This document is an Amendment to a Solicitation for the Floating Breakwater Replacement project at Bar Point Harbor in Ketchikan, Alaska, issued by the U.S. Army Corps of Engineers. The amendment extends the proposal due date to 06-May-2025 at 2:00 PM and updates several key documents, including wage determinations and performance requirements for the concrete floating breakwater.

The amendment includes updated wage rates for various construction trades in Alaska, specifying minimum wage rates under Executive Orders 14026 and 13658, with rates ranging from $27.82 to $74.34 per hour depending on the trade and geographic location. The technical specifications require the contractor to provide a 960-foot long main concrete floating breakwater with 1.6 feet of freeboard and a 140-foot long entrance breakwater, both designed to attenuate waves to no greater than 1 foot in the marina. The project involves replacing existing floating breakwaters with new post-tensioned concrete modules anchored by concrete blocks and chains, with a 50-year design life requirement and specific performance criteria for wave transmission, wind loading, and structural integrity.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

KET005

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to incorporate the follow ing changes:

1. Extend Proposal Due Date.

2. Update 00 73 46 Wage Determinations.

3. Update Section 01 91 41, Concrete Floating Breakw ater Performance Requirements, paragraphs 1.4.2.1 and 1.5 .

4. Include Bidder Inquiry Report.

The point of contact for this amendment is Jennifer Gosh at Jennifer.Gosh@usace.army.mil.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 18

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-Apr-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911KB25R0018

X 9B. DATED (SEE ITEM 11)

28-Feb-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-Apr-2025

CODE

U.S. ARMY ENGINEER DISTRICT, AK

CEPOA-CT (W911KB)

2204 TALLEY AVENUE

JBER AK 99506-0898

W911KB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911KB25R0018

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 11 00 - STANDARD FORM (SF) 1442

The required response date/time has changed from 29-Apr-2025 02:00 PM to 06-May-2025 02:00 PM.

SECTION 00 73 46 - WAGE DETERMINATIONS SCHEDULES

The following have been modified:

"General Decision Number: AK20250001 04/18/2025

Superseded General Decision Number: AK20240001

State: Alaska

Construction Types: Building and Heavy

Counties: Alaska Statewide.

BUILDING AND HEAVY CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all|

|extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2025. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/03/2025 1 01/31/2025 2 03/14/2025 3 04/18/2025

ASBE0007-006 02/27/2023

Rates Fringes

Asbestos Workers/Insulator (includes application of all insulating materials protective coverings, coatings and finishings to all types of mechanical systems).........................$ 41.35 16.46

HAZARDOUS MATERIAL HANDLER

(includes preparation, wetting, stripping, removal scrapping, vacuming, bagging, and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems).........$ 37.38 19.55

BOIL0502-002 01/01/2024

Rates Fringes

BOILERMAKER......................$ 51.08 33.04

BRAK0001-002 07/01/2023

Rates Fringes

Bricklayer, Blocklayer, Stonemason, Marble Mason, Tile Setter, Terrazzo Worker.....$ 42.01 19.20 Tile & Terrazzo Finisher.........$ 35.84 19.20

* CARP1281-001 04/01/2025

Rates Fringes

CARPENTER

Including Lather and Drywall Hanging.............$ 50.79 26.42

CARP1281-002 09/01/2024

Rates Fringes

MILLWRIGHT.......................$ 55.42 27.08

* CARP2520-003 04/01/2025

Rates Fringes

Diver Stand-by....................$ 53.03 26.42 Tender......................$ 52.03 26.42 Working.....................$ 92.83 26.42 Piledriver Piledriver; Skiff Operator and Rigger..................$ 48.72 26.42 Sheet Stabber...............$ 48.72 26.42 Welder......................$ 54.28 26.42

DEPTH PAY PREMIUM FOR DIVERS BELOW WATER SURFACE:

50-100 feet $1.00 per foot 101 feet and deeper $2.00 per foot

ENCLOSURE PAY PREMIUM WITH NO VERTICAL ASCENT:

5-50 FEET $1.00 PER FOOT/DAY

51-100 FEET $2.00 PER FOOT/DAY

101 FEET AND ABOVE $3.00 PER FOOT/DAY

SATURATION DIVING:

The standby rate applies until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. the diver rate shall be paid for all saturation hours.

WORK IN COMBINATION OF CLASSIFICATIONS:

Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.

