W911KF-19-R-0278-0002_Questions_and_Answers.pdf
PDF 649 KB Posted
- Attached to
- CNC Laser Cutting Machine
- Solicitation number
- W911KF-19-R-0278
About this file
Questions and Answers
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911KF-19-R-0278-0002_Questions and Answers
1. Please provide photos and/or available drawings of the foundation?
Answer: There is no special foundation for the existing equipment at the proposed location.
The area proposed is standard shop floor with concrete approximately eight (8) inches thick.
See Reference Layout.
2. Could you send me photos of the machine and the area around it?
Answer: No photos are allowed to be taken on the Anniston Army Depot.
3. Please provide weights and dims on this system?
Answer: The equipment and its supporting components occupies a space of approximately 28 feet long x 20 feet wide.
4. Where is said system to be re-located?
Answer: The equipment will be decommissioned, removed from the building to an identified location outside of the current building or loaded on a truck.
5. Is said system to be re-installed for use? If so, will utility services be required?
Answer: No. The equipment will not be re-installed. Service for this equipment will not be required.
6. Information requested -- age of foundation; floor thickness; is there any rebar in the foundation?
Answer: The addition was constructed in 1995-96 timeframe. Please see the attached Building construction layout.
7. If it is determined that a new foundation is required, will dust protection be required.
Answer: Yes. If any construction is required that will create dust and debris in the areas surrounding the location and adjacent equipment will need to be protected from dust and debris.
8. How thick is the concrete floor?
Answer: The area is standard shop floor approximately eight (8) inches thick. Please see the attached Layout for references.
9. Nitrogen system - will contractor be able to tap into the existing line or will a new gas line be required?
The SOW requests a nitrogen generator to be quoted as an option for this project. It will have to be determined depending on the proposed equipment requirements if the existing Nitrogen supply is used.
10. Rigging equipment -- are there any special crane or equipment requirements/restrictions?
Answer: The Equipment to be removed is a STRIPPIT PUNCHING AND SHEARING MACHINE CNC
LASER, Model Number: 1250 MXP 30 with PRC 2200 watt Laser.
SCALE:
DRAWN BY:
DESIGNED BY:
FILE DRAWER NO.
SHEET NO. OF
DATE:
PLAN NO.
IED
APPROVAL
CHECKED BY
DPW DM DAO DSP DPA
DOIM DLES DOC FAC.
ENGR.
AMMO.
SURV.
SAFETY CHEM.
SURETY
FIRE
CH.
IND.
HYG.
APPROVED
D A
T E
R E
V I S I O
N B
Y B
Y Anniston Army Depot Anniston, Alabama
DR
FE-416-95
5 9
AS NOTED
INDUSTRIAL ENGINEERING DIVISION
DIRECTOR of PRODUCTION ENGINEERING
MED
Rebecca Cleveland
DIVISION CHIEF
DRM
Building 145
Machining Facility
Sections and Details (2)
NOT TO SCALE
BRIDGE CRANE DETAIL
1" = 1'-0"
NEW ADDITION
SECTION THRU
2" MINIMUM
A P
P R
O X
CONTROL PENDANT
1/2
3" MIN. CLEARANCE
LINE
CLEARANCE
2" MIN.
2'-3"
OF HOOK TRAVEL
APPROX. LIMIT
CL RAIL
A P
P R
O X
30 September 95
FINISH
8" THICK WITH MONOLITHIC
NEW CONCRETE SLAB
SEE TECHNICAL PROV.
NEW 2 TON BRIDGE
(TWO REQUIRED)
FOR SPECIFICATIONS
ADEQUATELY SUPPORT LOADING REQ'D
BE DESIGNED BY THE CONTRACTOR TO
CRANE RAIL SUPPORTS/COLUMNS SHALL
WITH NEW METAL BUILDING COLUMNS
CRANE RAIL SUPPORTS INTEGRATED
ELEVATION
BUILDING FINISHED FLOOR
ELEVATION OF ORIGINAL
FLOOR ELEVATION TO MATCH
NEW ADDITION FINISHED
(REMAIN)
ORIGINAL BLDG. 145
WALL PANELS OF
EXISTING EXTERIOR
BUILDING 145
ORIGINAL STRUCTURE
ADDITION.
AT TRANSITION TO NEW
THROUGH-WALL FLASHING
INSTALL CONTINUOUS
BEHING D.S. AS REQ'D
ADDITION ROOF. PROVIDE BRACING
D.S. WILL DISCHARGE ONTO NEW
AND INSTALL ELBOW SUCH THAT
CUT OFF EXISTING DOWNSPOUTS
GUTTER
EXISTING
SEAM ROOF
EXISTING STANDING
BUILDING MFG.
SIZE AS PER METAL
GIRTS- SPACING,
15' HIGH
LINER PANELS APPROX.
NEW INTERIOR WALL
OF ORIGINAL BUILDING)
(MATCH CONFIGURATION
EXTERIOR WALL PANELS
INSULATION
CURB
CONCRETE
CRANE (TWO REQUIRED)
TWO-TON BRIDGE
AS PER METAL BLDG. MFG.
PURLINS- SPACING AND SIZE
ROOF PANELS
NEW STANDING SEAM
INSULATION
DOWNSPOUTS
NEW GUTTER AND
E A
V E
OR NEW CONCRETE
EXISTING HARDSTAND
NEW 30# ASCE RAIL (MIN.)
(SIZE AS REQ'D)
NEW CHANNEL
(SIZE AS REQUIRED)
NEW CRANE BEAM
50'-0" CL TO CL OF RAIL
CONCRETE
NEW
FLOOR
| Questions and Answers for W911KF-19-R-0278 |
| FE-416-95 Bldg 145 Addn Sheet 5 PMD-Default-000 PMD |
File details come from the government source that posted it.