This is an Area of Interest (AoI) document announcing a federal contracting opportunity for fire suppression system inspection and repair services at Anniston Army Depot.
The Army Contracting Command – Anniston Army Depot (ACC-ANAD) seeks a contractor to provide semi-annual inspection, testing, maintenance, and repair services for three types of fire suppression systems across 16 buildings: Kitchen Hood systems (Buildings 47, 78, 141, 1500), FM-200 systems (Buildings 52, 53, 79, 96, 97, 362, 363, 513), and HFC-227/CO₂ production systems (Buildings 128, 410, 474, 475). The contract consists of one base year plus four option years. Work must comply with NFPA standards 12, 17A, 72, 96, and 2001, and include functional testing of detection and alarm devices, visual inspection of cylinders and piping, cylinder weight and pressure verification, hydro-testing, detector cleaning, battery backup testing, and detailed inspection reporting. Contractor personnel must hold NICET certification and be licensed and experienced with Fike, Ansul, Notifier, and Pyro-Chem systems. A mandatory pre-work site visit is required. Contractors must comply with OSHA regulations, environmental rules, and Army safety protocols. The AoI includes separate not-to-exceed budgets for repairs (billed as firm fixed price) and emergency work (24-hour response requirement). Pricing must include a Rough Order of Magnitude sufficient to assess general affordability. Written solutions must be submitted by 4:00 PM CDT on 20 May 2026, with all questions due by 4:00 PM CDT on 4 May 2026. Offerors must be registered in SAM.gov. Additional detailed system information is available in referenced attachments QD89-FM200-Bldg List and QD89-FM200-Inspection Schedule.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QD89-FM200-Bldg List.pdf | ||
| QD89-FM200-Inspection Schedule.pdf | ||
| Area of Interest W911KF25SC002-AOI0007.pdf | ||
| CSO-Anniston Army Depot Updated 4.20.26.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Area of Interest (AoI) – FM200 System Inspection and Repairs
Federal Agency: Army
Office: Army Contracting Command – Anniston Army Depot (ACC-ANAD)
AoI Title: FM200 System Inspection and Repairs
CSO AoI Number: AoI #0007
AoI Release Date: 20 April 2026
Responses: See W911KF-25-S-C002 for procedure details
Questions and Answers:
1. How many of each system is located within the buildings? Please review the attachments QD89-FM200-Bldg List and QD89-FM200-Inspection Schedule for this information.
2. What is the “not-to-exceed” repair budget? Are we supposed to give that number, or is that something the gov’t is providing? It says repairs are based on inspection findings, meaning we won’t know what needs to be repaired until an inspection is completed.
This information will not be given award.
3. What is the “not-to-exceed” emergency budget? Are we supposed to give that number or is that the something the gov’t is providing? This information will not be given until award.
4. Other than the cleaning of the detectors, what other “maintenance and repair” items need to be included? Please review the attachment QD89-FM200-Inspection Schedule for this information. The Activity column has the required Inspection, Test, and Maintenance labeled with the frequency noted under the Periodic Frequency column.
5. The AoI just says to verify hydro-test dates… Will hydro-testing of the cylinders be required? If so, we will need to know the size and quantity of all the cylinders. Yes, hydrotesting is required. Please review the attachments QD89-FM200-Bldg List and QD89-FM200-Inspection Schedule for this information.
6. Is pricing to be included in the form of basic year plus four option years. In other quotes of this type a requirement to price each building individual is that a requirement here. The brief must include a ROM price sufficient for the Government to assess general affordability per 3.2.1(4) of the Commercial Solutions Opening.
7. What type of maintenance is required and on what items. Please review the attachments QD89-FM200-Bldg List and QD89-FM200-Inspection Schedule for this information.
8. Can you provide detailed information for the suppression systems requiring inspections on this contract. We need to know how much agent, how many detectors, and how many links are on each system to provide an accurate proposal. Please review the attachments QD89-FM200-Bldg List and QD89-FM200-Inspection Schedule for this information.
Additional questions will not be accepted in relation to this AoI.
1. Overview
• ACC-ANAD is seeking solutions for semi-annual inspection, testing, maintenance, and repair of Clean Agent systems (FM-200/HFC-227), Carbon Dioxide (CO2) systems, and Kitchen Hood fire extinguishing systems at Anniston Army Depot (ANAD). The resulting contract will include one base year plus four option years.
• Interested parties should review the full CSO posting on SAM.gov for submission and evaluation procedures.
