This is a solicitation for repair and renovation work at Fort Wainwright, Alaska. The solicitation seeks proposals to correct building deficiencies, update HVAC DDC controls, provide new ceiling tiles and flooring, paint walls, install LED lighting and fans, repair exterior doors and EFIS, repair mechanical and sewage systems, add washer/dryer connections and convert rooms at Barracks B3207. Proposals are due through the PIEE system by 1 August 2023. The work includes phased repairs to the east and west wings while maintaining building systems for occupied areas. The contractor must begin physical work by 1 October 2023 and any awarded contract will be C2 DO rated for national defense and energy programs.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
FTW459 REPAIR PP BARRACKS B3207, FORT WAINWRIGHT, ALASKA
a. This amendment provides changes to the solicitation as indicated on the continuation pages of this document
b. The proposal due date has been extended to 2:00 PM AKST, 1 August 2023
c. YOU ARE REQUIRED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE SIDE OF THIS STANDARD FORM 1442.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Jul-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911KB23R0010
X 9B. DATED (SEE ITEM 11)
17-May-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-Jul-2023
CODE
U.S. ARMY ENGINEER DISTRICT, AK
CEPOA-CT (W911KB)
2204 TALLEY AVENUE
JBER AK 99506-0898
W911KB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
a. The following drawings are substituted for the superseded documents/sections:
NONE
b. The following revised documents/sections are substituted for the superseded documents/sections. The identifier “AM#0005” appears before and after new and/or revised materials, except as noted below.
NOTE: Revisions within the following documents do not contain the above referenced identifiers:
SECTION 00 11 00 – STANDARD FORM 1442, BLOCK 13
– The required response date/time has changed to 1 August 2023 by 2:00 pm AKDT
SECTION 00 73 46 – WAGE DETERMINATIONS
– Replaced with AK1, dated 21 July 2023
c. The following sections are deleted:
d. The following documents are added:
e. The following revisions are incorporated:
f. Other:
Additional questions and clarification have been added.
(End of Summary of Changes)
ALL OTHER TERMS AND CONDITIONS SHALL REMAIN THE SAME.
"General Decision Number: AK20230001 07/21/2023
Superseded General Decision Number: AK20220001
State: Alaska
Construction Types: Building and Heavy
Counties: Alaska Statewide.
BUILDING AND HEAVY CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).
|If the contract is entered |. Executive Order 14026 |
|into on or after January 30, | generally applies to the |
|2022, or the contract is | contract. |
|renewed or extended (e.g., an |. The contractor must pay |
|option is exercised) on or | all covered workers at |
|after January 30, 2022: | least $16.20 per hour (or |
| | the applicable wage rate |
| | listed on this wage |
| | determination, if it is |
| | higher) for all hours |
| | spent performing on the |
| | contract in 2023. |
|If the contract was awarded on|. Executive Order 13658 |
|or between January 1, 2015 and| generally applies to the |
|January 29, 2022, and the | contract. |
|contract is not renewed or |. The contractor must pay all|
|extended on or after January | covered workers at least |
|30, 2022: | $12.15 per hour (or the |
| | applicable wage rate listed|
| | on this wage determination,|
| | if it is higher) for all |
| | hours spent performing on |
| | that contract in 2023. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the
Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date
0 01/06/2023
1 01/13/2023
2 01/27/2023
3 04/14/2023
4 05/05/2023
5 05/19/2023
6 06/23/2023
7 07/21/2023
ASBE0007-006 06/01/2021
Rates Fringes
Asbestos Workers/Insulator
(includes application of all insulating materials protective coverings, coatings and finishings to all types of mechanical systems).........................$ 38.68 21.57
HAZARDOUS MATERIAL HANDLER
(includes preparation, wetting, stripping, removal scrapping, vacuming, bagging, and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems).........$ 37.38 19.55
BOIL0502-002 01/01/2021
BOILERMAKER......................$ 47.03 30.59
BRAK0001-002 07/01/2020
Bricklayer, Blocklayer, Stonemason, Marble Mason, Tile Setter, Terrazzo Worker.....$ 42.16 19.67
Tile & Terrazzo Finisher.........$ 35.99 19.67
CARP1281-001 09/01/2022
CARPENTER
Including Lather and
Drywall Hanging.............$ 43.34 28.86
CARP1281-002 09/01/2022
MILLWRIGHT.......................$ 46.48 24.32
CARP2520-003 09/01/2022
Diver
Stand-by....................$ 47.65 28.32
Tender......................$ 46.65 28.32
Working.....................$ 87.45 28.32
Piledriver
Piledriver; Skiff Operator and Rigger..................$ 38.34 26.51
Sheet Stabber...............$ 38.34 26.51
Welder......................$ 43.90 26.51
DEPTH PAY PREMIUM FOR DIVERS BELOW WATER SURFACE:
50-100 feet $1.00 per foot
101 feet and deeper $2.00 per foot
ENCLOSURE PAY PREMIUM WITH NO VERTICAL ASCENT:
5-50 FEET $1.00 PER FOOT/DAY
51-100 FEET $2.00 PER FOOT/DAY
101 FEET AND ABOVE $3.00 PER FOOT/DAY
SATURATION DIVING:
The standby rate applies until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. the diver rate shall be paid for all saturation hours.
