This solicitation is for repair and renovation work at Building B3207, Fort Wainwright, Alaska. The scope of work includes correcting building deficiencies, updating HVAC DDC controls, providing new ceiling tiles and flooring throughout, patching and painting walls, installing new DDC controls and control valves in 144 dorm rooms, installing new LED lighting and ceiling fans in dorm rooms, repairing or replacing exterior doors, repairing exterior EFIS, installing a redesigned downspout, repairing two sewage lift stations, repairing water damage in the main mechanical room, adding new washer and dryer connections in the laundry room, and converting four multipurpose rooms to weight rooms. The solicitation number is W911KB23R0010 and proposals must be submitted through the PIEE system by the specified due date. Any contract awarded will be certified for national defense and emergency preparedness use.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT TITLE/LOCATION: FTW459 REPAIR PP BARRACKS B3207, FORT WAINWRIGHT, ALASKA- This solicitation is hereby amended as follow s- A) Please see the SF30 below for further changes B) YOU ARE REQUIRED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE SIDE OF THE STANDARD FORM 1442.

-POC for this amendment is Ron Perry (ronald.perry@usace.army.mil)

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911KB23R0010

X 9B. DATED (SEE ITEM 11)

17-May-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0003

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Jul-2023

CODE

U.S. ARMY ENGINEER DISTRICT, AK

CEPOA-CT (W911KB)

2204 TALLEY AVENUE

JBER AK 99506-0898

W911KB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

a. The following changes have been made-

All bidder inquiries and responses have been added, please see attached.

Section 00 21 00, 1.2 CONTRACT COST CEILING LIMITATION FOR DESIGN AND

CONSTRUCTION COSTS, the following text has been deleted- “Offerors are also notified that the contract resulting from this solicitation may be incrementally funded- refer to Section 00 72 00, Contract Clause DFARS 252.232-7007, Limitation of Government’s Obligation, for anticipated funding availability.”

Section 00 22 11, 5.1. TAB A – FACTOR 1 – SPECIALIZED EXPERIENCE, Paragraph 5.1.1.1.

the following has been edited, “Experience with renovation projects that include Architectural renovations specifically Doors, Walls, Ceilings and Flooring, HVAC Direct Digital Controls replacement, and/or electrical renovations” and changed to “Experience with renovation projects that include Architectural renovations specifically Doors, Walls, Ceilings and Flooring, HVAC Direct Digital Controls replacement, and electrical renovations”.

Section 00 22 11, 5.1. TAB A – FACTOR 1 – SPECIALIZED EXPERIENCE, Paragraph 5.1.1.1.

the following has been edited, “Experience with new vertical construction projects that include Architectural, HVAC Direct Digital Controls, and/or Electrical installation” and changed to “Experience with new vertical construction projects that include Architectural, HVAC Direct Digital Controls, and Electrical installation”.

Section 00 22 11, 5.2. TAB B – FACTOR 2 –SUMMARY MILESTONE SCHEDULE, Paragraph 5.2.1.3., the Notice to Proceed has been changed from “1 July 2023” to “1 October 2023”.

Section 00 72 00, Clause 52.211-10 duration has been changed from “730 Days” to “550 Days”.

Section 00 72 00, Clause 52.211-12 liquidated damages amount has been changed from

“$3,959.00” to “$2,361.00”.

Section 00 72 00, Clause 252.232-7007 LIMITATION OF GOVERNMENT'S OBLIGATION

(APR 2014) has been deleted.

Section 00 72 00, Clause 52.204-27 PROHIBITION ON A BYTEDANCE COVERED

APPLICATION (JUN 2023) has been added.

Design Analysis has been removed.

Wage Determination have been updated.

The following drawings are substituted for the superseded documents/sections:

o A-204, P-001, M-601, M-604, M-607, E-001 E-419, E-420, E-421, E-422, E-423, E-424, E-425, E-426, E-427, E-429, E-430, E-431, E-432, E-433, E-434, E-437, E-604

The following drawings are added:

o M-104, E-441, E-611

The following revised documents/sections are substituted for the superseded documents/sections:

o 01 19 30.01 29 – Edited paragraph 1.8 to include begin physical work on 1 Oct 2023 and clarify requirements.

o 02 41 00 – Edited paragraph 1.3 to protect items in place and delete “removed, stored, and replaced”.

o 08 11 13 – Edited paragraph 1.3 and 2.6 to address knockdown frames.

o 10 26 00 – Deleted paragraph 2.1 STANDARD PRODUCTS. Modified paragraph 2.1.1

Clear Polycarbonate Corner Guards.

o 10 28 13 – Added dimensions of mirrors to paragraph 2.1.5.

o Section 23 09 00 – Revised section 3.1.3

(End of Summary of Changes)

ALL OTHER TERMS AND CONDITIONS SHALL REMAIN THE SAME.