* ELEC1547-004 04/01/2025

Rates Fringes

CABLE SPLICER....................$ 53.44 3%+28.67

ELECTRICIAN......................$ 53.44 3%+28.67

* ELEC1547-005 04/01/2025

Line Construction

Rates Fringes

CABLE SPLICER....................$ 74.34 3%+33.47

Linemen (Including Equipment Operators, Technician)...........$ 72.59 3%+33.47 Powderman........................$ 70.59 3%+33.47

TREE TRIMMER.....................$ 42.23 3%+28.83

ELEV0019-002 01/01/2025

Rates Fringes

ELEVATOR MECHANIC................$ 71.44 38.435+a+b

FOOTNOTE:

a. Employer contributes 8% of the basic hourly rate for over 5 year's service and 6% of the basic hourly rate for 6 months to 5 years' of service as vacation paid credit.

b. Eight paid holidays:

New Year's Day; Memorial Day; Independence Day;

Labor Day; Veteran's Day; Thanksgiving Day; Friday after Thanksgiving, and Christmas Day

ENGI0302-002 01/01/2025

Rates Fringes

POWER EQUIPMENT OPERATOR

GROUP 1.....................$ 53.23 29.50

GROUP 1A....................$ 55.33 29.50

GROUP 2.....................$ 52.32 29.50

GROUP 3.....................$ 51.46 29.50

GROUP 4.....................$ 44.06 29.50

TUNNEL WORK

GROUP 1....................$ 58.55 29.50

GROUP 1A...................$ 60.86 29.50

GROUP 2....................$ 57.55 29.50

GROUP 3....................$ 56.60 29.50

GROUP 4....................$ 48.47 29.50

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Asphalt Roller: Breakdown, Intermediate, and Finish; Back Filler; Barrier Machine (Zipper); Beltcrete with power pack and similar conveyors; Bending Machine;

Boat Coxwains; Bulldozers; Cableways, Highlines and Cablecars; Cleaning Machine; Coating Machine; Concrete Hydro Blaster; Cranes-45 tons and under or 150 foot boom and under (including jib and attachments): (a) Hydralifts or Transporters, all track or truck type,(b) Derricks;

Crushers; Deck Winches-Double Drum; Ditching or Trenching Machine (16 inch or over); Drilling Machines, core, cable, rotary and exploration; Finishing Machine Operator, Concrete Paving, Laser Screed, Sidewalk, Curb and Gutter Machine; Helicopters; Hover Craft, Flex Craft, Loadmaster, Air Cushion, All Terrain Vehicle, Rollagon, Bargecable, Nodwell, and Snow Cat; Hydro Ax: Feller Buncher and similar; Loaders (2 1/2 yards through 5 yards, including all attachments): Forklifts with telescopic boom and swing attachment, Overhead and front end, 2 1/2 yards through 5 yards, Loaders with forks or pipe clamps; Loaders, elevating belt type, Euclid and similar types; Mechanics, Bodyman; Micro Tunneling Machine; Mixers: Mobile type w/hoist combination; Motor Patrol Grader; Mucking Machines:

Mole, Tunnel Drill, Horizontal/Directional Drill Operator, and/or Shield; Operator on Dredges; Piledriver Engineers, L. B. Foster, Puller or similar Paving Breaker; Power Plant, Turbine Operator, 200 k.w. and over (power plants or combination of power units over 300 k.w.); Scrapers-through 40 yards; Service Oiler/Service Engineer; Sidebooms-under 45 tons; Shot Blast Machine; Shovels, Backhoes, Excavators with all attachments, and Gradealls (3 yards and under), Spreaders, Blaw Knox, Cedarapids, Barber Greene, Slurry Machine; Sub-grader (Gurries, Reclaimer, and similar types); Tack tractor; Truck mounted Concrete Pumps, Conveyor, Creter; Water Kote Machine; Unlicensed off road hauler

GROUP 1A: Camera/Tool/Video Operator (Slipline), Cranes-over 45 tons or 150 foot (including jib and attachments): (a) Clamshells and Draglines (over 3 yards),

(b) Tower cranes; Licensed Water/Waste Water Treatment Operator; Loaders over 5 yds.; Certified Welder, Electrical Mechanic, Camp Maintenance Engineer, Mechanic (over 10,000 hours); Motor Patrol Grader, Dozer, Grade Tractor, Roto-mill/Profiler (finish: when finishing to final grade and/or to hubs, or for asphalt); Power Plants: 1000 k.w.

