in the minimum limit of $500,000 per occurrence for bodily injury liability.

c. Comprehensive Automotive Liability Insurance with minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury, and a minimum limit of $20,000 per occurrence for property damage.

15. AMC-Level Protest Program. Prior to submitting an agency protest, it is preferable that you first attempt to resolve your concerns with the responsible contracting officer. However, you may also file a protest to the Headquarters (HQ), Army Materiel Command (AMC). The HQ AMC-Level Protest Program is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forum, rather than filing a protest with the General Accountability Office (GAO), or other external forum. Contract award or performance is suspended during the protest to the same extent, and within the same time periods, as if filed at the GAO. The AMC protest decision goal is to resolve protests within 35 calendar days from filing. To be timely, protests must be filed within the periods specified in Federal Acquisition Regulation 33.103. If you want to file a protest under the HQ AMC-Level Protest Program, the protest must request resolution under that program and be sent to the address below.

Headquarters U.S. Army Materiel Command Office of Command Counsel-Deputy Command Counsel

4400 Martin Road Rm: A6SE040.001

Redstone Arsenal, AL 35898-5000 Fax: (256) 450-8840 or email usarmy.redstone.usamc.mbx.protests@mail.mil

The AMC-level protest procedures are found at: www.amc.army.mil/amc/commandcounsel.html If internet access is not available, contact the contracting officer or HQ, AMC to obtain the AMC-Level Protest Procedures.

16. Pre-Award Survey: A Pre-Award Survey may be conducted to examine the offeror's technical ability, management structure, financial capability, accounting systems, security controls/clearances, labor resources, performance record, and ability to meet required schedules.

17. Commercial Warranty. The Contractor agrees that the supplies or services furnished under this contract shall be covered by the most favorable commercial warranties the contrator gives to any customer for such supplies

PERFORMAND WORK STATEMENT

LIGHTNING PROTECTION SYSTEM (LPS) SERVICE

1.0 General:

1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, quality control and other items and non-personal services necessary to perform lightning protection system service and repair as defined in this PWS, except as specified in Paragraph 3.0 as Government Furnished. The contractor shall perform to the standards in this contract and according to DA PAM 385-64 (24 MAY 2011 with RAR 10 OCT 2013) and all applicable publications. The tasks and actions described in the PWS will be performed on site in an ammunition based organization that has greater than normal hazardous conditions within the working environment. This risk of performing this service in an ammunition related area will be identified and acknowledged via a signed memorandum issued by the COR/TPOC.

1.2 Background: Lightning protection systems are used to reduce the risk, damage and destruction of a lightning strike to different buildings, docks and other specific sites. The lightning protection systems of Letterkenny Munitions Center (LEMC) consist of integral systems (lightning rods), mast systems and catenary systems (overhead wire). The integral system consists of air terminals mounted directly to the facility or structure to be protected, down conductors and a grounding system. The mast system consists of an air terminal (lightning rod) on a mast, down conductors and an earth electrode subsystem. The catenary system (overhead wires), consist of one or more overhead wires strung between masts and connected to a grounding system. LEMC uses a variety of all the mentioned systems in the docks, buildings and earth covered magazines (ECM). The requirement is that all of the active LPS in LEMC is tested at least one time per year and the repairs will be listed as routine. A repair shall need to be scheduled within 48 hours of report. This entire PWS will be monitored by the LEMC COR.

1.3 General Information:

1.3.1 Recognized Holidays: The following are recognized US holidays. The contractor shall not perform services on these days:

1.3.1.1 New Year’s Day: January 1st

1.3.1.2 Martin Luther King, Jr.’s Birthday: Third Monday in January

1.3.1.3 President’s Day: Third Monday in February

1.3.1.4 Memorial Day: Last Monday in May

1.3.1.5 Independence Day: July 4th

1.3.1.6 Labor Day: First Monday in September

1.3.1.7 Columbus Day: Second Monday in October

1.3.1.8 Veteran’s Day: November 11th

1.3.1.9 Thanksgiving Day: Fourth Thursday in November

1.3.1.10 Christmas Day: December 25th

Please Note: When an observed holiday falls on a Tuesday or Thursday, the Depot regularly schedules a closure on the corresponding Monday or Friday.