WORK IN COMBINATION OF CLASSIFICATIONS:
Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.
ELEC1547-004 04/01/2023
CABLE SPLICER....................$ 44.44 3%+28.39
ELECTRICIAN......................$ 44.44 3%+28.39
ELEC1547-005 04/01/2023
Line Construction
CABLE SPLICER....................$ 63.44 3%+31.90
Linemen (Including Equipment
Operators, Technician)...........$ 61.29 3%+30.98
Powderman........................$ 61.44 3%+32.69
TREE TRIMMER.....................$ 40.71 3%+28.05
ELEV0019-002 01/01/2023
ELEVATOR MECHANIC................$ 65.83 37.335+a+b
FOOTNOTE: a. Employer contributes 8% of the basic hourly rate for over 5 year's service and 6% of the basic hourly rate for 6 months to 5 years' of service as vacation paid credit. b. Eight paid holidays:
New Year's Day; Memorial Day; Independence Day;
Labor Day; Veteran's Day; Thanksgiving Day; Friday after
Thanksgiving, and Christmas Day
ENGI0302-002 04/01/2023
POWER EQUIPMENT OPERATOR
GROUP 1.....................$ 47.74 27.20
GROUP 1A....................$ 49.64 27.20
GROUP 2.....................$ 46.91 27.20
GROUP 3.....................$ 46.13 27.20
GROUP 4.....................$ 39.42 27.20
TUNNEL WORK
GROUP 1....................$ 52.51 27.20
GROUP 1A...................$ 54.60 27.20
GROUP 2....................$ 51.60 27.20
GROUP 3....................$ 50.74 27.20
GROUP 4....................$ 43.36 27.20
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Asphalt Roller: Breakdown, Intermediate, and
Finish; Back Filler; Barrier Machine (Zipper); Beltcrete with power pack and similar conveyors; Bending Machine;
Boat Coxwains; Bulldozers; Cableways, Highlines and
Cablecars; Cleaning Machine; Coating Machine; Concrete
Hydro Blaster; Cranes-45 tons and under or 150 foot boom and under (including jib and attachments): (a) Hydralifts or Transporters, all track or truck type,(b) Derricks;
Crushers; Deck Winches-Double Drum; Ditching or Trenching
Machine (16 inch or over); Drilling Machines, core, cable, rotary and exploration; Finishing Machine Operator, Concrete Paving, Laser Screed, Sidewalk, Curb and Gutter
Machine; Helicopters; Hover Craft, Flex Craft, Loadmaster, Air Cushion, All Terrain Vehicle, Rollagon, Bargecable, Nodwell, and Snow Cat; Hydro Ax: Feller Buncher and similar; Loaders (2 1/2 yards through 5 yards, including all attachments): Forklifts with telescopic boom and swing attachment, Overhead and front end, 2 1/2 yards through 5 yards, Loaders with forks or pipe clamps; Loaders, elevating belt type, Euclid and similar types; Mechanics, Bodyman; Micro Tunneling Machine; Mixers: Mobile type w/hoist combination; Motor Patrol Grader; Mucking Machines:
Mole, Tunnel Drill, Horizontal/Directional Drill Operator, and/or Shield; Operator on Dredges; Piledriver Engineers, L. B. Foster, Puller or similar Paving Breaker; Power