and over; Quad; Screed; Shovels, Backhoes, Excavators with all attachments (over 3 yards), Sidebooms over 45 tons;

Slip Form Paver, C.M.I. and similar types; Scrapers over 40 yards;

GROUP 2: Boiler-fireman; Cement Hog and Concrete Pump Operator; Conveyors (except as listed in group 1); Hoist on steel erection; Towermobiles and Air Tuggers;

Horizontal/Directional Drill Locator;Licensed Grade Technician; Loaders, (i.e., Elevating Grader and Material Transfer Vehicle); Locomotives: rod and geared engines;

Mixers; Screening, Washing Plant; Sideboom (cradling rock drill regardless of size); Skidder; Trencing Machine under 16 inches; Waste/ Waste Water Treatment Operator.

GROUP 3: ""A"" Frame Trucks, Deck Winches: single power drum;

Bombardier (tack or tow rig); Boring Machine; Brooms-power;

Bump Cutter; Compressor; Farm tractor; Forklift, industrial type; Gin Truck or Winch Truck with poles when used for hoisting; Grade Checker and Stake Hopper; Hoist, Air Tuggers, Elevators; Loaders: (a) Elevating-Athey, Barber Green and similar types (b) Forklifts or Lumber Carrier (on construction job site) (c) Forklifts with Tower (d) Overhead and Front-end, under 2 1/2 yds. Locomotives:Dinkey (air, steam, gas and electric) Speeders; Mechanics (light duty); Oil, Blower Distribution; Post Hole Diggers, mechanical; Pot Fireman (power agitated); Power Plant, Turbine Operator, under 200 k.w.; Pumps-water; Roller-other than Plantmix; Saws, concrete; Skid Steer with all attachments; Straightening Machine; Tow Tractor

GROUP 4: Rig Oiler/Crane Assistant Engineer;Parts and Equipment Coordinator; Swamper (on trenching machines or shovel type equipment); Spotter; Steam Cleaner; Drill Helper.

FOOTNOTE: Groups 1-4 receive 10% premium while performing tunnel or underground work. Rig Oiler/Crane Assistant Engineer shall be required on cranes over 85 tons or over 100 feet of boom.

IRON0751-003 07/01/2024

Rates Fringes

IRONWORKER

BENDER OPERATOR.............$ 44.99 38.98

BRIDGE, STRUCTURAL,

ORNAMENTAL, REINFORCING

MACHINERY MOVER, RIGGER,

SHEETER, STAGE RIGGER,

BENDER OPERATOR.............$ 44.99 38.98

FENCE, BARRIER INSTALLER....$ 41.49 38.98

GUARDRAIL INSTALLERS........$ 42.49 38.98

GUARDRAIL LAYOUT MAN........$ 42.23 38.98

HELICOPTER, TOWER...........$ 45.99 38.98

LABO0341-001 04/01/2024

Rates Fringes

LABORER (South of the 63rd Parallel & West of Longitude 138 Degrees)

GROUP 1.....................$ 38.25 33.11

GROUP 2.....................$ 39.25 33.11

GROUP 3.....................$ 40.15 33.11

GROUP 3A....................$ 44.28 33.11

GROUP 3B....................$ 50.11 29.06

GROUP 4.....................$ 27.82 33.11

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 42.08 33.11

GROUP 2....................$ 43.18 33.11

GROUP 3....................$ 44.17 33.11

GROUP 3A...................$ 48.71 33.11

GROUP 3B...................$ 55.12 29.06

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke Setters, Hook Tender, Rigger, Signalman; Concrete Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos (limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or Power Tools; Portable or Chemical Toilet Serviceman; Pump Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tenders; Scaffold Building and Erecting; Slurry Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine Operator; Green Cutter (dam work); Gunnite Operator; Hod Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer Plant Maintenance Man; Thermal Plastic Applicator; Timber Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill

Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers.