7/5/23, 9:28 AM ProjNet: Logged In User https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 1/16

Controlled Unclassified Information (CUI) Only

Bid Inquiry Contractor Report All Inquiries

Project: Repair PP Barracks B3207 Review: FTW459 Repair B3207 (00001) (sorted by CommentID ) Displaying 80 inquiries.

Id Discipline Sheet Detail Spec 10276867 General SECTION 00 22 11 Para 5.1.2.1. and 5.1.3.

Comment Classification: Controlled Unclassified Information (CUI)

Paragraph 5.1.3 states that in order to meet the "Acceptable" definition for specialized experience:

"- The offeror demonstrates experience in Architectural features (doors, walls, flooring, ceiling) that is equivalent to 50,000 SF of space. Experience can either be self-performed work or managing an Architectural subcontractor.

- Installation of HVAC Direct Digital Controls (DDC) totaling 50,000 SF of area. Experience can either be self-performed work or managing an HVAC DDC subcontractor.

- Installation of Interior Electrical totaling 50,000 Sf. Experience can either be self-performed work or managing an Electrical subcontractor."

Paragraph 5.1.2.1. also states: "The experience need not be demonstrated on each project submitted, but all the experience must be demonstrated on the projects submitted."

Please confirm that the above 50,000 SF requirement applies to a combined total square footage of all specialized experience and not a single project. If a single project, would the Government please consider reducing 50,000 SF requirement to 30,000 SF per facility? Since this is an 8(a) set-aside, this will increase competition and participation among qualified 8(a) companies.

On: May 19 2023.

Government Response. . The 50,000 applies to a combination total square footage. The 50,000 can be met through one project or adding square footage up to 5 projects. On: Jun 08 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293388 Electrical E-401 - E-418 Comment Classification: Controlled Unclassified Information (CUI)

Design Analysis 5.1.2.2.2 Barrack Room, 5.1.2.2.7 Corridors, 5.1.2.2.8 Stairways, 5.1.2.2.9 Restrooms, 5.1.2.2.10 Mechanical Room, 5.1.2.2.11 Telecommunication Room, and 5.1.2.2.12 Electrical Room All state that lighting will be retrofitted for LEDs.

However, drawings E-401 through E-418 all have notes to demo the existing and provide new fixtures. Does the project call for new LED fixtures, or retrofitting the existing fixtures to LED?

On: May 31 2023.

Government Response. . See Amendment for Details on Design Analysis On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293404 Electrical Design Analysis Comment Classification: Controlled Unclassified Information (CUI)

Design Analysis 5.1.2.2.9 Restrooms "All hallway lighting will be retrofitted for LEDs" This section appears to have similar verbiage to 5.1.2.2.7. Please confirm that no additional and or different criteria is needed.

On: May 31 2023.

Government Response. . See Amendment for Details on Design Analysis On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293405 Electrical Design Analysis Comment Classification: Controlled Unclassified Information (CUI)

Design Analysis 5.1.2.2.8 Stairways "All hallway lighting will be retrofitted for LEDs" This section appears to have identical verbiage to 5.1.2.2.7. Please confirm that no additional and or different criteria is needed.

On: May 31 2023.

https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont&RequestTimeout=1000&pagStrRowSort=CommentID https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont&RequestTimeout=1000&pagStrRowSort=Discipline https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont&RequestTimeout=1000&pagStrRowSort=Sheet https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont&RequestTimeout=1000&pagStrRowSort=Detail https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont&RequestTimeout=1000&pagStrRowSort=SpecText https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 2/16

Government Response. . See Amendment for details on Design Analysis On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293409 Electrical E-402 Comment Classification: Controlled Unclassified Information (CUI)

E-402 Sheet Note 1 (typical of several stairwell notes) states connected the stairwell lighting circuit to the second floor. Is this an informational note or does the stairwell lighting circuits need to be reconfigured?

On: May 31 2023.

Government Response. . SPECIFIC ELECTRICAL NOTE 1 is for informational purposes to inform the viewer that the circuit continues to another sheet. On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293411 Electrical E-419 - E-434 Comment Classification: Controlled Unclassified Information (CUI)

E-419 - E-434 General note 1. Is this note informational or does the project require new control transformers?

On: May 31 2023.

Government Response. . "GENERAL SHEET NOTES 1" Is for information purposes only. On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293412 Electrical E-419 Comment Classification: Controlled Unclassified Information (CUI)

E-419 Sheet notes 2, 6, &7. Are these informational notes or new work? If new work, are the hallway receptacles new work also? Sheet note numbers varies, but is typical of E-419 through E-343.

On: May 31 2023.

