Market Research Questionnaire EAR048 Draft 23OCT26.pdf
PDF 364 KB Posted
- Solicitation number
- W911KB27RWP12
About this file
This is a Comprehensive Market Research Questionnaire and Sources Sought / Request for Information (RFI) issued by the U.S. Army Corps of Engineers, Alaska District, in pre-solicitation status.
The Government seeks expert feedback from industry partners and Project Delivery Teams to determine the optimal project delivery method and contracting vehicle for the repair and upgrade of the fire alarm system at Eareckson Air Station, located on Shemya Island, Alaska. The project involves designing and implementing a wireless fire alarm system across approximately 45 buildings to withstand sub-Arctic maritime conditions, including hurricane-force winds, high salt-spray corrosion, and severe isolation. The system must also operate without interference from high-power military radar and telemetric systems. The target budget is $27M–$33M under Sustainment, Restoration, and Modernization (SRM) funding, with a Period of Performance from FY27–FY30. Critical milestones include design start in FY27, construction start in FY28, and construction completion no later than FY30. The Government is evaluating three delivery approaches: Accelerated Design-Build to Budget (DBtB), Construction Manager at Risk (CM@Risk) under OTA, and Progressive Design-Build (PDB) under OTA.
Responses must be submitted by 16 November 2026 at 14:00 Alaska Time via online form or email to MAJ Quentin Sica and Theresa Afrank. The questionnaire requests detailed industry input across five major sections: company information and bidding intent; project-specific challenges including phasing, commissioning, remote location risks, temporary space requirements, construction duration, mobilization readiness, and design transition from wired to wireless systems; budget realism, cost drivers, and schedule risks; collaboration priorities, industry engagement interest, stipend preferences, and contract incentives; and overall delivery recommendations with evaluation strategy rationale. The document serves as a template to inform procurement strategy and does not constitute a formal solicitation or commitment to award a contract.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Comprehensive Market Research Questionnaire
Project Delivery & Acquisition Strategy
Originating Agency U.S. Army Corps of Engineers / Alaska District
Document Type Sources Sought / Request for Information (RFI) Template
Target Audience Project Delivery Teams (PDTs) & Industry Partners
Classification Unclassified / Pre-Solicitation
Market Research Questionnaire | Project Delivery & Acquisition Strategy
Table of Contents
1. Project Information Packet (PIP)
Project Overview & Constraints
2. Industry Questionnaire
Part I: Company Information & Bidding Intent
Part II: Project-Specific Challenges
1. Phasing/Turn Over/Commissioning Considerations
2. Remote Location and Environmental Risks…
3. Structuring the OTA for Success………...…………
4. Temporary Space Requirements
5. Construction Duration & Schedule Realism
6. Mobilization & Start-Work Readiness …
7. Unidentified Project Risks ………
8. Existing Design Incorporation………………………………………………………………………………….7
Part III: Budget, Cost Drivers & Schedule
1. Budget Realism
2. Primary Cost Drivers
3. Schedule/Supply Chain Risk
Part IV: Defining Value, Collaboration & Financial Drivers
1. Collaboration Priorities
2. Industry Engagement & Proprietary Meetings
3. Stipends (Honorariums) & Proposal Costs
4. Contract Incentives
5. Program Capability/Interest
Part V: Overall Delivery Recommendation
1. Recommended Project Delivery Path
2. Basis of Recommendation & Contracting Vehicle
3. Evaluation Strategy
4. Commercial Best Practices & Concerns
1. Project Information Packet (PIP)
Project Overviews & Constraints
Project Name Location Site Characterization
(EAR048) Repair Fire Alarm System Eareckson Air Station Facilities
Project is located within the Shemya Island perimeter, on a previously developed site, and in Climate Zone 6A.
Mission Statement Design and implement a Wireless Fire Alarm System in Eareckson Air Station Alaska, adapted to Sub-Arctic Maritime Conditions, hurricane-force winds, high salt-spray corrosion, severe isolation and the Eareckson Air Station Design Standards.
Facility Type & Scale Repair/upgrade site fire alarm system with wireless Fire Alarm System, approximately 45 buildings.
Primary Functional Spaces Project includes identifying ruggedized wireless architectures that can withstand extreme Aleutian weather, operate without interfering with (or being disrupted by) high-power military radar/telemetric systems, and offer simplified maintenance routines that installation staff can execute without off-island technician dispatch. The design will need to upgrade 45 buildings across Eareckson Air Station.
Funding Type SRM
Target Budget (CCL) $27M – $33M
Period of Performance FY27 – FY30
Critical Milestones Design Starts FY27, Construction Starts FY28, and Construction complete not later than FY30.
2. Industry Questionnaire
Purpose: The Government seeks your expert feedback to select the optimal project delivery method and contracting vehicle (FAR-based or OTA) for the above facilities. Please go to the following link to submit your responses https://forms.osi.apps.mil/r/DgMYxp3wcZ or email your response to MAJ Quentin Sica at Quentin.Sica@usace.army.mil and Theresa Afrank at Theresa.m.afrank@usace.army.mil by 16 November 2026 at 14:00 Alaska Time.