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

LABO0942-001 04/01/2024

Rates Fringes

Laborers: North of the 63rd Parallel & East of Longitude 138 Degrees

GROUP 1.....................$ 38.25 33.11

GROUP 2.....................$ 39.25 33.11

GROUP 3.....................$ 40.15 33.11

GROUP 3A....................$ 44.03 33.11

GROUP 3B....................$ 49.61 29.06

GROUP 4.....................$ 27.82 33.11

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 42.08 33.11

GROUP 2....................$ 43.18 33.11

GROUP 3....................$ 44.17 33.11

GROUP 3A...................$ 48.43 33.11

GROUP 3B...................$ 54.57 29.06

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush

Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke Setters, Hook Tender, Rigger, Signalman; Concrete Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos (limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or Power Tools; Portable or Chemical Toilet Serviceman; Pump Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tenders; Scaffold Building and Erecting; Slurry Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine Operator; Green Cutter (dam work); Gunnite Operator; Hod Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer Plant Maintenance Man; Thermal Plastic Applicator; Timber Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers.

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

PAIN1959-001 07/01/2024

NORTH OF THE 63RD PARALLEL

Rates Fringes

PAINTER

BRUSH/ROLLER PAINT OR WALL

COVERER.....................$ 40.33 26.17

TAPING, TEXTURING,

STRUCTURAL PAINTING,

SANDBLASTING, POT TENDER,

FINISH METAL, SPRAY,

BUFFER OPERATOR, RADON

MITIGATION, LEAD BASED

PAINT ABATEMENT, HAZARDOUS

MATERIAL HANDLER............$ 40.85 26.17

PAIN1959-002 07/01/2024

SOUTH OF THE 63RD PARALLEL

Rates Fringes

PAINTER

General Painter.............$ 35.97 28.52 Industrial Painter..........$ 37.32 28.52 Taper / Paper & Vinyl Hanger......................$ 37.22 28.52

PAIN1959-003 07/01/2024

NORTH OF THE 63RD PARALLEL

GLAZIER..........................$ 44.54 29.68

PAIN1959-004 07/01/2023

Rates Fringes

FLOOR LAYER: Carpet.............$ 39.86 15.87

PAIN1959-006 07/01/2024

SOUTH OF THE 63RD PARALLEL

Rates Fringes

GLAZIER..........................$ 45.20 28.32

PLAS0528-006 06/01/2024

Rates Fringes

PLASTERER

North of the 63rd parallel..$ 52.50 20.67 South of the 63rd parallel..$ 52.50 20.67

PLAS0528-007 04/01/2023

Rates Fringes

CEMENT MASON/CONCRETE FINISHER

North of the 63rd parallel..$ 44.43 22.13 South of the 63rd parallel..$ 44.43 22.13

PLUM0262-002 01/01/2023

East of the 141st Meridian

Rates Fringes

Plumber; Steamfitter.............$ 41.50 27.62

PLUM0367-002 07/01/2021

South of the 63rd Parallel

Rates Fringes

Plumber; Steamfitter.............$ 41.00 27.95

PLUM0375-002 07/01/2024

North of the 63rd Parallel

Rates Fringes

Plumber; Steamfitter.............$ 51.66 32.90

PLUM0669-002 01/01/2025

SPRINKLER FITTER.................$ 56.61 31.39

ROOF0189-006 04/01/2024

Rates Fringes

ROOFER...........................$ 49.62 18.53

SHEE0023-003 07/01/2024

South of the 63rd Parallel

Rates Fringes

SHEET METAL WORKER...............$ 48.75 30.14

SHEE0023-004 07/01/2024

North of the 63rd Parallel

Rates Fringes

SHEET METAL WORKER...............$ 54.00 30.52

TEAM0959-003 01/01/2025

Rates Fringes

TRUCK DRIVER

GROUP 1.....................$ 51.58 26.43

GROUP 1A....................$ 53.05 26.43

GROUP 2.....................$ 50.12 26.43

GROUP 3.....................$ 49.17 26.43

GROUP 4.....................$ 48.50 26.43

GROUP 5.....................$ 47.62 26.43

GROUP 1: Semi with Double Box Mixer; Dump Trucks (including rockbuggy and trucks with pups) over 40 yards up to and including 60 yards; Deltas, Commanders, Rollogans and similar equipment when pulling sleds, trailers or similar equipment; Boat Coxswain; Lowboys including attached trailers and jeeps, up to and including 12 axles; Ready-mix over 12 yards up to and including 15 yards); Water Wagon (250 Bbls and above); Tireman, Heavy Duty/Fueler

GROUP 1A: Dump Trucks (including Rockbuggy and Trucks with pups) over 60 yards up to and including 100 yards; Jeeps (driver under load)

GROUP 2: Turn-O-Wagon or DW-10 not self-loading; All Deltas, Commanders, Rollogans, and similar equipment; Mechanics;