1.3.2 Place and Performance of Services: The contractor shall provide services between the hours of 0700 to 1530, Monday through Thursday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, weather conditions, or similar Government-directed facility/installation closings. Performance shall be at the area of designation, according to a schedule, provided by the government COR. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

1.3.3 Security Requirements: The contractor must identify all employees in advance to the government COR, so all security measures may be completed in advance of any install, service or repair actions. The contractor shall provide information like, but not limited to: the dates of birth, places of birth, social security number, address, and phone number as necessary. If foreign nationals are to be employed, the contractor shall provide, copies, of work visa, social security cards, permanent resident cards, passports, birth certificates or other documents. If the contractor and/or employee of the contractor do not possess a United States Citizenship and cannot get a favorable or acceptable response from the investigation conducted via the LEAD Information Form then they shall not be authorized access to the organization. The contractor must have all employees complete the necessary background checks in order to gain access to the LEMC facility.

1.3.3.1 Personnel that have been charged and or convicted of murder, terrorism, human trafficking, domestic violence with a weapon, drug trafficking, and/other related offense shall not be granted access to

LEMC.

1.3.3.2 Contractor vehicles shall have their company logo affixed to both sides of their vehicle if that vehicles needs to enter the ammunition storage area. Vehicle and equipment shall have a fully charged 10BC rated fire extinguisher affixed inside of the vehicle, and/or to the piece of motorized equipment that is being introduced in to the ammunition storage area.

1.3.3.3 Contract personnel working in the ammunition storage area shall abide by the thunderstorm stand down procedures and the evacuation plans for the Letterkenny Munitions Center, which shall be provided by the LEMC COR.

1.3.4 Physical Security: The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.3.4.1 Explosives Area Safety: Radio and wireless transmissions/cellular telephone calls/broadcast devices are prohibited in areas that are posted due to the sensitivity to Radio Frequency (RF) exposure.

Cellular telephones, portable two-way radios, computers wire wireless links, wearable technology devices with wireless links, and hand held communication devices (Blackberries, Smart Phones, wireless devices, computer tablets, Fitbit activity trackers, etc.) will not be used in any operational buildings and will not be used within 25 feet of an area of building where ammunition and/or explosives are being processed or stored. Further, devices that have built in cameras are prohibited from being introduced into the ammunition storage area without permission from the LEMC Security Manager.

1.3.5 Special Qualifications: The contractor must have technicians trained according to listed government standards to test, disassemble, renovate or conduct other modifications, or repair the LPS according to government regulations and/or Standard Operating Procedures (SOP). This would include a skill set trained to conduct testing of the LPS with the appropriate electronic testing equipment and then be able to report and read the test equipment to make the pass/fail decision for the test. The test shall fail if the reading on the equipment is above or outside the parameters of DA PAM 385-64 (table 17-1) requirements. The contractor must have all on site employees take and pass successfully the following training:

1.3.5.1 AMMO-28-DL Army Electrical Explosive Safety – This training is taken one time by each individual contractor, and no re-certification is necessary.

1.3.6 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with Federal Acquisition Regulations Subpart 42.5. The KO, Contracting Officer’s Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the Contracting Officer shall apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced the contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

1.3.7 Identification of Contractor Employees: All contract personnel working inside the LEAD/LEMC facility, are required to identify themselves, by wearing a government visitor badge or government issued identification badge, as such to avoid creating an impression in the minds of members of the public that they are Government officials.

The contractor shall also ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed and reported to the government designated COR.

2.0 Definitions and Acronyms:

2.1.1 CONTRACTOR: A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2 CONTRACTING OFFICER (KO): A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR): An employee of the U.S. Government designated by the KO to monitor contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4 DEFECTIVE SERVICE: A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5 DELIVERABLE: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.6 KEY PERSONNEL: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7 PHYSICAL SECURITY: Actions that prevent the loss or damage of Government property.

2.1.8 QUALITY ASSURANCE: The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10 QUALITY CONTROL: All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11 SUBCONTRACTOR: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.12 WORK DAY: The number of hours per day the Contractor provides services in accordance with the contract.