Plant, Turbine Operator, 200 k.w. and over (power plants or combination of power units over 300 k.w.); Scrapers-through
40 yards; Service Oiler/Service Engineer; Sidebooms-under
45 tons; Shot Blast Machine; Shovels, Backhoes, Excavators with all attachments, and Gradealls (3 yards and under), Spreaders, Blaw Knox, Cedarapids, Barber Greene, Slurry
Machine; Sub-grader (Gurries, Reclaimer, and similar types); Tack tractor; Truck mounted Concrete Pumps, Conveyor, Creter; Water Kote Machine; Unlicensed off road hauler
GROUP 1A: Camera/Tool/Video Operator (Slipline), Cranes-over 45 tons or 150 foot (including jib and attachments): (a) Clamshells and Draglines (over 3 yards),
(b) Tower cranes; Licensed Water/Waste Water Treatment
Operator; Loaders over 5 yds.; Certified Welder, Electrical
Mechanic, Camp Maintenance Engineer, Mechanic (over 10,000 hours); Motor Patrol Grader, Dozer, Grade Tractor, Roto-mill/Profiler (finish: when finishing to final grade and/or to hubs, or for asphalt); Power Plants: 1000 k.w.
and over; Quad; Screed; Shovels, Backhoes, Excavators with all attachments (over 3 yards), Sidebooms over 45 tons;
Slip Form Paver, C.M.I. and similar types; Scrapers over 40 yards;
GROUP 2: Boiler-fireman; Cement Hog and Concrete Pump
Operator; Conveyors (except as listed in group 1); Hoist on steel erection; Towermobiles and Air Tuggers;
Horizontal/Directional Drill Locator;Licensed Grade
Technician; Loaders, (i.e., Elevating Grader and Material
Transfer Vehicle); Locomotives: rod and geared engines;
Mixers; Screening, Washing Plant; Sideboom (cradling rock drill regardless of size); Skidder; Trencing Machine under
16 inches; Waste/ Waste Water Treatment Operator.
GROUP 3: ""A"" Frame Trucks, Deck Winches: single power drum;
Bombardier (tack or tow rig); Boring Machine; Brooms-power;
Bump Cutter; Compressor; Farm tractor; Forklift, industrial type; Gin Truck or Winch Truck with poles when used for hoisting; Grade Checker and Stake Hopper; Hoist, Air
Tuggers, Elevators; Loaders: (a) Elevating-Athey, Barber
Green and similar types (b) Forklifts or Lumber Carrier
(on construction job site) (c) Forklifts with Tower (d)
Overhead and Front-end, under 2 1/2 yds. Locomotives:Dinkey
(air, steam, gas and electric) Speeders; Mechanics (light duty); Oil, Blower Distribution; Post Hole Diggers, mechanical; Pot Fireman (power agitated); Power Plant, Turbine Operator, under 200 k.w.; Pumps-water; Roller-other than Plantmix; Saws, concrete; Skid Steer with all attachments; Straightening Machine; Tow Tractor
GROUP 4: Rig Oiler/Crane Assistant Engineer;Parts and
Equipment Coordinator; Swamper (on trenching machines or shovel type equipment); Spotter; Steam Cleaner; Drill
Helper.
FOOTNOTE: Groups 1-4 receive 10% premium while performing tunnel or underground work. Rig Oiler/Crane Assistant
Engineer shall be required on cranes over 85 tons or over
100 feet of boom.