Government Response. . "SPECIFIC ELECTRICAL NOTES" 2,6, and 7 are all informational notes. Outlets and circuits are already installed. On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293413 Electrical E-421 & E-431 Comment Classification: Controlled Unclassified Information (CUI)

E-421, E-431 and a few other pages have bold notes. Assuming the bold means new work, can the remaining electrical sheets be updated with bold notes for new work? For example, note 9 on E-426 is the same as note 9 on E-431 but is not bold on E- 426.

On: May 31 2023.

Government Response. . Concur, the bold "SPECIFIC ELECTRICAL NOTES" are new work to be performed in this project/contract. On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293414 Electrical E-427 Comment Classification: Controlled Unclassified Information (CUI)

E-427 sheet note 2 markers in rooms E263 and E264, assume these are relics?

On: May 31 2023.

Government Response. . Concur, "SPECIFIC ELECTRICAL NOTES 2" referenced in rooms E263 and E264 are relics and not intended to be showing there. On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293415 Electrical E-434 Comment Classification: Controlled Unclassified Information (CUI) https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 3/16

E-434 sheet note 8, please verify that this note is correct.

On: May 31 2023.

Government Response. . "SPECIFIC ELECTRICAL NOTES 8" is not intended to be next to the disconnect and exhaust fan and was accidently left there. On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293417 Electrical E-437 & E-601 26 20 00, 2.16 Comment Classification: Controlled Unclassified Information (CUI)

E-437 & E-601 sheet note 2 and 26 20 00, 2.16, please provide more design or clarity on the meter installation. Does it use the existing CT's or are new CT's to be installed? If new CT's, does it have to be revenue grade? Additional new revenue grade CT's, on top of the existing CT's are typically extremely invasive, time consuming and expensive. If existing CT's are to be used please provide drawings and details.

On: May 31 2023.

Government Response. . The intent of the design is to install new CT's and a new revenue grade meter. On: Jun

26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293418 Electrical E-438 Comment Classification: Controlled Unclassified Information (CUI)

The Design Analysis lists Minka-Aire F519L-BN fan and WCS212 switch, both made in China. Please provide a FAR 52.225-11 complaint fan and switch as a basis of design or list it as excluded in 52.225-11 (b)(3).

On: May 31 2023.

Government Response. . See amendment for detail on Design Analysis On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293444 Communications E-001 General Note #5 Comment Classification: Controlled Unclassified Information (CUI)

Drawing E-001, General Note #5, specifies "replace any damaged telecommunication faceplates, outlets or modules". Please quantify number of faceplates, outlets or modules to be replaced for bidding purposes. The statement is completely ambiguous and could lead to wildly differing estimates between offerors.

On: May 31 2023.

Government Response. . Concur, the intent is that the contractor will not be replacing any existing damaged or broken faceplates/covers and telecommunication outlets. The intent of the note is that the contractor must replaced any outlets that they damage or paint over, during the construction of this project. On: Jun 13 2023

Current Request Status: Request Closed Information for this report is procurement sensitive.

10293448 Communications E-001 General Note #5 Comment Classification: Controlled Unclassified Information (CUI)

Drawing E-001, General Note #5, specifies "replace any damaged telecommunication faceplates, outlets or modules". Please clarify what a telecommunication "module" is.

On: May 31 2023.

Government Response. . Concur, the intent is that the contractor will not be replacing any existing damaged or broken faceplates/covers and telecommunication outlets. The intent of the note is that the contractor must replaced any outlets that they damage or paint over, during the construction of this project On: Jun 13 2023

Current Request Status: Request Closed Information for this report is procurement sensitive.

10293458 Communications E-001 General Note #5 Comment Classification: Controlled Unclassified Information (CUI)

Drawing E-001, General Note #5, specifies "replace any damaged telecommunication faceplates, outlets or modules". If a CAT5 or CAT6 outlet (jack) is replaced will the new outlet, existing cabling, and TER end of the circuit need to be re-certified with test https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 4/16 report documentation provided to owner.

On: May 31 2023.

Government Response. . Concur, if the outlet is damaged/painted during construction, then the outlet must be re-certified and test results provided. On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10293460 Communications E-001 General Note #5 Comment Classification: Controlled Unclassified Information (CUI)

Drawing E-001, General Note #5, specifies "replace any damaged telecommunication faceplates, outlets or modules". Does a replacement wallplate, outlet or module need to be the same manufcturer/model of the damaged one? If so please provide manufacturer, model and category rating of the outlet.

On: May 31 2023.

Government Response. . Concur, the intent is that the contractor will not be replacing any existing damaged or broken faceplates/covers and telecommunication outlets. The intent of the note is that the contractor must replaced any outlets that they damage or paint over, during the construction of this project. The replacement outlets and covers must be rated for CAT6 system and 568B Configuration. On: Jun 13 2023

Current Request Status: Request Closed Information for this report is procurement sensitive.