2.1.13 WORK WEEK: Monday through Thursday, unless specified otherwise.

2.2 ACRONYMS:

AE Ammunition and Explosives AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTS Commercial-Off-the-Shelf CSA Canadian Standards Association DA Department of the Army DA PAM Department of the Army Pamphlet DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DOD Department of Defense ECM Earth Covered Magazine JMCN Joint Munitions Command LEAD Letterkenny Army Depot LEMC Letterkenny Munitions Center FAR Federal Acquisition Regulation KO Contracting Officer OCI Organizational Conflict of Interest ODC Other Direct Costs PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program NFPA National Fire Protection Association TE Technical Exhibit UL Underwriters Laboratory

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government shall provide the facilities, equipment, materials, and/or services listed below:

3.1 The Government shall furnish the necessary workspace for the contractor staff to provide the support outlined in this PWS to include parking space for the mobile equipment and LEMC COR guidance for schedules, quality control and physical directions to the individual sites. This does not include any administrative space for training or any other administrative functions.

4.0 Contractor Furnished Property, Materials, Equipment (CFP/M/E):

4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.

4.2 Equipment: The contractor shall provide all the equipment necessary in order to reach points that are in the air and the height range is from 0 feet to over 80 feet. This shall also include ladders, man lifts, climbing spikes (for the catenary systems), etc. The testing equipment shall be able to conduct electrical tests consisting of measuring the bonding resistance of the LPS components. The test equipment shall be calibrated according to industry standards to test lightning protection systems. Commercially available test equipment can be purchased which can provide a measurement accuracy of 10% minimum. However, the assumptions used in the various test methods will often result in much greater inaccuracies or variations in the repeatability of the test results. Only instruments specifically designed for earth ground system testing shall be used to measure the earth system resistance. These instruments are generally designed to reject ground current. Instruments used to measure the earth resistance shall be able to measure multiple ranges with ± 10% accuracy. Instruments used to measure the electrical resistance of objects bonded to the secondary ground shall be able to measure from 0-1 ohm with ±10% accuracy. The same instrument may be used to measure both earth and bond resistances if desired.

5.0 Requirements: The contractor shall:

5.1 Testing: The testing of all buildings, docks, and ECMs, shall be conducted according to a schedule established by the LEMC COR and the testing criteria shall be described in the PWS and then evaluated for quality using the QASP by the LEMC COR. The entire system at LEMC must be tested once every, 12 months or 1 year.

5.1.1 Testing of Earth Covered Magazines (approximately 10,000 test points) in accordance with form JMCN 3751-R. Magazines shall be tested IAW DA Pam 385-64 (Appd B) and test results documented on JMCN Form 3751 and, returned to the COR within 5 working days of the test. Annotate results of 3 Point Fall of Potential resistance reading (25 ohms maximum) in notes section. Lightning protection subsystem (bonding check) have a maximum resistance of 1 ohm. LPS tests shall be IAW DA Pam 385-64 (Appd D) with results annotated in JMCN Form 3897-R. CLIN 0001

5.1.2 Testing of air terminals, masts, and catenary systems on Explosive Operating Buildings (approximately 1000 test points, each building has a different number according to the size and structure of the LPS), in accordance with form JMCN 3897-R, and a this shall be returned to the COR within 5 working days of the test. The building testing portion externally also includes, but is not limited to: bonding, windows, overhead doors, pedestrian doors, external access points, and/or within 6 foot side flash distance (which includes any or all points of the LPS system), etc. Earth electrode subsystems and Bonding Checks shall be tested IAW DA Pam 385-64 (Appd B) and test results documented in accordance with form JMCN 3897-R. Tests shall be IAW DA Pam 385-64 (Appd D) with results annotated in JMCN Form 3897-R. The instrument must be capable of measuring resistance up to 1 ohm +10 percent. The manufacturer’s instruction manual will be followed to assure proper use of the instrument. If the meter reading exceeds one ohm, the lightning protection subsystem is not acceptable. CLIN 0002

5.1.2.1 Bonding: According to DA PAM 385-64; 17-22 Bonding shall have:

(A) Protection from side flash shall be obtained by either separation distance or by bonding. The required separation distance shall be determined by using the formula in NFPA 780, ’ Standard for the Installation of Lightning Protection Systems’ as indicated below. Bonding is used to reduce the possibility of a side flash and is used to ensure no electrical potential differences are produced by lightning current. Chapter 4 and Annex K of NFPA 780 shall be used to determine the minimum bonding requirements except as modified herein.

