This file is a Questions and Answers document for federal contract opportunity EAR048 - Repair Fire Alarm Systems at Eareckson Air Station Facilities, dated 06 NOV 2026.

The Government seeks to repair and standardize fire alarm systems throughout Eareckson Air Station. The existing systems consist of a combination of various antiquated conventional panels over 25 years old that are no longer supported by manufacturers. The Government intends to standardize all systems throughout the area with Monaco systems. The contract will be structured as a progressive design-build Other Transaction Agreement (OTA). The awardee will be responsible for providing and pricing independent, formally facilitated construction partnering services during design and preconstruction phases, consistent with EP 34-1-1, Partnering Playbook (2024). If phased construction is authorized, continued partnering facilitation will be addressed in applicable agreement modifications. Expected partnering deliverables include a partnering charter, facilitated workshops, and an issue-resolution process, with specific requirements to be defined in the resulting OTA agreement.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Government Response

1 Can you provide information about the existing fire alarm system? They are a combination of various systems, most are 25+ year old antiquated conventional panels not supported by the manufacturer anymore.

2 What brand is it and would we need to use the same brand for the upgrade? Intend of project is to standardized all systems throughout the area with Monaco systems.

For the planned progressive design-build OTA, does the Government anticipate using formal, independently facilitated construction partnering during design and preconstruction, and continuing into phased construction if authorized?

Yes. The Government anticipates requiring formal, independently facilitated partnering during design and preconstruction and, if phased construction is authorized, during construction. The awardee will be responsible for providing and pricing these partnering services as part of agreement performance, consistent with EP 34-1-1, Partnering Playbook (2024). Specific requirements will be included in the solicitation and resulting OTA agreement.

If so, what partnering outcomes or deliverables does the Government expect? Would the Government consider including an independent facilitator in the awardee’s design and pre-construction scope, with funding for continued facilitation addressed in later construction modifications?

The Government anticipates requiring the awardee to provide and price an independent facilitator for partnering during design and preconstruction. If phased construction is authorized, continued partnering facilitation will be addressed in the applicable agreement modification. Expected deliverables may include, but are not limited to, a partnering charter, facilitated workshops, and an issue-resolution process. Specific partnering requirements will be defined in the resulting OTA agreement.

As of 06 NOV 2026

Industry Questions EAR048 - Repair Fire Alarm Systems, Eareckson Air Station Facilities.

GOV Response