IRON0751-003 07/01/2022
IRONWORKER
BENDER OPERATOR.............$ 41.49 34.86
BRIDGE, STRUCTURAL,
ORNAMENTAL, REINFORCING
MACHINERY MOVER, RIGGER,
SHEETER, STAGE RIGGER,
BENDER OPERATOR.............$ 41.49 34.86
FENCE, BARRIER INSTALLER....$ 37.99 34.86
GUARDRAIL INSTALLERS........$ 38.99 34.86
GUARDRAIL LAYOUT MAN........$ 38.72 34.86
HELICOPTER, TOWER...........$ 42.49 34.86
LABO0341-001 04/01/2023
LABORER (South of the 63rd
Parallel & West of Longitude
138 Degrees)
GROUP 1.....................$ 36.00 32.56
GROUP 2.....................$ 37.00 32.56
GROUP 3.....................$ 37.90 32.56
GROUP 3A....................$ 41.78 32.56
GROUP 3B....................$ 47.36 28.51
GROUP 4.....................$ 25.57 32.56
TUNNELS, SHAFTS, AND RAISES
GROUP 1....................$ 39.60 32.56
GROUP 2....................$ 40.70 32.56
GROUP 3....................$ 41.69 32.56
GROUP 3A...................$ 45.96 32.56
GROUP 3B...................$ 52.10 28.51
LABORERS CLASSIFICATIONS
GROUP 1: Asphalt Workers (shovelman, plant crew); Brush
Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke
Setters, Hook Tender, Rigger, Signalman; Concrete
Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;
Ditch Diggers; Dump Man; Environmental Laborer (asbestos
(limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;
Flagman; Form Strippers; General Laborer; Guardrail
Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;
Laborers (building); Landscape or Planter; Laying of
Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or
Power Tools; Portable or Chemical Toilet Serviceman; Pump
Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot
Tender; Saw Tenders; Scaffold Building and Erecting; Slurry
Work; Stake Hopper; Steam Point or Water Jet Operator;
Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor
Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner
GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or
Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);
Culvert Pipe Laborer; Cured in place Pipelayer;
Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine
Operator; Green Cutter (dam work); Gunnite Operator; Hod
Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and
Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad
Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer
Plant Maintenance Man; Thermal Plastic Applicator; Timber
Faller, chain saw operator, filer; Timberman
GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine
Operator; High Rigger and tree topper; High Scaler;
Multiplate; Slurry Seal Squeegee Man
GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill
Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);
Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers
GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)
GROUP 4: Final Building Cleanup
TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS
GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;
Tunnel Track Laborer
GROUP 2: Burning and Cutting Torch; Concrete Laborers;
Jackhammers; Nozzleman, Pumpcrete or Shotcrete.
GROUP 3: Miner; Retimberman to, wagon drills, air track drills; hydraulic drills);
type drills); Pipelayers.
Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.
LABO0942-001 04/01/2023
Laborers: North of the 63rd
Parallel & East of Longitude
138 Degrees
GROUP 1.....................$ 36.00 32.56
GROUP 2.....................$ 37.00 32.56
GROUP 3.....................$ 37.90 32.56
GROUP 3A....................$ 41.78 32.56
GROUP 3B....................$ 47.36 28.51
GROUP 4.....................$ 25.57 32.56
TUNNELS, SHAFTS, AND RAISES
GROUP 1....................$ 39.60 32.56
GROUP 2....................$ 40.70 32.56
GROUP 3....................$ 41.69 32.56
GROUP 3A...................$ 45.96 32.56
GROUP 3B...................$ 52.10 32.56
LABORERS CLASSIFICATIONS
GROUP 1: Asphalt Workers (shovelman, plant crew); Brush
Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke
Setters, Hook Tender, Rigger, Signalman; Concrete
Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;
Ditch Diggers; Dump Man; Environmental Laborer (asbestos
(limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;
Flagman; Form Strippers; General Laborer; Guardrail
Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;
Laborers (building); Landscape or Planter; Laying of
Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or
Power Tools; Portable or Chemical Toilet Serviceman; Pump
Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot
Tender; Saw Tenders; Scaffold Building and Erecting; Slurry
Work; Stake Hopper; Steam Point or Water Jet Operator;
Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor
Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner
GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or
Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);
Culvert Pipe Laborer; Cured in place Pipelayer;
Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine
Operator; Green Cutter (dam work); Gunnite Operator; Hod
Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and
Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad
Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer
Plant Maintenance Man; Thermal Plastic Applicator; Timber
Faller, chain saw operator, filer; Timberman
GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine
Operator; High Rigger and tree topper; High Scaler;
Multiplate; Slurry Seal Squeegee Man to, wagon drills, air track drills; hydraulic drills);
type drills); Pipelayers
GROUP 4: Final Building Cleanup
TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS
GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;
Tunnel Track Laborer
GROUP 2: Burning and Cutting Torch; Concrete Laborers;
Jackhammers; Nozzleman, Pumpcrete or Shotcrete.