(B) For buildings which are 36 feet in height, or less:

(1) Bonding will be required for large masses of metal (400 inches square or larger surface area) located on the exterior, or within facilities,

(2) Bonding is also required if the object is within 6 feet of an opening or within six feet of any part of the LPS. Examples include facility metal items such as radiators, tanks, permanent machinery, stair rails, ventilator, metal doors, air conditioning ducts, metal columns and metal siding.

(C) For buildings greater than 36 feet in height: Bonding will be required as specified in NFPA 780, chapter 3.

(D) The material used to bond the LPS to the grounding loop conductor will meet the requirements set forth in table 17–5. The resistance of any object bonded to the LPS will not exceed one ohm. Exceptions are noted in table 17–1.

(E) Fences which come within 6 feet of an explosives structure’s LPS will be bonded to the structure’s LPS or its grounding system.

(F) Railroad tracks which run within 6 feet of an explosives structure’s LPS will be bonded to the structure’s LPS or its grounding system. If the tracks are used to carry electrical signals, they will have insulated joints immediately external to bond the LPS’s ground loop conductor. If these tracks enter a facility, they will also be bonded to the frame of the structure or equivalent.

5.1.3 Testing of the LPS catenary systems on 29 explosive loading docks (approximately 800 points, each dock has a different number of points according to the size and structure of the LPS), and railroad tracks (within 6 feet of dock or catenary pole), in accordance with form JMCN 3897-R. Railroad tracks which run within 6 feet of an explosives structure’s LPS will be bonded to the structure’s LPS or its grounding system. Tests shall be performed IAW DA Pam 385-64 (Appd B) and test results documented on JMCN Form 3751, and this shall be returned to the COR within 5 working days of the test. Annotate results of 3 Point Fall of Potential resistance reading (25 ohms maximum) in notes section. Lightning protection subsystem (bonding check) have a maximum resistance of 1 ohm. LPS tests shall be IAW DA Pam 385-64 (Appd D) with results annotated in JMCN Form 3897-R. CLIN 0003

5.1.4 RESISTANCE OF SYSTEM. The resistance from all air termination systems and down conductors to the lightning protection grounding system shall be less than one ohm. The resistance to earth of the lightning protection grounding system shall be 25 ohms or less. If not, steps need to be taken until these levels of resistance are met. Additional, deeper ground rods or any other approved method may be used to achieve this reading. At locations where achieving 25 ohms or less is not feasible through the installation of additional ground rods or a ground loop conductor, other alternatives are possible, but must be approved by LEMC COR and TPOC.

5.2 Repair: The repairs shall be scheduled for all points that do not successfully pass the testing process according to the list/steps in 5.1, within 48 hours of submission of the deficiency annotated on report form JMCN 3751-R or JMCN 3897-R and, returned to the COR within 5 working days of the repair/test. The static electricity charge dissipation subsystem has to possess a required resistance of less than or equal to 25 kΩ to 1 MΩ (Ω is OHMs). The repairs may include replacement of ground rods (copper, copper-clad, stainless steel, hot-dipped galvanized steel), ground loops (counterpoise) (stranded copper, copper-clad steel cable), and air terminals (solid copper, copper-clad steel, hot-dipped galvanized steel, solid aluminum, tubular aluminum, tubular copper), and catenary (overhead wire) system (copper, copper-clad, aluminum, stainless steel) and main conductor cables (copper, aluminum), and main conductor solid strip (copper, aluminum), and bonding straps (solid or stranded) (copper, aluminum). The repairs could also include but not be limited to cable replacement underground, which would require the cable to be a minimum of 30” underground. Repairs and replacement of components must meet the requirements of NFPA 780 and DA PAM 385-64 (table 17-4 LPS requirements). Grounding system material will be in accordance with NFPA 780, NFPA 70, Article 250, Part J, paragraphs 250–90 through 250–106, and DA PAM 385-64. After the repair is conducted, then a test must be conducted/repeated, in order to confirm the point is within the establish parameters.

All test equipment shall be calibrated according to the industry standards established for this type of test equipment.

The warranty on the repairs shall last at least 12 months from the date of the repair, which means that the repair will still be able to successfully pass the testing criteria in 5.0 up to 12 months from the date of the repair. If not, the repairs will be completed again and the warranty period will begin from that date. CLIN 0004

5.2.1 Bonding: According to DA PAM 385-64; 17-22 Bonding shall have:

(A) Protection from side flash shall be obtained by either separation distance or by bonding. The required separation distance shall be determined by using the formula in NFPA 780, ’ Standard for the Installation of Lightning Protection Systems’ as indicated below. Bonding is used to reduce the possibility of a side flash and is used to ensure no electrical potential differences are produced by lightning current.