10293521 Planning - Plan Formulation A-003 General Note #1 Comment Classification: Controlled Unclassified Information (CUI)

Facility Occupancy- will building 3207 be occupied by residents during renovation? If so to what extent? Extensive work is required in sleeping room/modules, so how is that going to work if occupied for painting, floor replacement, lighting replacement?

Is there going to be a phasing plan?

On: May 31 2023.

Government Response. . See Section 01 19 30.01 29 Paragraph 1.8 Access and Phasing of Work for description of occupancy and phasing requirements. On: Jun 16 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10295147 Contracting 00 72 00 Comment Classification: Controlled Unclassified Information (CUI)

Section 00 72 00 appears to be structured for a different acquisition, including references to:

52.211-10 730 day time for completion (in conflict with SF1442), 52.211-12 $3,959.00 / calendar day Liquidated Damages, 525.232-7007 CLINS 0001-0006(?) and $51.7 mil contract amount.

Please clarify if above provisions are applicable.

On: Jun 01 2023.

Government Response. . Provisions will be corrected via amendment to properly reflect this acquisition (FTW459)

On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10295191 Contracting Design Analysis Comment Classification: Controlled Unclassified Information (CUI)

A Design Analysis document is included with the RFP.

Is it intended for reference (only), or to define scope?

In the event of conflict with other documents, please clarify the order of precedence.

On: Jun 01 2023.

Government Response. . See Amendment for detail on Design Analysis On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10295786 Plumbing M-609 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 5/16

Energy and Water Metering, 1.3. "Install new water meter."

What exactly is required?

The original 3" Badger Turbo meter has already been replaced with a 4" Badger compound water meter.

On: Jun 01 2023.

Government Response. . If the now existing meter is compliant with the FT Wainwright design guides and is capable of supporting the required DDC inputs it may remain and not be replaced, otherwise provide new compatible meter On: Jun 13 2023

Current Request Status: Request Closed Information for this report is procurement sensitive.

10298549 Other SF1442 RFP Page 5 Comment Classification: Controlled Unclassified Information (CUI)

RFP Page 5...SF 1442 page 2 has a "DRAFT" watermark. Please clarify if you will either issue a new SF1442, leave as is to be acceptable, or allow Offerors' to remove the watermark?

On: Jun 05 2023.

Government Response. . The "draft" watermark will be removed from the SF1442 along with any other edits that need correction via amendment. On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10298554 Electrical 00 22 11, TAB A, Factor 1 Comment Classification: Controlled Unclassified Information (CUI)

RFP Section 00 22 11, TAB A-Factor 1-Specialized Experience, 5.1.1.1 references recent/relevant type as:

• Experience with renovation projects..."and/or" electrical renovations.

• Experience with new vertical construction..."and/ or" Electrical installation.

However, 5.1.3. Evaluation Rating System states: "ACCEPTABLE – Proposal meets the minimum requirements of the solicitation..."Ins tallation of Interior Electrical totaling 50,000 Sf."

Please clarify: The Evaluation Rating System is in conflict to the Specialized Experience Requirements...

1) Is Electrical installation an optional element (Specialized Experience) or is it a requirement (Rating System)?

On: Jun 05 2023.

Government Response. . Electrical installation is not an optional element. An amendment will be issued to correct it to the following-

"•Experience with renovation projects that include Architectural renovations specifically Doors, Walls, Ceilings and Flooring, HVAC Direct Digital Controls replacement, and electrical renovations.

•Experience with new vertical construction projects that include Architectural, HVAC Direct Digital Controls, and Electrical installation. On: Jun 13 2023

Current Request Status: Request Closed Information for this report is procurement sensitive.

10301047 Construction Management 00 72 00 Comment Classification: Controlled Unclassified Information (CUI)

FAR 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR states "...the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent..."Can project superintendence be subcontracted as part of a teaming agreement for this contract?

On: Jun 06 2023.

Government Response. . No On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10301159 Electrical E-604 Comment Classification: Controlled Unclassified Information (CUI)

E-604 type B3 fixture is not listed, however , type B3 fixtures are shown on other prints like E-401, please clarify.

On: Jun 06 2023.

https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 6/16

Government Response. . New Fixture Type B3 is the same as both "A3H" and "A2AH". On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10301160 Electrical E-604 Comment Classification: Controlled Unclassified Information (CUI)

E-604 Type D1 fixtures are not shown on other prints, however D2 fixtures are, is D1 a typo?

On: Jun 06 2023.

Government Response. . D1 is an extra light fixture that shouldn't have been included. D2 and D3 are the same light fixtures. On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10301163 Electrical E-438 Comment Classification: Controlled Unclassified Information (CUI)

E-438 Detail Note #4 - Can it be assumed that the existing fan boxes are currently listed fan-rated boxes on both East and West wings?

On: Jun 06 2023.