GROUP 3: Miner; Retimberman to, wagon drills, air track drills; hydraulic drills);
type drills); Pipelayers.
Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.
PAIN1959-001 07/01/2022
NORTH OF THE 63RD PARALLEL
PAINTER
BRUSH/ROLLER PAINT OR WALL
COVERER.....................$ 36.08 25.45
TAPING, TEXTURING,
STRUCTURAL PAINTING,
SANDBLASTING, POT TENDER,
FINISH METAL, SPRAY,
BUFFER OPERATOR, RADON
MITIGATION, LEAD BASED
PAINT ABATEMENT, HAZARDOUS
MATERIAL HANDLER............$ 36.60 25.45
PAIN1959-002 12/01/2021
SOUTH OF THE 63RD PARALLEL
PAINTER
General Painter.............$ 32.64 25.95
Industrial Painter..........$ 32.74 25.95
Taper / Paper & Vinyl
Hanger......................$ 32.64 25.95
PAIN1959-003 12/01/2021
NORTH OF THE 63RD PARALLEL
GLAZIER..........................$ 41.16 28.16
PAIN1959-004 07/01/2019
FLOOR LAYER: Carpet.............$ 28.75 14.44
PAIN1959-006 12/01/2021
SOUTH OF THE 63RD PARALLEL
GLAZIER..........................$ 41.37 27.25
PLUM0262-002 01/01/2023
East of the 141st Meridian
Plumber; Steamfitter.............$ 41.50 27.62
PLUM0367-002 07/01/2021
South of the 63rd Parallel
Plumber; Steamfitter.............$ 41.00 27.95
PLUM0375-002 07/01/2021
North of the 63rd Parallel
Plumber; Steamfitter.............$ 42.91 31.25
PLUM0669-002 04/01/2023
SPRINKLER FITTER.................$ 54.01 30.22
ROOF0189-006 04/01/2023
ROOFER...........................$ 47.62 18.53
* SHEE0023-003 07/01/2023
South of the 63rd Parallel
SHEET METAL WORKER...............$ 47.05 29.50
* SHEE0023-004 07/01/2023
North of the 63rd Parallel
SHEET METAL WORKER...............$ 51.93 30.16
TEAM0959-003 04/01/2023
TRUCK DRIVER
GROUP 1.....................$ 46.84 24.33
GROUP 1A....................$ 48.19 24.33
GROUP 2.....................$ 45.51 24.33
GROUP 3.....................$ 44.64 24.33
GROUP 4.....................$ 44.02 24.33
GROUP 5.....................$ 43.22 24.33
GROUP 1: Semi with Double Box Mixer; Dump Trucks (including rockbuggy and trucks with pups) over 40 yards up to and including 60 yards; Deltas, Commanders, Rollogans and similar equipment when pulling sleds, trailers or similar equipment; Boat Coxswain; Lowboys including attached trailers and jeeps, up to and including 12 axles; Ready-mix over 12 yards up to and including 15 yards); Water Wagon
(250 Bbls and above); Tireman, Heavy Duty/Fueler
GROUP 1A: Dump Trucks (including Rockbuggy and Trucks with pups) over 60 yards up to and including 100 yards; Jeeps
(driver under load)
GROUP 2: Turn-O-Wagon or DW-10 not self-loading; All Deltas, Commanders, Rollogans, and similar equipment; Mechanics;
Dump Trucks (including Rockbuggy and Trucks with pups) over
20 yards up to and including 40 yards; Lowboys including attached trailers and jeeps up to and including 8 axles;
Super vac truck/cacasco truck/heat stress truck; Ready-mix over 7 yards up to and including 12 yards; Partsman;
Stringing Truck
GROUP 3: Dump Trucks (including Rockbuggy and Trucks with pups) over 10 yards up to and including 20 yards; batch trucks 8 yards and up; Oil distributor drivers; Oil
Distributor Drivers; Trucks/Jeeps (push or pull); Traffic
Control Technician
GROUP 4: Buggymobile; Semi or Truck and trailer; Dumpster;
Tireman (light duty); Dump Trucks (including Rockbuggy and
Truck with pups) up to and including 10 yards; Track Truck
Equipment; Grease Truck; Flat Beds, dual rear axle; Hyster
Operators (handling bulk aggregate); Lumber Carrier; Water
Wagon, semi; Water Truck, dual axle; Gin Pole Truck, Winch
Truck, Wrecker, Truck Mounted ""A"" Frame manufactured rating over 5 tons; Bull Lifts and Fork Lifts with Power Boom and
Swing attachments, over 5 tons; Front End Loader with
Forks; Bus Operator over 30 passengers; All Terrain
Vehicles; Boom Truck/Knuckle Truck over 5 tons; Foam