Chapter 4 and Annex K of NFPA 780 shall be used to determine the minimum bonding requirements except as modified herein.

(B) For buildings which are 36 feet in height, or less:

(1) Bonding will be required for large masses of metal (400 inches square or larger surface area) located on the exterior, or within facilities,

(2) Bonding is also required if the object is within 6 feet of an opening or within six feet of any part of the LPS. Examples include facility metal items such as radiators, tanks, permanent machinery, stair rails, ventilator, metal doors, air conditioning ducts, metal columns and metal siding.

(C) For buildings greater than 36 feet in height: Bonding will be required as specified in NFPA 780, chapter 3.

(D) The material used to bond the LPS to the grounding loop conductor will meet the requirements set forth in table 17–5. The resistance of any object bonded to the LPS will not exceed one ohm. Exceptions are noted in table 17–1.

(E) Fences which come within 6 feet of an explosives structure’s LPS will be bonded to the structure’s LPS or its grounding system.

(F) Railroad tracks which run within 6 feet of an explosives structure’s LPS will be bonded to the structure’s LPS or its grounding system. If the tracks are used to carry electrical signals, they will have insulated joints immediately external to bond the LPS’s ground loop conductor. If these tracks enter a facility, they will also be bonded to the frame of the structure or equivalent.

5.2.2 RESISTANCE OF SYSTEM. The resistance from all air termination systems and down conductors to the lightning protection grounding system shall be less than one ohm. The resistance to earth of the lightning protection grounding system shall be 25 ohms or less. If not, steps need to be taken until these levels of resistance are met. Additional, deeper ground rods or any other approved method may be used to achieve this reading. At locations where achieving 25 ohms or less is not feasible through the installation of additional ground rods or a ground loop conductor, other alternatives are possible, but must be approved by LEMC COR and TPOC.

5.3 Parts/Materials: This shall cover all parts and materials required for the repairs to be conducted in section 5.2. If amount of the parts/materials exceed $500 then verbal or written approval from the LEMC COR or TPOC shall be required before any work is authorized to begin. All parts/materials used for repairs shall be UL rated and approved, and use a LPS standards, and CSA certified. CLIN 0005.

5.4 CONTRACTOR MANAGEMENT REPORTING (CMR): The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor shall report ALL Contractor manpower (including subcontractor manpower) required for performance of this contract.

The contractor shall completely fill in all the information in the format using the following web address https://Contractormanpower.army.pentagon.mil. The required information includes: (1) Contracting Office, KO, Contracting Officer’s Technical Representative (COTR) or also known as the Contracting Officer’s Representative (COR); (2) Contract number, including task and delivery order number; (3) Beginning and ending dates covered by reporting period; (4) Contractor's name, address, phone number, e-mail address, identity of Contractor employee entering data; (5) Estimated direct labor hours (including sub-Contractors); (6) Estimated direct labor dollars paid this reporting period (including sub-Contractors); (7) Total payments (including sub-Contractors); (8) Predominant Federal Service Code (FSC) reflecting services provided by Contractor (and separate predominant FSC for each sub- Contractor if different); (9) Estimated data collection cost; (10) Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring Activity is responsible for providing the Contractor with its UIC for the purposes of reporting this information); (11) Locations where Contractor and sub-Contractors perform the work (specified by zip code in the United States and nearest city, country, when in an overseas location, using standardized nomenclature provided on website); (12) Presence of deployment or contingency contract language; and (13) Number of Contractor and sub-Contractor employees deployed in theater this reporting period (by country). As part of its submission, the Contractor shall provide the estimated total cost (if any) incurred to comply with this reporting requirement.

Reporting period shall be the period of performance not to exceed 12 months ending September 30 of each government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor’s system to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from the website.

6.0 Applicable Publications: Publications applicable to this PWS are listed below:

TECHNICAL EXHIBIT 1

Performance Requirements Summary This Performance Requirements Summary includes performance standards. The Government shall use these standards to determine contractor performance and shall compare contractor performance to the Acceptable Quality Level (AQL). These standards will be used in the QASP to measure performance according to the listed COPR duties.

PWS

Paragraph

Task

Performance Standard

Acceptable Quality Levels

(AQL)

Surveillance Method / By Whom

5.1 Testing The contractor shall

perform 95% of the required testing each year.

100% Periodic Inspection - COR shall review monthly work order logs.

5.2 Repairs

99% Repairs shall pass test 1% rework

Periodic Inspection - COR shall review monthly work order logs.

1.3.5 Special

Qualifications

All contractor employees on site shall complete the training listed in 1.4.4

100% Submit evidence of training annually to COR – Begins when contract is awarded

Publication (Chapter / Page)

Date of Publication

Mandatory or Advisory Website

NFPA 780 2011 Edition Standard for the Installation of Lightning Protection Systems www.nfpa.org

DA PAM 385-64 24 MAY 2011

(RAR 10 OCT

2013)

Ammunition and Explosive Safety Standards www.apd.army.mil

MIL-HDBK-419A

Volume II of 2

Volumes – Applications

29 DEC 1987 Military Handbook, Grounding, Bonding and Shielding for Electronic

Equipment and Facilities www.wbdg.org

Unified Facilities Criteria (UFC)

UFC 3-575-01

1 JUL 2012 Lightning and Static Electricity Protection Systems

Unified Facilities Criteria (UFC)

UFC 4-420-01

1 MAY 2015 Ammunition and Explosives Storage Magazines

(Chapter 3-8, 3-9, Electrical Design & Grounding)

NFPA 70 2017 Edition National Electrical Code

TECHNICAL EXHIBIT 2

Deliverables Schedule

Deliverable Frequency Number of

Copies Submission Format Submit To

5.1 Test results on form

JMCN 3897-R or JMCN

3751-R

Each Test – Within 7 days of completion

1 Electronic Submission/ Hard

Copy

CORhttps://cmra.army .mil/

5.2 Repairs Test results

on form JMCN 3897-R or JMCN 3751-R

Each Test – Within 7 days of completion

1 Electronic Submission/ Hard

Copy

COR

5.5 CMR Reporting period shall be

the period of performance not to exceed 12 months ending September 30 of each government fiscal year and must be reported by 31 October of each calendar year.

1 Electronic Submission https://Contractormanp ower.army.pentagon.m il

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Lot Name: TEST ECM

FFP

Description: LIGHTNING PROTECTION SYSTEM SERVICE- TEST

WITHOUT LIFT OF THE EARTH COVERED MAGAZINES C/W SECTION

5.1.1 OF THE PWS.

FOB: Destination

NSN: AASSVC835302ER

MILSTRIP: W25G1R835302ER

PURCHASE REQUEST NUMBER: W25G1R835302ER0001

PSC CD: J062

NET AMT

0002 1 Lot Name: TEST BUILDINGS

FFP

Description: LIGHTNING PROTECTION SYSTEM SERVICE TEST WITH

LIFT OF AIR TERMINALS, MASTS, AND CATENARY SYSTEMS ON

EXPLOSIVE OPERATING BUILDINGS IN C/W SECTION 5.1.2 OF THE PWS.

FOB: Destination

NSN: AASSVC835302ES

MILSTRIP: W25G1R835302ES

PURCHASE REQUEST NUMBER: W25G1R835302ES0002

0003 1 Lot Name: TEST LOADING DOCKS

FFP

Description: LIGHTNING PROTECTION SYSTEM SERVICE TEST WITH

LIFT OF THE LPS CATENARY SYSTEMS ON 29 EXPLOSIVE LOADING

DOCKS IN C/W SECTION 5.1.3 OF THE PWS.

FOB: Destination

NSN: AASSVC835302ET

MILSTRIP: W25G1R835302ET

PURCHASE REQUEST NUMBER: W25G1R835302ET0003

ITEM NO SUPPLIES/SERVICES ESTIMATED

QUANTITY

UNIT UNIT PRICE AMOUNT

0004 1 Lot Name: REPAIR-LABOR

LH

Description: LIGHTNING PROTECTION SYSTEM SERVICE LABOR

REPAIR IN C/W SECTION 5.2 OF THE PWS.

FOB: Destination

NSN: AASSVC835302EU

MILSTRIP: W25G1R835302EU

PURCHASE REQUEST NUMBER: W25G1R835302EU0004

TOT ESTIMATED PRICE

CEILING PRICE

0005 25,000 Lot

NAME: PARTS-MATERIALS

T&M Description: LIGHTNING PROTECTION SYSTEM SERVICE PARTS &

MATERIALS IN C/W SECTION 5.3 OF THE PWS. DO NOT QUOTE THIS

CLIN-FUNDING WILL BE PROVIDED FOR COVERAGE

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

NSN: AASSVC835302EV

MILSTRIP: W25G1R835302EV

PURCHASE REQUEST NUMBER: W25G1R835302EV0005

0006 1 Lot

MANPOWER REPORTING

FFP

LIGHTNING PROTECTION SYSTEM SERVICE MANPOWER REPORTING

IN C/W SECTION 5.4 OF THE PWS.

FOB: Destination

PURCHASE REQUEST NUMBER: W25G1R835302EW0006

1001 1 Lot OPTION Name: TEST ECM

FFP

Description: LIGHTNING PROTECTION SYSTEM SERVICE- TEST

WITHOUT LIFT OF THE EARTH COVERED MAGAZINES C/W SECTION

5.1.1 OF THE PWS.

FOB: Destination

1002 1 Lot OPTION Name: TEST BUILDINGS

FFP

Description: LIGHTNING PROTECTION SYSTEM SERVICE TEST WITH

LIFT OF AIR TERMINALS, MASTS, AND CATENARY SYSTEMS ON

EXPLOSIVE OPERATING BUILDINGS IN C/W SECTION 5.1.2 OF THE PWS.

1003 1 Lot OPTION Name: TEST LOADING DOCKS

FFP

Description: LIGHTNING PROTECTION SYSTEM SERVICE TEST WITH

LIFT OF THE LPS CATENARY SYSTEMS ON 29 EXPLOSIVE LOADING

DOCKS IN C/W SECTION 5.1.3 OF THE PWS.

UNIT UNIT PRICE AMOUNT

1004 1 Lot OPTION Name: REPAIR-LABOR

LH

Description: LIGHTNING PROTECTION SYSTEM SERVICE LABOR

REPAIR IN C/W SECTION 5.2 OF THE PWS.

1005 1 Lot

OPTION NAME: PARTS-MATERIALS

T&M Description: LIGHTNING PROTECTION SYSTEM SERVICE PARTS &

MATERIALS IN C/W SECTION 5.3 OF THE PWS. DO NOT QUOTE THIS

CLIN-FUNDING WILL BE PROVIDED FOR COVERAGE

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

1006 1 Lot

OPTION MANPOWER REPORTING

FFP

LIGHTNING PROTECTION SYSTEM SERVICE MANPOWER REPORTING

IN C/W SECTION 5.4 OF THE PWS.

2001 1 Lot OPTION Name: TEST ECM

FFP

Description: LIGHTNING PROTECTION SYSTEM SERVICE- TEST

WITHOUT LIFT OF THE EARTH COVERED MAGAZINES C/W SECTION

5.1.1 OF THE PWS.

2002 1 Lot OPTION Name: TEST BUILDINGS

FFP

Description: LIGHTNING PROTECTION SYSTEM SERVICE TEST WITH

LIFT OF AIR TERMINALS, MASTS, AND CATENARY SYSTEMS ON

EXPLOSIVE OPERATING BUILDINGS IN C/W SECTION 5.1.2 OF THE PWS.

2003 1 Lot OPTION Name: TEST LOADING DOCKS

FFP

Description: LIGHTNING PROTECTION SYSTEM SERVICE TEST WITH

LIFT OF THE LPS CATENARY SYSTEMS ON 29 EXPLOSIVE LOADING

DOCKS IN C/W SECTION 5.1.3 OF THE PWS.

UNIT UNIT PRICE AMOUNT

2004 1 Lot OPTION Name: REPAIR-LABOR

LH

Description: LIGHTNING PROTECTION SYSTEM SERVICE LABOR

REPAIR IN C/W SECTION 5.2 OF THE PWS.

2005 1 Lot

OPTION NAME: PARTS-MATERIALS

T&M Description: LIGHTNING PROTECTION SYSTEM SERVICE PARTS &

MATERIALS IN C/W SECTION 5.3 OF THE PWS. DO NOT QUOTE THIS

CLIN-FUNDING WILL BE PROVIDED FOR COVERAGE

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

2006 1 Lot

OPTION MANPOWER REPORTING

FFP

LIGHTNING PROTECTION SYSTEM SERVICE MANPOWER REPORTING

IN C/W SECTION 5.4 OF THE PWS.