Government Response. . Concur, assume that existing ceiling fans are installed to fan boxes currently. On: Jun 13

Current Request Status: Request Closed

Information for this report is procurement sensitive.

10304518 Mechanical AD-101, P-___ Comment Classification: Controlled Unclassified Information (CUI)

On drawing AD-101 it states for the Mens room 138A, Mud room 138, and Womens room 138B, to "demo all fixtures except the utility sink and floor sink". But right below that note it says to "remove, store, and replace the utility sink and floor sink". Also, there is no plumbing drawing that mentions room 138, and on the plumbing schedule it does not have a utility sink or floor sink on the list. Please clarify how to proceed.

On: Jun 08 2023.

Government Response. . Pluming drawings / schedule are for only areas where plumbing reconfiguration is scheduled - areas where fixtures are to remain / be removed and reinstalled are to remain with the current connections and are not shown. On: Jun 13 2023

Current Request Status: Request Closed Information for this report is procurement sensitive.

10304722 Architectural 10 26 00 2.2.1 Comment Classification: Controlled Unclassified Information (CUI)

Referenced specification calls for Corner Guards, "...radius formed to profile shown. Provide corner guards that extend from floor to ceiling."

We've been unable to locate required Corner Guard profile, nor details of coordination with other wall finishes (rubber base, ceramic tile base, wainscot, chair rail, etc.).

Please clarify missing corner guard details / requirements.

On: Jun 08 2023.

Government Response. . No On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10305147 General Specs Comment Classification: Controlled Unclassified Information (CUI)

It looks like all the doors and frames require paint, excluding Mechanical, Electric, Storage, Closets, Communications, and Fan rooms correct?

On: Jun 08 2023.

Government Response. . See door schedule and schedule general notes for doors requiring paint. On: Jun 26 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 7/16

Current Request Status: Request Closed Information for this report is procurement sensitive.

10305151 General SOW Comment Classification: Controlled Unclassified Information (CUI)

Scope says all walls are to receive paint, but the Dorm rooms are not on the finish schedule. Are they to receive paint?

On: Jun 08 2023.

Government Response. . Finishes are based on typical floor plan (reverse similar). See A9/A-401 for sleeping room unit plan with room numbers. See A-603 for finish schedule for sleeping unit finishes. On: Jun 19 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10305153 General SOW Comment Classification: Controlled Unclassified Information (CUI)

Do the doors and frames in the corridor or inside the units receive paint?

On: Jun 08 2023.

Government Response. . See door schedule and schedule general notes for doors requiring paint. On: Jun 26

Current Request Status: Request Closed

Information for this report is procurement sensitive.

10305154 General Specs Comment Classification: Controlled Unclassified Information (CUI)

Will the Exterior painting only be the lower 3' under the areas with no EIFS?

On: Jun 08 2023.

Government Response. . Painting is below the expansion joint on the EIFS and precast concrete exterior walls. On:

Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10305155 General Specs Comment Classification: Controlled Unclassified Information (CUI)

Are current as-builts available?

On: Jun 08 2023.

Government Response. . As builts will be provided. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10305157 General SOW Comment Classification: Controlled Unclassified Information (CUI)

Will the entire facility require TAB?

On: Jun 08 2023.

Government Response. . The new fans and air outlets, as well as the modified AHU's and EF's require balancing / re- balancing - the remaining devices remain as currently functioning. On: Jun 13 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10305643 Cybersecurity 10 14 00.20 Comment Classification: Controlled Unclassified Information (CUI)

Section 10 14 00.20 (Interior Signage) contains sub-section 1.3.4 (Cyber security). This seems to be an irregularity. Please confirm that section 1.3.4 is supposed to be in section 10 14 00.22

On: Jun 08 2023.

Government Response. . Paragraph will be deleted via amendment. On: Jun 26 2023 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 8/16

Current Request Status: Request Closed Information for this report is procurement sensitive.

10306851 Architectural A-501 E10, G10 Comment Classification: Controlled Unclassified Information (CUI)

Referenced Window Head and Sill details are not tied to specific locations. Is it safe to assume E10 & G10 are intended to show requirements at new weight rooms?

On: Jun 09 2023.

Government Response. . Correct, these details are in reference to the new windows at the weight rooms. On: Jun

26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10308184 Mechanical M-101 Comment Classification: Controlled Unclassified Information (CUI)

Please provide the original submittal data for the Innovent AIR-TO-AIR Heat Exchanger for AHU-1-East & West.

On: Jun 11 2023.

Government Response. . Will be provided in amendment. On: Jun 14 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10308186 Energy Mon & Controls M-806 Comment Classification: Controlled Unclassified Information (CUI)

Please provide all original submittal data with product cut sheets for the original Honeywell DDC system. This data is necessary for accurate conversion to a Siemens DDC system.

On: Jun 11 2023.