Dump Trucks (including Rockbuggy and Trucks with pups) over 20 yards up to and including 40 yards; Lowboys including attached trailers and jeeps up to and including 8 axles;

Super vac truck/cacasco truck/heat stress truck; Ready-mix over 7 yards up to and including 12 yards; Partsman;

Stringing Truck

GROUP 3: Dump Trucks (including Rockbuggy and Trucks with pups) over 10 yards up to and including 20 yards; batch trucks 8 yards and up; Oil distributor drivers; Oil Distributor Drivers; Trucks/Jeeps (push or pull); Traffic Control Technician

GROUP 4: Buggymobile; Semi or Truck and trailer; Dumpster;

Tireman (light duty); Dump Trucks (including Rockbuggy and Truck with pups) up to and including 10 yards; Track Truck Equipment; Grease Truck; Flat Beds, dual rear axle; Hyster Operators (handling bulk aggregate); Lumber Carrier; Water Wagon, semi; Water Truck, dual axle; Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted ""A"" Frame manufactured rating over 5 tons; Bull Lifts and Fork Lifts with Power Boom and Swing attachments, over 5 tons; Front End Loader with Forks; Bus Operator over 30 passengers; All Terrain Vehicles; Boom Truck/Knuckle Truck over 5 tons; Foam Distributor Truck/dual axle; Hydro-seeders, dual axle;

Vacuum Trucks, Truck Vacuum Sweepers; Loadmaster (air and water); Air Cushion or similar type vehicle; Fire Truck/Ambulance Driver; Combination Truck-fuel and grease;

Compactor (when pulled by rubber tired equipment); Rigger (air/water/oilfield); Ready Mix, up to and including 7 yards;

GROUP 5: Gravel Spreader Box Operator on Truck; Flat Beds, single rear axle; Boom Truck/Knuckle Truck up to and including 5 tons; Pickups (Pilot Cars and all light duty vehicles); Water Wagon (Below 250 Bbls); Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted ""A"" Frame, manufactured rating 5 tons and under; Bull Lifts and Fork Lifts (fork lifts with power broom and swing attachments up to and including 5 tons); Buffer Truck; Tack Truck; Farm type Rubber Tired Tractor (when material handling or pulling wagons on a construction project); Foam Distributor, single axle; Hydro-Seeders, single axle; Team Drivers (horses, mules and similar equipment); Fuel Handler (station/bulk attendant); Batch Truck, up to and including 7 yards;

Gear/Supply Truck; Bus Operator, Up to 30 Passengers;

Rigger/Swamper

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.

Union Rate Identifiers

A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.

0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.

Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.

Union Average Rate Identifiers

The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:

UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.

The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.

A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.

Survey Rate Identifiers

The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.

?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).

State Adopted Rate Identifiers

The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.

The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.

WAGE DETERMINATION APPEALS PROCESS

1) Has there been an initial decision in the matter? This can be:

a) a survey underlying a wage determination

b) an existing published wage determination

c) an initial WHD letter setting forth a position on a wage determination matter

d) an initial conformance (additional classification and rate) determination

On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:

Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.

Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).

Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210.

END OF GENERAL DECISION"

(End of Summary of Changes)