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government 0006 Destination Government Destination Government 1001 Destination Government Destination Government

1002 Destination Government Destination Government 1003 Destination Government Destination Government 1004 Destination Government Destination Government 1005 Destination Government Destination Government 1006 Destination Government Destination Government 2001 Destination Government Destination Government 2002 Destination Government Destination Government 2003 Destination Government Destination Government 2004 Destination Government Destination Government 2005 Destination Government Destination Government 2006 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 POP 23-AUG-2019 TO

22-AUG-2020

N/A LETTERKENNY MUNITIONS CENTER

MONICA R DEAN

BLDG 3315

1 OVERCASH AVE

CHAMBERSBURG PA 17201-4150

717.267.9577

W25G1R

0002 POP 23-AUG-2019 TO

22-AUG-2020

N/A (SAME AS PREVIOUS LOCATION)

0003 POP 23-AUG-2019 TO

N/A (SAME AS PREVIOUS LOCATION)

0004 POP 23-AUG-2019 TO

N/A (SAME AS PREVIOUS LOCATION)

0005 POP 23-AUG-2019 TO

N/A (SAME AS PREVIOUS LOCATION)

0006 POP 23-AUG-2019 TO

N/A (SAME AS PREVIOUS LOCATION)

1001 POP 23-AUG-2020 TO

22-AUG-2021

N/A (SAME AS PREVIOUS LOCATION)

1002 POP 23-AUG-2020 TO

N/A (SAME AS PREVIOUS LOCATION)

1003 POP 23-AUG-2020 TO

N/A (SAME AS PREVIOUS LOCATION)

1004 POP 23-AUG-2020 TO

N/A (SAME AS PREVIOUS LOCATION)

1005 POP 23-AUG-2020 TO

N/A (SAME AS PREVIOUS LOCATION)

1006 POP 23-AUG-2020 TO

N/A (SAME AS PREVIOUS LOCATION)

2001 POP 23-AUG-2021 TO

22-AUG-2022

N/A (SAME AS PREVIOUS LOCATION)

2002 POP 23-AUG-2021 TO

N/A (SAME AS PREVIOUS LOCATION)

2003 POP 23-AUG-2021 TO

N/A (SAME AS PREVIOUS LOCATION)

2004 POP 23-AUG-2021 TO

N/A (SAME AS PREVIOUS LOCATION)

2005 POP 23-AUG-2021 TO

N/A (SAME AS PREVIOUS LOCATION)

2006 POP 23-AUG-2021 TO

N/A (SAME AS PREVIOUS LOCATION)

CLAUSES INCORPORATED BY REFERENCE

52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-6 Alt I Restrictions On Subcontractor Sales To The Government

(Sep 2006) -- Alternate I

OCT 1995

52.203-12 Limitation On Payments To Influence Certain Federal Transactions

OCT 2010

52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights

APR 2014

52.203-18 Prohibition on Contracting With Entities That Require Certain Internal Confidentiality Agreements or Statements-- Representation

JAN 2017

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

JAN 2017

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper

MAY 2011

52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

OCT 2018

52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting JUL 2016

52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.204-19 Incorporation by Reference of Representations and

Certifications.

DEC 2014

52.212-1 Instructions to Offerors--Commercial Items OCT 2018 52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018 52.217-5 Evaluation Of Options JUL 1990 52.219-6 Notice Of Total Small Business Set-Aside NOV 2011 52.219-8 Utilization of Small Business Concerns OCT 2018 52.219-14 Limitations On Subcontracting JAN 2017 52.222-3 Convict Labor JUN 2003 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment

Exceeding $15,000

MAY 2014

52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-35 Equal Opportunity for Veterans OCT 2015 52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-37 Employment Reports on Veterans FEB 2016 52.222-41 Service Contract Labor Standards AUG 2018 52.222-43 Fair Labor Standards Act And Service Contract Labor

Standards - Price Adjustment (Multiple Year And Option Contracts)

AUG 2018

52.222-50 Combating Trafficking in Persons JAN 2019 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-11 Ozone-Depleting Substances and High…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.