Government Response. . All available DDC information has been provided in the exhibit drawings. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10308190 Energy Mon & Controls M-818 Comment Classification: Controlled Unclassified Information (CUI)

Sheet M-818, Emergency Shutoff switch #2 references a drawing from FTW 248. Please provide drawing M2.03 from FTW 248

On: Jun 11 2023.

Government Response. . The drawing will be added in the next amendment, for your reference. see below.

note 11 states the following

Two ventilation emergency shutdown switches on wall behind CO desk. one for mail room, one for all other systems.

On: Jun 26 2023

Current Request Status: Request Closed Information for this report is procurement sensitive.

10308191 Energy Mon & Controls M-851 & M-601 Comment Classification: Controlled Unclassified Information (CUI)

M-851 Indicates that there are two circulation pumps associated with the east side domestic hot water heating system. Please confirm that the configuration on detail #1 on sheet M-601 is the desired configuration.

On: Jun 11 2023.

Government Response. . No, the configuration on M-605. Sheet M-601 does not have a detail. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10308195 Energy Mon & Controls M-601 00 21 00 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 9/16

M-601, Note 6 refers to areas that are to be stand-alone thermostats/control valves. The base assumption is that after testing, 5% of valves, thermostats, and or wires will need to be replaced. Mention is also made of replacing control valves in all 144 dorm rooms in section 1.1 of 00 21 00 pg.2. Please confirm the owner's intent of up to 5% to be replaced under this SOW.

On: Jun 11 2023.

Government Response. . Note 6 is correct. 00 21 00 will be revised to reflect note 6. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10308204 Energy Mon & Controls 23 09 00 - 3.1.3 Comment Classification: Controlled Unclassified Information (CUI)

DDC contractor is required to calibrate existing devices as necessary to place them in proper working order all devices which are to be reused. It might not be possible to get all devices back to the original factory calibration. Please indicate the acceptable accuracy range of existing devices.

On: Jun 11 2023.

Government Response. . +- 5% of factory calibration. will add requirement to spec. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10308208 Energy Mon & Controls 23 09 00 Comment Classification: Controlled Unclassified Information (CUI)

There is no mention in the RFP of the availability of government-owned fiber for communication between B3207 and the FTW UMCS main network. It is currently assumed that the AFAR wireless communication system will have to be used to add this building to the FTW UMCS, this is a less-than-ideal network arrangement. Please confirm that the 59th Signal does not have spare fiber optic capacity to B3207.

On: Jun 11 2023.

Government Response. . One spare fiber is available for the new DDC to be connected to. Assume FTW UMCS communication method will be through fiber and not the AFAR wireless communication system. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10308221 Energy Mon & Controls 10 14 00.20 - 1.3.4 a Comment Classification: Controlled Unclassified Information (CUI)

Please confirm that the UMCS network and DDC system in B3207 will not need to receive an Authority to Operate (ATO) under this RFP.

On: Jun 11 2023.

Government Response. . It will not require ATO. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10308875 Mechanical M-840 Comment Classification: Controlled Unclassified Information (CUI)

Controls system exhibit drawings sheet M-840 indicates two AHU-3 units in the building. This contradicts M-604, which does not differentiate between AHU-3 West or East. Please confirm the correct quantity and locations of AHU-3.

On: Jun 12 2023.

Government Response. . Will change to clarify M-604 is for both AHU-3 E and W via amendment On: Jun 14 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10308949 Energy Mon & Controls M-601 5 Comment Classification: Controlled Unclassified Information (CUI)

M-601, Note #5.

Due to the requirement of retaining conduit and raceways to the maximum extent possible. Please consider a second site visit to further investigate the existing conduit and raceways.

On: Jun 12 2023.

https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 10/16

Government Response. . There will not be a second site visit. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309009 Energy Mon & Controls E-421 B1 Comment Classification: Controlled Unclassified Information (CUI)

Please confirm that the government will allow for the installation of a new locking DDC enclosure in the Telecommunications room to house new network equipment.

On: Jun 12 2023.

Government Response. . No, intent is to place DDC enclosure near existing. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309142 Construction Management 00 22 11 Comment Classification: Controlled Unclassified Information (CUI)

Book 1 section 00 22 11 Paragraph 5.2.1.3 states, "For schedule purposes only, utilize a Notice to Proceed (NTP) date of 1 July 2023. This date is solely to assist in evaluation of offerors' proposals and shall not be construed as a contractual NTP date."

Does the government know the anticipated start date of the project? Or at least the month?

On: Jun 12 2023.

Government Response. . The anticipated NTP will be 1 Oct 2023, this will be changed via amendment. On: Jun 27

Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309147 Construction Management 00 22 11 Comment Classification: Controlled Unclassified Information (CUI)

Is the intent of the contract to 100% complete the West wing with all testing commission and inspections, then move personnel out of the East wing and into the West wing?