Accelerated Design-Build to Budget (DBtB) FAR-based delivery approach where the Government develops sufficient project definition to competitively establish a Firm-Fixed-Price before collaborative design development.
Construction Manager at Risk (CM At Risk) - OTA Project delivery method where a construction manager acts as a consultant to the owner during the design phase and transitions to a general contractor role during construction.
Progressive Design-Build (PDB) – OTA Single design-build agreement. Phase 1 collaboratively matures the design and negotiates a Guaranteed Maximum Price cost before the Government decides whether to proceed with construction.
Part I: Company Information & Bidding Intent
Company Name & CAGE Code
Point of Contact
Socioeconomic Status (Check all that apply)
☐ Large Business ☐ Small Business (SB) ☐ 8(a) Business Development Program ☐ HUBZone Small Business ☐ Service-Disabled Veteran-Owned (SDVOSB) ☐ Women-Owned Small Business (WOSB)
Bonding Capacity Single Project Limit: $[Insert Amount Here]_______________ Aggregate Limit: $[Insert Amount Here]_______________
Intent to Propose ☐ Yes as Prime ☐ Yes as Sub ☐ No ☐ Undecided https://forms.osi.apps.mil/r/DgMYxp3wcZ
Anticipated Teaming ☐ Standalone Prime ☐ Joint Venture (JV) ☐ Mentor-Protégé ☐ Subcontractor/Designer Only
Part II: Project-Specific Challenges
1. Phasing/Turn Over/ Commissioning Considerations The Government intends to supply mainline utilities up to the demarcation point for each project site. A key responsibility for the selected contractor will be to coordinate the design and construction with Government representatives to ensure the final utility installation is seamless.
To mitigate associated risks, it will be important to implement effective strategies and establish specific validation criteria during the site turnover process. Additionally, we need to consider the best approach to the commissioning process for the system—should it be performed on a per-building basis? Lastly, identifying the most effective methods to minimize gaps in fire alarm coverage will be crucial.
2. Remote Location and Environmental Risks Given the challenges of soil contamination from a wired connection between two D21s in a remote location with minimal logistical support, along with the cold, windy, and corrosive environment at Eareckson Air Station, it’s crucial to mitigate delays effectively. In what ways can the contractor prioritize reducing on-site delays caused by harsh weather? What risks do you anticipate associated with remote location, and contaminated soils during construction? What methods would you use to help mitigate these risks? What information or project requirements would you recommend be established during preconstruction to reduce these risks?
3. Structuring the OTA for Success Describe which OTA vehicle your firm feels will yield the highest probability of a completed facility at or below the budget target without compromise to project quality. What performance metrics or strategies do you recommend the Government build into an OTA to mitigate the risks of a delay or project cost increase?
4. Temporary Space Requirements For projects of these magnitudes, what is your estimated space requirement for temporary facilities such as staging, material laydown, offices, workforce parking, etc.? Furthermore, do you foresee any need for new or upgraded supporting infrastructure, such as access roads or port facilities, to support construction logistics?
5. Construction Duration & Schedule Realism What do you believe is a realistic and reasonable timeframe (in calendar days or years) to complete each projects design and construction? The project will include working in secure and classified buildings. What is your plan to accommodate working these building and do you have any suggested methods to mitigate and reduce the site impacts?
6. Mobilization & Start-Work Readiness Assuming a contract award is made, what is your firm's estimated lead time to mobilize Phase 1 (Design and Preconstruction Services) and Phase 2 (Final Design & Construction Services)?
What is the optimal time of year for a contract award to align with your mobilization and maximize the active construction season?
7. Unidentified Project Risks Outside of the challenges already identified, what other significant risks do you foresee for a project of this scale at Eareckson Air Station? What are factors that the Government should address to reduce costs or increase competition?
8. Existing Design Incorporation The project has a 100% design for a wired alarm system. What cost, schedule, constructability, or risk do you anticipate associated with joining the project and pivoting the design from a wired to a wireless alarm system? What information would you require upon joining the project to perform your preconstruction services effectively?
Part III: Budget, Cost Drivers & Schedule
1. Budget Realism Based on current market data, do the target budgets appear realistic for these facility types and scale?
2. Primary Cost Drivers What specific mission needs or functional requirements do you anticipate driving the most cost?
3. Schedule/Supply Chain Risk What systems or trades present the most significant schedule risk (e.g., long-lead MEP, local labor)?
Part IV: Defining Value, Collaboration & Financial Drivers
1. Collaboration Priorities Please rank the areas that would benefit most from early builder involvement during the design phase of the above projects (1 = Greatest Benefit, 5 = Least Benefit).
Area of Collaboration Rank (1–5)
Cost Certainty & Real-Time Estimating
Schedule Certainty & Phasing
Constructability & Quality Control
Innovation & Scope Betterments (Getting more for the money)
Overall Risk Reduction / Site Mitigations
2. Industry Engagement & Proprietary Meetings If the Government utilizes a delivery method that allows for confidential, one-on-one proprietary meetings during the solicitation phase to collaboratively discuss innovative solutions, would your firm participate?
☐ Yes ☐ No
3. Stipends (Honorariums) & Proposal Costs In highly collaborative procurement methods (like DBtB), offerors will incur design and proposal development costs. Would the Government's offer of a stipend significantly influence your decision to compete?
☐Yes ☐ No
If Yes, what is a commercially reasonable stipend amount for a project of this scale? [Insert Amount/Percentage Here] ______________________________
4. Contract Incentives What specific contract incentives would best drive innovation and maximize your firm's interest in these projects?
☐ Shared Cost Savings (e.g., within a GMP Structure)
☐ Award Fee for Quality / Innovation
☐ Other [Insert Recommendations Here] ______________________________
5. Program Capability/Interest Considering the project listed in Section 1 for Eareckson Air Station with a combined estimated value of approximately $33M:
a) Would your firm be interested in proposing as a prime contractor?
☐Yes ☐ No
b) If yes, does your firm have the necessary bonding capacity to cover the total estimated project value?
☐Yes ☐ No
c) If yes, please state your firm’s current aggregate bonding capacity. [Insert Amount Here]
Part V: Overall Delivery Recommendation
1. Recommended Project Delivery Path Considering all factors, which project delivery path is optimal for these specific projects?
(Provide a response for each project listed in Section 1 above)
☐ CM@Risk: Government needs to control the design but needs early builder collaboration.
☐ Design-Build to Budget (DBtB): Requirements are understood enough to drive a competitive (10-15%), fixed-price solution, use of proprietary meetings to advance design solutions (highly collaborative).
☐ Progressive Design-Build (PDB): Scope is highly complex/undefined. Requires a single contract to collaboratively mature the design before locking in a GMP.
2. Basis of Recommendation & Contracting Vehicle Please explain your selections above for each project. Indicate if you recommend executing this via a standard FAR-based contract or an Other Transaction Authority (OTA):
3. Evaluation Strategy For these specific projects, what evaluation criteria do you believe the Government should weigh most heavily to ensure success? (Rank top 3: 1 being most important)
Past Performance
Technical Approach/Design
Price/GMP
Key Personnel & Team Integration
Other [Insert Recommendat ons Here] ______________________________
4. Commercial Best Practices & Concerns Please provide any additional comments, overly prescriptive constraints to avoid, or commercial best practices the Government should consider.
| Table of Contents |
| 1. Project Information Packet (PIP) |
| Project Overviews & Constraints |
| 2. Industry Questionnaire |
| Accelerated Design-Build to Budget (DBtB) |
| Construction Manager at Risk (CM At Risk) - OTA |
| Progressive Design-Build (PDB) – OTA |
| 1. Phasing/Turn Over/ Commissioning Considerations |
| 2. Remote Location and Environmental Risks |
| 3. Structuring the OTA for Success |
| 4. Temporary Space Requirements |
| 5. Construction Duration & Schedule Realism |
| 6. Mobilization & Start-Work Readiness |
| 7. Unidentified Project Risks |
| 8. Existing Design Incorporation |
| Part III: Budget, Cost Drivers & Schedule |
| 1. Budget Realism |
| 2. Primary Cost Drivers |
| 3. Schedule/Supply Chain Risk |
| Part IV: Defining Value, Collaboration & Financial Drivers |
| 1. Collaboration Priorities |
| 2. Industry Engagement & Proprietary Meetings |
| 3. Stipends (Honorariums) & Proposal Costs |
| 4. Contract Incentives |
| 5. Program Capability/Interest |
| Part V: Overall Delivery Recommendation |
| 1. Recommended Project Delivery Path |
| 2. Basis of Recommendation & Contracting Vehicle |
| 3. Evaluation Strategy |
| 4. Commercial Best Practices & Concerns |
| Text1: |
| Text2: |
| Check Box3: Off |
| Check Box9: Off |
| Check Box10: Off |
| Check Box11: Off |
| Check Box12: Off |
| Check Box13: Off |
| Text14: |
| Text15: |
| Text17: |
| Text18: |
| Text19: |
| Text20: |
| Text21: |
| Text22: |
| Text23: |
| Text24: |
| Text25: |
| Text26: |
| Text27: |
| Dropdown18: [Select] |
| Dropdown19: [Select] |
| Dropdown20: [Select] |
| Dropdown21: [Select] |
| Dropdown22: [Select] |
| Group2: Off |
| Group1: Off |
| Group3: Off |
| Group4: Off |
| Text28: |
| Text29: |
| Group5: Off |
| Text30: |
| Group6: Off |
| Group7: Off |
| Group8: Off |
| Text31: |
| Text32: |
| Text33: |
| Text34: |
| Text35: |
| Text36: |
| Text37: |
| Text38: |