AMD006 FLOATING BREAKWATER REPLACEMENT, BAR POINT HARBOR KET005

KETCHIKAN, ALASKA

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 91 41

CONCRETE FLOATING BREAKWATER PERFORMANCE REQUIREMENTS

04/21

PART 1 GENERAL

1.1 SCOPE

1.2 REFERENCES

1.3 SUBMITTALS

1.4 QUALITY CONTROL

1.4.1 Manufacturer Qualifications

1.4.2 Concrete Floating Breakwater Loading

1.4.2.1 Wave Loading - Installed Position

1.4.2.2 Loading - Construction Related Activities

1.4.2.3 Transient Mooring Wind Loading

1.4.2.4 Extreme Wind Loading

1.4.2.5 Vertical Live Load Capacity

1.4.3 Concrete Floating Breakwater Performance

1.4.3.1 Wave Transmission - Installed Position

1.4.3.2 Draft Restrictions

1.4.4 Concrete Floating Breakwater Anchor Requirements

1.5 DESIGN REQUIREMENTS

1.5.1 Precast Concrete Floating Breakwater Design and Anchorage

Calculations and Drawings

1.5.2 Construction Plan

1.5.3 Shop Drawings

1.6 DESIGN CRITERIA REFERENCES

1.7 QUALITY REQUIREMENTS

1.8 TURN OVER REQUIREMENTS

1.8.1 As-Built Survey

PART 2 PRODUCTS

2.1 CONCRETE

2.1.1 Concrete Durability Calculations

2.1.2 Concrete Reinforcement

2.2 CONCRETE EMBEDMENTS

2.3 STRESSING TENDONS AND ACCESSORIES

2.4 ANCHORING SYSTEM

2.5 CONCRETE FLOATING BREAKWATER OUTFITTING

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 91 41 Page 1

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 91 41 Page 2

SECTION 01 91 41

CONCRETE FLOATING BREAKWATER PERFORMANCE REQUIREMENTS

04/21

PART 1 GENERAL

1.1 SCOPE

The work includes the provision of precast, concrete floating breakwater modules herein referred to as concrete floating breakwater, and all other items relating to the concrete floating breakwater system including the anchor system. Precast floating breakwater shall be the product of a manufacturer specializing in the production of precast concrete floating breakwaters with a minimum of 3 projects and 15 -years of experience in the manufacture of precast concrete floating breakwaters.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 1-300-02 (2014, with Change 2, 2019) Unified Facilities Guide Specifications (UFGS) Format Standard

UFC 3-201-01 (2018) Civil Engineering

UFC 3-220-01 (2012) Geotechnical Engineering

UFC 3-301-01 (2019) Structural Engineering

UFC 4-150-06 (2010) Military Harbors and Coastal Facilities

UFC 4-152-01 (2017) Design: Piers and Wharves

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction Plan ; G

SD-02 Shop Drawings

SECTION 01 91 41 Page 3

Shop Drawings ; G

Design Drawings ; G

SD-05 Design Data

Calculations ; G

Concrete durability calculations ; G

SD-07 Certificates

Manufacturer Qualifications ; G

SD-11 Closeout Submittals

As-Built Survey ; G

1.4 QUALITY CONTROL

The following requirements shall be the minimum acceptable performance requirements for the concrete floating breakwaters.

1.4.1 Manufacturer Qualifications

Manufacturer must supply documentation confirming 15 years of experience in the production of precast concrete floating breakwaters.

1.4.2 Concrete Floating Breakwater Loading

1.4.2.1 Wave Loading - Installed Position

A significant wave AM006.... estimated at....AM006 (Hs) = AM006....5.2....AM006 feet with a maximum period of AM006....3.1....AM006 seconds ( AM006.... 50 ....AM006 -year return period) shall be used for the wave attenuation calculations. The AM006.... 50....AM006 -year return significant wave approaching the Main Attenuator at 64 degrees from perpendicular and the Entrance Attenuator at 30 degrees from perpendicular be attenuated to a significant wave height of 1 ft. or less directly behind the attenuators. A significant wave AM006.... estimated at....AM006 (Hs)= 5.2 feet with a maximum period of 3.1 seconds (50-year return period) shall be used for the structural design of the concrete floating breakwater. The minimum design load from this wave AMD006....deleted text....AMD006 shall be used in combination with the transient mooring wind load indicated below. As a minimum, a multiplier of 1.67 shall be used to adjust wave height to H1/100 for all concrete floating breakwater internal structural design requirements. AM006... All estimated parameters for the wave attenuation and structural analyses for the concrete floating breakwater shall be validated by the manufacturer's designer and submitted for approval....AM006

1.4.2.2 Loading - Construction Related Activities

The concrete floating breakwater design shall include provision for all construction related activities such as handling, transportation, and site deployment.

SECTION 01 91 41 Page 4

1.4.2.3 Transient Mooring Wind Loading

The concrete floating breakwater shall not be designed for transient mooring.

1.4.2.4 Extreme Wind Loading

The concrete floating breakwater shall be designed for winds blowing perpendicular to the length of the concrete floating breakwater of 123 mph for 3 seconds. Effects of icing may be disregarded as accumulation of ice shall be offset by a corresponding decrease in freeboard.

1.4.2.5 Vertical Live Load Capacity

The uniform live load capacity of the concrete floating breakwater shall not be less than 100 psf. Such loading shall be continuous over the entire deck surface, and alternatively to occur in any combination of unbalanced conditions. The concrete floating breakwater shall be designed to carry a 400-pound point load applied at any point on the breakwater.