On: Jun 12 2023.

Government Response. . The West Wing must be fully habitable before moving soldiers into the wing. Some commissioning and inspections can happen after turnover as long as it does not interrupt the soldiers or affect the quality of life for the soldiers moving into the wing. On: Jun 26 2023

Current Request Status: Request Closed Information for this report is procurement sensitive.

10309154 Construction Management 00 22 11 Comment Classification: Controlled Unclassified Information (CUI)

If the governments intent is to 100% complete the west wing then move personnel from the East wing. How much time will the government need to move personnel to the West wing?

On: Jun 12 2023.

Government Response. . Yes, the West wing will need to be 100% complete before moving to the East Wing. On:

Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309206 General 00 22 11 Comment Classification: Controlled Unclassified Information (CUI)

Will the contractor be able to utilize a few existing bathroom per floor while work is being performed?

On: Jun 12 2023.

Government Response. . Yes. Contractor is responsible for repairing any damages and cleaning prior to turnover.

On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309266 Architectural 099000 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 11/16

Comment Classification: Public (Public)

Do baseboard covers paint?

On: Jun 12 2023.

Government Response. . Do not paint wall base. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309269 Architectural 099000 Comment Classification: Controlled Unclassified Information (CUI)

Do chair rail, picture rail, window sill and apron varnish?

On: Jun 12 2023.

Government Response. . Provide varnish on new window sills. All others to remain as existing. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309270 Architectural A-601 General note # 1 099000 Comment Classification: Controlled Unclassified Information (CUI)

What does it mean to Maintain Existing Door Frames? Do we paint existing door frames?

On: Jun 12 2023.

Government Response. . See door schedule general notes - keep existing doors and frames in place where noted to maintain. Paint both door and frames. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309274 Architectural 099000 Comment Classification: Controlled Unclassified Information (CUI)

Do we paint the green stair steel in stairwells? To include handrails, stringers, risers, undersides, etc.

On: Jun 12 2023.

Government Response. . No. Paint color is for walls only. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309706 General SOW Comment Classification: Controlled Unclassified Information (CUI)

Please confirm if EIFS repair work is only required at the downspouts & splash blocks locations?

On: Jun 12 2023.

Government Response. . Correct. Repair EIFS up to 10 feet on either side of downspout locations. On: Jun 26

Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309707 General RFP Comment Classification: Controlled Unclassified Information (CUI)

Would the Government consider extending the proposal due date by at least one week, preferably two, to allow for additional time identifying interested subcontractors?

On: Jun 12 2023.

Government Response. . The proposal due date for FTW459 will be extended to July 11th, 2023. This will be captured via amendment. On: Jun 16 2023 Current Request Status: Request Closed

10309708 Architectural AD101 Not 3 08 11 13 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 12/16

Comment Classification: Controlled Unclassified Information (CUI)

Demo note 3 AD101. Can the government please explain the difference between "Sleeping Rooms" and "Sleeping Unit Main Rooms"?

On: Jun 12 2023.

Government Response. . See A9/A-401 for Sleeping Unit arrangements. Sleeping Room refers to rooms 004A and

005A. Sleeping Unit Main Room is the common area in the unit, Room 001. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309709 General Spec 02 41 00 Comment Classification: Controlled Unclassified Information (CUI)

Spec 02 41 00 – Attachment 1 instructs the contractor to remove existing FF&E from the building and store it at a designated location. Please provide the storage location?

On: Jun 12 2023.

Government Response. . See amendment for updates. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309710 General SOW Comment Classification: Controlled Unclassified Information (CUI)

Does the Government expect the contractor to demo & patch EFIS as needed to replace the existing foundation base flashing?

On: Jun 12 2023.

Government Response. . Yes, patch and repair EIFS as needed to correctly install base flashing. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309711 General SOW Comment Classification: Controlled Unclassified Information (CUI)

For bidding purposes, please confirm that the contractor should assume 50% of the total lineal footage of existing base flashing will need to be removed, cleaned, and reinstalled?

On: Jun 12 2023.

Government Response. . Yes, base flashing on the West Wing will need to be removed and reinstalled. On: Jun 26

Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309713 General SOW Comment Classification: Controlled Unclassified Information (CUI)

Should the contractor assume that all existing base flashing removed will be suitable for re-installation?

On: Jun 12 2023.

Government Response. . Contractor shall verify that flashing is in acceptable shape to be reinstalled. On: Jun 26

Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309715 Architectural A501 A10 07 24 00 Comment Classification: Controlled Unclassified Information (CUI)

The base flashing details A10 on Sheet A501 are not matching base flashing installed on the East side of the building. The East side of the barracks base flashing looks to be in good condition and the wall material is concrete not EIFS as indicated on elevation drawings A-201 – A-204. The noted A10 flashing detail is for the West side of the building that has a EIFS finish and the bottom caulking joint that is failing.

A. Is there any base flashing work to be performed on the East barracks wing?

B. Would the government like only damaged flashing to be replaced on the West wing or all base flashing to be replaced?

https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 13/16

On: Jun 12 2023.

Government Response. . See amendment for correction. Base flashing on the East Wing to remain. Flashing on the West Wing to be removed and replaced.

A. No B. Yes On: Jun 26 2023

Current Request Status: Request Closed Information for this report is procurement sensitive.

10309716 General 00 22 11 Comment Classification: Controlled Unclassified Information (CUI)

Could an additional site visit be scheduled for project. Specifically, another chance to count lighting fixtures in the sleeping rooms. The light fixtures at the sleeping rooms are not shown on the contract drawings.

On: Jun 12 2023.

Government Response. . No additional site visit will be provided. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309717 Architectural 08 11 13 Comment Classification: Controlled Unclassified Information (CUI)

Specification 08 11 13 calls out welded frames for new door frames 2.6.1. Would the government consider allowing knock down frames for this project?

On: Jun 12 2023.

Government Response. . See amendment for correction. Knockdown frames are acceptable. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309718 Mechanical M-805 23 09 23.02 Comment Classification: Controlled Unclassified Information (CUI)

9. Pumps P-1A-W, P-1B-W, P-1A-E and P-1A-W, are being converted to variable speed controls with external VFD and pressure sensors. Will this require pre-construction measurement of existing pump flows/system pressure and verification/recalib ration for flows/system pressure of pumps after VAV and pressure sensors are installed?

On: Jun 12 2023.

Government Response. . Referenced pumps are for building sewer. There is no requirement to add VFD to building sewer. On: Jun 16 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309719 Mechanical 23 09 23.02 Comment Classification: Controlled Unclassified Information (CUI)

Will change out of DDC controls and control valves and modification of pumps require re-balance of entire hydronic system or just the large coils at the HVAC equipment? If the entire hydronic system, will all existing balance valves be replaced? Existing balance valves are 18 years old and typically will be difficult to measure/adjust due to clogged test ports, inoperable valve, clogged balance valves.

On: Jun 12 2023.

Government Response. . No On: Jun 16 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309721 Mechanical 23 09 23.02 Comment Classification: Controlled Unclassified Information (CUI)

Will change out of DDC controls require re-balance of entire constant volume ventilation system or just verification of flows at Air Handlers?

On: Jun 12 2023.

Government Response. . No On: Jun 16 2023 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont 14/16

Current Request Status: Request Closed Information for this report is procurement sensitive.

10309733 Energy Mon & Controls M-607 2 Comment Classification: Controlled Unclassified Information (CUI)

Sheet M-607, detail 2 shows EF-1, EF-2, and EF-3 with status via a differential pressure switch.

The sequence of operation on sheet M-607 indicates the monitoring status via a current transformer (CT). Existing DDC system exhibit drawings M-826 and M-854 show CT for status.

Siemens recommends that CTs be used for fan status to match existing.

Please confirm your preference.

On: Jun 12 2023.

Government Response. . Drawings will show CT. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309883 Energy Mon & Controls M-854 & M-607 2 Comment Classification: Controlled Unclassified Information (CUI)

Exhibit Drawings sheet M-854 EF-2-E & EF-3-E are shown with damper actuators. EF-2-E & EF-3-E are shown on M-607 to not have damper actuators and the Sequence of Operations (SOO) does not provide direction for damper actuators.

Please provide an SOO and directions regarding these damper actuators.

On: Jun 12 2023.

Government Response. . Will update and provide. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309905 Energy Mon & Controls M-601 & M-606 Comment Classification: Controlled Unclassified Information (CUI)

Sheet M-601 requires that CABINET UNIT HEATERS IN ENTRY VESTIBULES, CABINET UNIT HEATERS IN STAIRWELLS, and UNIT HEATERS not be connected to BAS.

The sequence of operations (SOO) on sheet M-606 for Unit Heaters, requires monitoring. To meet SOO, Unit Heaters must be connected to the BAS.

Please indicate which requirement takes precedence.

On: Jun 12 2023.

Government Response. . Will be Updated. On: Jun 26 2023 Current Request Status: Request Closed

Information for this report is procurement sensitive.

10309960 Fire Protection/Life Safety 21 13 00 Comment Classification: Controlled Unclassified Information (CUI)

Are Sprinkler Systems As-Builts available to define existing conditions and aid in understanding / pricing the work?

On: Jun 12 2023.

Current Request Status: Request Pending

Information for this report is procurement sensitive.

10309965 Architectural A-606 Finish Material Legend Comment Classification: Controlled Unclassified Information (CUI)

The Finish Material Legend callc for Mannington Rubber Teles Plank flooring / 3 colors / installed "random". We will need further guidance for this.