• ACC-ANAD is not obligated to extend a request for proposal or make an award as a result of this CSO AoI; all awards are subject to the availability of funds and successful negotiations. This CSO AoI is not an authorization to begin performance, and in no way obligates the Government for any costs incurred by the Offeror associated with developing a Response. Prior to commencement of any activities associated with performance under this CSO AoI, the Government will issue a written directive or contractual document signed by the Contracting Officer with appropriate consideration established. ACC-ANAD reserves the right to modify the requirements of this CSO AoI.
2. General & Administrative Requirements
2.1 Contractor Responsibilities & Qualifications
• Site Familiarization: Mandatory pre-work site visit.
• Personnel Qualifications: Technicians must be licensed and experienced for the testing, inspection, and maintenance in the following systems, Fike, Ansul, Notifier, Pyro-Chem, and all associated peripheral equipment for each product.
• National Institute for Certifications in Engineering Technologies (NICET) Certification: Required; proof submitted with proposal.
• Uniform Standards: Uniform apparel is required for all personnel.
2.2 Safety & Environmental Compliance
• OSHA Compliance: Full adherence to 29CFR1926/1910 and ANAD safety rules.
• Environmental Regulations: Must comply with federal, state, local, and Army environmental rules (including AR 200-1).
• Training: Visitor safety training and annual RCRA training required.
• Hot Work: Requires ANAD Fire Department permit.
2.4 Required Submittals
• Site-Specific Safety Plan & QC Plan (30 days prior)
• Safety Data Sheets (before work)
• Work Schedule (14 days after award; monthly updates)
• Certifications (with proposal)
• Inspection Reports (within 14 days of inspections)
3. Scope of Work
3.1 System Types & Locations
The contractor will service three system categories across 16 buildings:
System Type Locations
Kitchen Hood Systems Bldgs. 47, 78, 141, 1500
FM-200 Systems Bldgs. 52, 53, 79, 96, 97, 362, 363, 513
HFC-227 / CO₂ Production Systems Bldgs. 128, 410, 474, 475
3.2 Inspection & Testing Requirements
All work must comply with National Fire Protection Association (NFPA) 12, 17A, 72, 96, 2001 and manufacturer guidance.
Tasks include:
• Functional testing of detection, alarm, and releasing devices
• Visual inspection of cylinders, piping, and nozzles
• Verification of cylinder weight, pressure, and hydro-test dates
• Simulation of discharge circuits and manual pulls
• Verification of alarm transmission and equipment shutdown
• Installation of new inspection tags
• Submission of detailed inspection reports with recommendations
3.3 System-Specific Requirements
• Kitchen Hoods: Replace fusible links and blow-off caps at first semi-annual inspection.
• FM-200/CO₂: Clean detectors, test battery backup, verify shutdown/evacuation circuits.
• System Shutdowns: Require ANAD Fire Department approval before any system shutdown for testing.
4. Remediation & Emergency Work
4.1 Remediation (Repairs)
• Annual not-to-exceed repair budget.
• Repairs based on inspection findings.
• Parts over $500 require prior Contracting Officer approval.
• Repairs billed as Firm Fixed Price (FFP).
4.2 Emergency Work
• Separate not-to-exceed emergency budget.
• Emergency = imminent threat requiring immediate action.
• Technician must be on-site within 24 hours of Contracting Officer Representative (COR) request; work completed within 48 hours.
• All emergency work requires COR approval.
5. AoI Constraints
• Offerors must be registered in SAM.gov.
6. Submission Instructions
• A written solution must be submitted via email to the Contracting Officer and Contract Specialist listed below by 4:00 PM CDT Wednesday, 20 May 2026 with the subject line:
o SOLUTION for AoI 0007 FM200 System Inspection and Repairs
• Late submissions will not be evaluated.
• All AoI questions must be submitted by 4:00 PM CDT, 4 May 2026 with the subject line:
o QUESTIONS for AoI 0007 FM200 System Inspection and Repair
• Late questions will not be answered.
• AoI Close Date: 4:00 PM CDT, 20 May 2026
7. Points of Contact
• AoI questions can be sent to:
• Contracting Officer: troy.m.gaddy2.civ@army.mil
• Contract Specialist: katherine.b.fuller2.civ@army.mil
• CSO AoI Contracting Officer: amber.e.burdett.civ@army.mil
• CSO AoI POC: diana.m.pritchettponder.civ@army.mil
File details come from the government source that posted it. Updated .