1.4.3 Concrete Floating Breakwater Performance

1.4.3.1 Wave Transmission - Installed Position

The concrete floating breakwater shall limit the transmitted wave to no greater than 1 foot on the harbor side in the region of the marina behind the main breakwater as indicated on Drawing C-101 under all incident wave conditions indicated above.

1.4.3.2 Draft Restrictions

No known draft restrictions exist at the proposed breakwater locations.

1.4.4 Concrete Floating Breakwater Anchor Requirements

The design of the concrete floating breakwater shall accommodate concrete anchor blocks and chain. Minor variations shall be considered acceptable, however, a proposal for a concrete floating breakwater design requiring a major departure from the anchoring scheme shown shall not be accepted.

Flexible anchoring systems shall not be considered.

1.5 DESIGN REQUIREMENTS

The main concrete floating breakwater material shall be of post-tensioned concrete fully encapsulated by concrete wall construction with minimum wall thickness of 6 inches. All exposed embedded metal shall be stainless steel. The configuration shall be such as to provide a 960 foot long concrete floating breakwater, with a minimum of 1.6 feet of freeboard and a 140-foot long concrete floating breakwater at the harbor entrance with

1.6 foot of freeboard. The width and draft and details shall be sufficient to achieve a 1-foot attenuated wave transmission to the marina, as shown on Drawing C-101, under the design wave event. The entrance breakwater shall be of the same design as the main breakwater. The anchorage system is designed for a tidal range from MLLW to MHHW with wave loads as shown on Drawing G-003. The system will be capable of accommodating a range of water levels from EL 21.0 (ft MLLW) to El -5.5 (ft MLLW). Deviation from the width, depth, anchor and chain layout or any other design consideration shown in the contract documents shall be documented and incorporated into the contractor's shop drawings and

SECTION 01 91 41 Page 5 calculations. All design drawings and calculations shall be stamped by a AMD006....deleted text....AMD006 registered professional engineer. While it is understood that some designs may be proprietary, full disclosure of all calculations required to fully demonstrate the performance and safety of the concrete floating breakwater for all listed environmental and loading conditions is required. Proprietary information will be protected and will not be made available to the public. Calculations shall be presented in a fully coordinated manner allowing a coastal engineer reviewer to readily understand and follow the calculations. Calculation packages submitted which require reviewers to perform parallel calculations to produce numbers or generate understanding shall not be considered acceptable.

Seismic design is not required for this project.

1.5.1 Precast Concrete Floating Breakwater Design and Anchorage Calculations and Drawings

Contractor shall submit stamped design calculations and design drawings of the Concrete Floating Breakwater for review and approval including anchoring system design calculations. Calculations shall demonstrate how the proposed design meets the requirements of the specification and achieves a 50 year design life.

Concrete for the precast concrete floating units shall conform to the requirements of Section 03 31 30 MARINE CONCRETE.

The Contractor is required to submit design life calculations showing this requirement is achieved with their design accounting for local conditions, concrete mix design, concrete cover, reinforcement material, admixtures, coatings, and anticipated degree of cracking. Acceptable software for design life modeling include:

a. Life-365, www.life-365.org

b. ConcreteWorks, www.txdot.gov/inside-txdot/division/information-technology/ engineering-software.html

c. Stadium, www.simcotechnologies.com/what-we-do/stadium-technology-portfolio

1.5.2 Construction Plan

Contractor shall submit a Construction Plan for review and approval. The Construction Plan shall demonstrate how the Contractor plans to execute the removal of the existing floating breakwater and anchoring system and install the new floating breakwater system while allowing marina operations and providing marina protection.

1.5.3 Shop Drawings

Contractor shall submit shop drawings for the Precast Concrete Breakwater for review and approval including the concrete units, the attachment system, the anchorage systems, the concrete embedment's, and the lifting inserts and devices.

SECTION 01 91 41 Page 6

1.6 DESIGN CRITERIA REFERENCES

All work shall be in accordance with the latest edition of the following references and other applicable and pertinent codes as of the date of award of the contract. Referenced documents include additional references that are applicable to this project. The most stringent requirement shall govern when discrepancies occur, unless otherwise directed by the Contracting Officer.