Distributor Truck/dual axle; Hydro-seeders, dual axle;
Vacuum Trucks, Truck Vacuum Sweepers; Loadmaster (air and water); Air Cushion or similar type vehicle; Fire
Truck/Ambulance Driver; Combination Truck-fuel and grease;
Compactor (when pulled by rubber tired equipment); Rigger
(air/water/oilfield); Ready Mix, up to and including 7 yards;
GROUP 5: Gravel Spreader Box Operator on Truck; Flat Beds, single rear axle; Boom Truck/Knuckle Truck up to and including 5 tons; Pickups (Pilot Cars and all light duty vehicles); Water Wagon (Below 250 Bbls); Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted ""A"" Frame, manufactured rating 5 tons and under; Bull Lifts and Fork Lifts (fork lifts with power broom and swing attachments up to and including 5 tons); Buffer Truck; Tack Truck; Farm type
Rubber Tired Tractor (when material handling or pulling wagons on a construction project); Foam Distributor, single axle; Hydro-Seeders, single axle; Team Drivers (horses, mules and similar equipment); Fuel Handler (station/bulk attendant); Batch Truck, up to and including 7 yards;
Gear/Supply Truck; Bus Operator, Up to 30 Passengers;
Rigger/Swamper
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate
(weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or
""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010
08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour
National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the
Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
U.S. Department of Labor
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISIO"
Questions and Clarification 25 July 2023
-01 19 30.01 29 1.8 Access and Phasing of Work (.pdf page 58 / 149):
The first paragraph indicates the work will be performed in dis nct phases (East Wing / West Wing), and one will be occupied by soldiers when the other is being repaired by the contractor.
The second paragraph indicates, “The area of the building not under construc on will be occupied 24 hours daily. The contractor shall maintain all building systems… “ It’s reasonable for the Contractor to be responsible for the por on (side of the building or Phase of work) to which the Contractor has access and control. It’s not fair or reasonable to saddle the Contractor with responsibility for areas that are occupied by others and not under the Contractor’s immediate control.
Since the building will be occupied by soldiers all the time, the systems will need to be maintained in the occupied areas. They can have some short-scheduled downtime. How they do that is up to the Designers and/or contractor.
-10305155 Ques on: Are current As-builts available? Response: “As-Builts will be provided.” - Follow-up Ques on: When?
As-builts have been provided as part of Amendment 3.
-10309960 Ques on: Are Sprinkler System As-Builts available? Response: “Response Pending.” - Follow-up Ques on: When?
All available as-builts have been provided.
-.pdf page 22 / 149 5.2.1.3. “For (Milestone Summary) schedule purposes only, u lize a No ce to Proceed (NTP) date 1 October 2023. This date is solely to assist in evalua on of offeror’s proposals and shall not be construed as a contractual NTP date.”
-.pdf page 58 / 149, 1.8 Access and Phasing of Work – “Contractor must take possession of the building and begin physical work 1 October2023.” - Ques on: Is 01 19 30.01 29 1.8 a contractual ‘must’? - Which provision governs?
October 1 date is for beginning of physical work. I don’t know when the NTP date needs to be to support that.
-Will the contractor need to repair the damaged insula on in the Mechanical Room?
The Contractor will not need to repair damaged insula on in the Mechanical Room as noted in the DA.
It’s not located anywhere in the RFP documents except for the DA.