UFC 1-300-02 , Unified Facilities Guide Specification Format Standard

UFC 3-201-01 , Civil Engineering

UFC 3-220-01 , Geotechnical Engineering

UFC 3-301-01 , Structural Engineering

UFC 4-150-06 , Military Harbors and Coastal Facilities

UFC 4-152-01 , Design: Piers and Wharves

Most current version of ACI 318, Building Code Requirements for Structural Concrete and Commentary

Most current version of AISC Steel Design Manual

Unified Facilities Criteria (UFC) are available at the following website: http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4

1.7 QUALITY REQUIREMENTS

The concrete floating breakwater will be placed in service in a harsh marine environment at Bar Point Harbor in Ketchikan, Alaska. The corrosion typical of marine environments is present as well as a high number of annual freeze-thaw cycles. The materials selected for use in the concrete floating breakwater shall be such as to provide for a minimum 50-year service life with only minor maintenance. Minor maintenance is defined as maintenance required in the Operations and Maintenance Manual for wearing parts such as connections between concrete floating breakwater segments and connection to marine chains. Acceptance of alternate designs shall be dependent on providing documentation of similar structures, in similar environmental conditions, which have been in service for a time period approaching or exceeding 15 years, with a documented record of minor maintenance. Contractor proposed designs shall include a minimum of three references of owners or operators of facilities where similar concrete floating breakwaters, in similar environmental conditions, have been in service for a minimum of 15 years.

Multiple breakwater units are specified and shall be match-cast to ensure that they may be properly assembled and post-tensioned. If post-tensioning is not accomplished at the precast concrete plant, the precast plant shall be certified by the PCI Plant Certification Program for Category C1 work for casting of concrete floating breakwater modules.

PCI Plant quality control program records shall be available for review.

If multiple units are not post-tensioned at the precast concrete plant the assembly/post-tensioning plan shall be included as part of the professional engineer's stamped design drawings and calculations.

Contractor is required to demonstrate by test results or supporting

SECTION 01 91 41 Page 7 calculations how the concrete floating breakwater articulation joints and chain connections have the durability to meet the design life requirement through the use of corrosion and fatigue resistant material selection, adequate reserve material to offset material loss or proper detailing and maintenance requirements as documented in the Operations and Maintenance Manual.

1.8 TURN OVER REQUIREMENTS

The concrete floating breakwater shall be turned over to the United States Army Corps of Engineers, Alaska District fully assembled and anchored in the correct location. Any field assembly shall be accomplished in compliance with EM 385-1-1 .

1.8.1 As-Built Survey

Contractor shall submit an As-Built Survey for review and approval. See Section 31 09 13.00 29 for the survey requirements. The As-Built Survey shall identify the center locations of all anchor blocks and the end points for each concrete floating breakwater unit. Sequence the survey data collection of the installed anchor blocks prior to final assembly/installation of the concrete floating breakwaters to ensure proper horizontal alignment as indicated in the drawings.

PART 2 PRODUCTS

2.1 CONCRETE

2.1.1 Concrete Durability Calculations

Contractor shall submit durability calculations for the Precast Concrete Floating Breakwater for review and approval. The durability calculations must meet a 50-year design life.

2.1.2 Concrete Reinforcement

Concrete reinforcement, cover, and mix admixtures shall be utilized to achieve a minimum design life of 50 years in the marine environment.

2.2 CONCRETE EMBEDMENTS

Concrete embedment's shall be stainless steel 316L or approved material.

Mild steel or painted mild steel embedment's will not be accepted.

2.3 STRESSING TENDONS AND ACCESSORIES

Concrete post-tensioning strands and accessories shall be designed to resist installation loads and environmental loads in the installed configuration.

2.4 ANCHORING SYSTEM

Anchoring system including concrete blocks with reinforcing bars, stud link anchor chain, and chain shackle shall be as shown in the contract drawings, unless the contractor’s concrete floating breakwater design is outside +/- 5 percent from the dimensions shown (length, width, freeboard,and draft).

SECTION 01 91 41 Page 8

2.5 CONCRETE FLOATING BREAKWATER OUTFITTING

Concrete floating breakwaters shall be outfitted with a rub rail on each side full length and at each end, and equivalent harbor lights and signage supports as the existing facility including:

Day beacon: at the eastern end of the main breakwater.

Coordinate signage requirements with the U.S. Coast Guard.

PART 3 EXECUTION

Not used

-- End of Section --

SECTION 01 91 41 Page 9

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 91 41 Page 10

SF30
Section 00 73 46 Wage Determinations Schedules

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .