F10AK029805_03.11_0501_a.pdf
PDF 3 MB Posted
- Solicitation number
- W911KB19R0016
About this file
USACE 2012. Final Revision 1 Risk Assessment/Probability Assessment, Possible CWM Storage Area
View the file
Other files
Show 40 more
Latest 50 of 52 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FINAL REVISION 1
RISK ASSESSMENT/PROBABILITY ASSESSMENT
POSSIBLE CWM STORAGE AREA
FORMER FORT GLENN
UMNAK ISLAND, ALASKA
FUDS #F10AK029805
February 2012
Prepared for:
U. S. Army Engineering and Support Center
Huntsville, Alabama and
U. S. Army Corps of Engineers, Alaska District Elmendorf AFB, Alaska
Contract No. W912DY-09-D-0061 Task Order: 0002
Prepared by:
12120 Shamrock Plaza, Suite 300
Omaha, Nebraska 68154
16170581
J4ENGRAR
Typewritten Text F10AK029805_03.11_0501_a 200-1e
Risk Assessment / Probability Assessment i Possible CWM Storage Area, Former Fort Glenn, Umnak Island, AK I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
Table of Contents
Section 1.0 Introduction ................................................................................................. 1-1
Section 2.0 History of Possible CWM Storage Area ..................................................... 2-1
Section 3.0 Probability of Encountering CWM ............................................................. 3-1
Section 4.0 Summary and Conclusion ........................................................................... 4-1
Section 5.0 Historical Information ................................................................................. 5-1
5.1 Site-Specific Work to Date Summary ........................................... 5-1
5.2 References ..................................................................................... 5-1
Section 6.0 Photographic Analysis - Historical Documentation and Maps ................... 6-1
List of Tables
Table 1 Mishap Risk Management Process Probability Categories
Table 2 Mishap Risk Management Process Severity Categories
Table 3 Standardized Army Risk Matrix
Table 4 Risk Matrix Codes and Descriptions
Risk Assessment / Probability Assessment ii
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
Acronyms and Abbreviations
ASR
CELMS
CSP
CWM
Archive Search Report
Corps of Engineers, St. Louis
Chemical Warfare Materiel Site Plan
Chemical Warfare Materiel
CWS
DOD
FUDS
mm
Chemical Warfare Service
Department of Defense
Formerly Used Defense Site millimeter
RAC
RI
TEC
USACE
Risk Assessment Code
Remedial Investigation
Topographic Engineering Center
United States Army Corps of Engineers
Risk Assessment / Probability Assessment 1-1
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
Risk Assessment/Probability Determination Possible CWM Storage Area
Former Fort Glenn, Umnak Island, Alaska December 2011
1.0 Introduction
1.1 This document details the risk assessment/probability determination performed for the Possible CWM Storage Area at the former Fort Glenn, Umnak Island, Alaska. An environmental response (i.e., Remedial Investigation) is planned at this site. This assessment has been completed in accordance with Chemical Warfare Materiel Responses and Related Activities, Interim Guidance (1 April 2009) Section 3-3 Probability of Encountering CWM Determination:
“Installation or district commanders will conduct an assessment of the probability of encountering Chemical Warfare Materiel (CWM) prior to conduct of ground disturbing (e.g. construction) or other intrusive activities (e.g., range clearance activities, environmental responses), other than a CWM response, at CWM sites or sites where previous encounters with CWM have occurred or where there is evidence (e.g., historical or physical) that CWM may be present. This assessment will be documented and approved by the commander. The procedures follow:
a. Determine the scope of proposed activities.
b. Determine whether the site is listed on Department of Defense (DOD’s) inventory of CWM sites.
c. Review or conduct Munitions Response Historical Records Review or Archive Search Report (ASR) to determine the probability of encountering CWM during ground disturbing or intrusive activities. The probability will be documented per DA PAM 385-30 [Mishap Risk Management, 10 October 2007].
d. If the probability of encountering CWM is categorized as “Seldom” or less, the commander or a designated representative may accept the risk of conducting activities as a non-CWM site. However, the safety and health plan for the response will include contingency plans for an explosives or munitions emergency response should CWM be encountered. CWM contingency plans will be approved by the commander or a designated representative.
e. If, during site activities, a munition with an unknown liquid fill or CWM is encountered, all intrusive response activities will be halted until such time as the fill is determined.
f. If the filler is determined to be CWM, the commander, in coordination with United States Army Corps of Engineers (USACE), will evaluate the circumstances and determine whether:
(1) The activity should be continued:
(a) As planned; or
(b) With modifications to address the potential to encounter additional CWM.
(2) A CWM response is required prior to continuing.”
Risk Assessment / Probability Assessment 1-2
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
1.2 Table 1 identifies the risk management process probability categories.
Table 1. Mishap Risk Management Process Probability Categories Key phase
Term-keyword
Symbol Single item/activity Fleet or inventory of items-multiple activities
Individual Soldier
All Soldiers exposed to the hazard
Frequent A Likely to occur often in the life of an item or activity, with a probability of occurrence greater than 10 -1 in that life
Continuously experienced
Occurs very often in the career. Expected to occur several times during mission or operations.
Always occurs
Occurs continuously during a specific mission, operation, or during a career
Likely B Will occur several times in the life of an item or activity, with a probability of occurrence less than 10 -1 and greater than 10 -2 in that life
Will occur frequently
Occurs several times in the career. Expected to occur during a specific mission or operation
Occurs at a high rate, but experienced intermittently (regular intervals, generally often.)
Occasional C Likely to occur some time in the life of an item or activity, with a probability of occurrence less than 10 -2 and greater than 10 -3 in that life
Will occur several times
Occurs some time in career.
May occur during a specific mission or operation, but not often
Occurs several times in a career
Seldom D Unlikely but possible to occur in the life of an item or activity, with a probability of occurrence less than 10 -3 and greater than 10 -6
Unlikely, but can reasonably be expected to occur
Possible to occur some time in a career, but rarely. Not expected to occur during a specific mission or operation
Occurs rarely within the exposed population as isolated incidents
Unlikely E So unlikely, it can be assumed occurrence may not be experienced, with a probability of occurrence less than 10 -6
Unlikely to occur, but possible
Occurrence not impossible, but can assume will almost never occur during a career. Can assume will not occur during a specific mission or operation
Occurs very rarely (almost never or improbable). Incident may occur over a career.
Notes:
1. Service life and career are defined as a period of 20 years unless specific as other.
Risk Assessment / Probability Assessment 1-3
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
1.3 Severity approximates the amount of potential harm, damage, or injury associated with a given hazard scenario or mishap occurring. Severity and probability are independent of each other. In other words, determining severity has no relationship to determining the probability. Determining an objective amount or cost for the hazard's outcome may be difficult. Therefore, severity ranges have been established to aid in this process. These severity ranges delineate a range of mishap outcomes. Table 2 identifies the mishap risk management process severity categories.
Table 2. Mishap Risk Management Process Severity Categories
Severity Symbol Quantitative Value Quantitative Value
Definition
Catastrophic I 1 or more deaths or permanent total disabilities
Loss exceeding $1M
Loss of ability to accomplish the mission or mission failure. Death or permanent total disability (accident risk). Loss of major or mission-critical system or equipment. Major property (facility) damage. Unacceptable collateral damage
Critical II 1 or more permanent partial disabilities or temporary total disability resulting in more than 3 months lost time
Loss exceeding $200K but less than $1M
Significantly (severely) degraded mission capability or unit readiness. Permanent partial disability, temporary total disability exceeding 3 months time (accident risk). Extensive (major) damage to equipment or systems. Significant damage to property. Significant collateral damage
Marginal III 1 or more injuries or illnesses resulting in less than 3 months lost time
Loss exceeding $20K but less than $200K
Degraded mission capability or unit readiness. Minor damage to equipment or systems, or property.
Lost days due to injury or illness not exceeding 3 months (accident risk)
Negligible IV 1 or more injuries or illnesses requiring first aid or medical treatment
Loss less than $20K
Little or no adverse impact on mission capability. First aid or minor medical treatment (accident risk). Slight equipment or system damage, but fully functional and serviceable. Little or no property damage
Risk Assessment / Probability Assessment 1-4
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
1.4 Using the Army’s standard risk assessment matrix in Table 3, probability and severity for each identified hazard are converted into a standard level of risk. The resultant risk assessment code (RAC) and description is found by using Table 4. For example, a site with a ‘Likely’ (B) probability and a ‘Marginal’ (III) severity yields a standardized matrix value of M (3) and a RAC of 3 (moderate).
Table 3. Standardized Army Risk Matrix Probability
Severity Frequent A Likely B Occasional C Seldom D Unlikely E Catastrophic I E (1) E (1) H (2) H (2) M (3) Critical II E (1) H (2) H (2) M (3) L (4) Marginal III H (2) M (3) M (3) L (4) L (5) Negligible IV M (3) L (4) L (4) L (5) L (5)
Table 4. Risk Matrix Codes and Descriptions Risk Assessment Code (RAC) Description
1 Extremely High 2 High 3 Moderate 4 Low 5 Low
1.5 Risk Summation. The following categories are derived using the Risk Matrix.
a. Extremely High - Loss of ability to accomplish the mission or the mission produces extremely severe outcomes. This implies that the risk associated with this mission, activity, or event may have severe consequences beyond those associated with this specific operation or event. The decision to continue must be weighted carefully against the potential gain to be achieved by continuing this course of action. This decision must then be approved at an appropriate level of command.
b. High - Significant degradation of mission capabilities in terms of the required mission standard, inability to accomplish all parts of the mission, high potential for serious injury to personnel, or inability to complete the mission to standard if hazards occur during the mission. This implies that if a hazardous event occurs, serious consequences will occur.
The decision to continue must be weighted carefully against the potential gain to be achieved by continuing this course of action. This decision must then be approved at an appropriate level of command.
Risk Assessment / Probability Assessment 1-5
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
c. Moderate - The ability to complete the mission will be slightly degraded in the event this hazard occurs. If a hazardous event occurs, the event will only slightly impact on the mission, result in only minor injury or loss, and not affect overall readiness.
d. Low - Expected losses have little or no impact on accomplishing the mission. Injury, damage, or illness will be minor and have no long-term impact or effect.
1.6 This assessment is applicable to any intrusive activity (i.e., subsurface disturbance), which would include trenching, grading, borings, or well installations as examples. This assessment, however, does not cover and is not applicable for above grade work, facility repairs, or routine maintenance that does not involve intrusive ground disturbing activities.
Risk Assessment / Probability Assessment 2-1
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
2.0 History of Possible CWM Storage Area
2.1 The Possible CWM Storage Area is located south of the main runway near the coastline just west of Deer Point, at N 53º 22′ 04.6″ W 167º 53′ 11.9″ according to the Corps of Engineers, St. Louis (CELMS 2001). This site covers approximately 1 acre, is situated between the base of a high bluff and the Pacific Ocean. The site is very isolated, but there is an access road between the site and the main airfield.
2.2 The ASR (CELMS 2001) and subsequent site reconnaissance identified three bunkers at this site. These bunkers are Quonset structures with their back end toward the bluff.
Typically, this type of structure would be earth covered and sealed at both ends with only one door. During the ASR site reconnaissance, only one of the bunkers still had its original earth covering, and all three bunkers had their doors removed. No records were available for review that indicated the type and amount of munitions stored in the bunkers; however, historical documents found during the ASR refer to the transfer of 15 each Mustard Gas cylinders (1 ton containers), 38 Lewisite Gas cylinders (1 ton containers), and 75 millimeter
(mm) HS filled projectiles (37 tons) from Fort Glenn. The ASR noted the remains of a building immediately to the west and identified this building on historical maps as a possible Chemical Warfare Service (CWS) facility.
2.3 A site visit was conducted at the former Fort Glenn on June 18 and 19, 2003, to evaluate the site conditions and confirm the findings of the ASR. This site visit is documented in the CWM Scoping and Security Study Report (Parsons 2006), as follows:
“The possible Chemical Storage Area consists of three metal Quonset huts located on a remote bluff, overlooking the Pacific coastline. The three huts back up to a steep cliff (50 to 70 feet in height) and are fronted by a roadway from the airfield area. This area is located in the extreme southeastern portion of the Fort Glenn airfield. No ordnance or CWM was noted in the three Quonset huts or in adjacent areas. No visual evidence of chemical agent residuals or degraded environment resulting from possible chemical agent storage practices was evident at this site.”
2.4 Further reconnaissance was done in July and August, 2004 as part of the CWM Scoping and Security Study Report (Parsons 2006). This reconnaissance at the Possible CWM Storage Area produced no noticeable evidence of buried trenches, only drainage trenches that were marked with GPS. No evidence of CWM or ordnance contamination was found at the Possible CWM Storage Area (Parsons 2006).
Risk Assessment / Probability Assessment 3-1
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
3.0 Probability of Encountering CWM
3.1 Historical records and site reconnaissance for the entire Fort Glenn facility have documented that CWM was present at the former Ft. Glenn; however, no records were available for review that indicated the type and amount of munitions stored at the Possible CWM Storage Area. Site reconnaissance at the Possible CWM Storage Area has produced no noticeable evidence of buried trenches, and no evidence of CWM or ordnance contamination was found at the Possible CWM Storage Area (Parsons, 2006). None of the historical documents reviewed nor other information provided heretofore has indicated that either chemical or conventional munitions were buried in this area.
3.2 The planned Remedial Investigation (RI) fieldwork will involve soil borings next to the storage bunkers. Based on historical information, soils at the storage bunkers may contain residual chemical agent dispersed within the soil matrices.
3.3 The hazard probability of encountering CWM or CAIS in this area is judged to be ‘Unlikely’ (E) based on historical site use. The severity of encountering CWM or CAIS is judged to be ‘Critical’ (II) based on the potential for work disruption and worker exposures.
The resultant RAC is ‘Low’. Based on a ‘Low’ RAC score, intrusive work will not require a Chemical Warfare Materiel Site Plan (CSP).
Risk Assessment / Probability Assessment 4-1
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
4.0 Summary and Conclusion
The conclusion is based on the information provided above, and the Chemical Warfare Materiel Responses and Related Activities, Interim Guidance (1 April 2009) and DA PAM 385-30, Mishap Risk Management (10 October 2007). The hazard probability of encountering CWM or CAIS in the Possible CWM Storage Area is judged to be ‘Low’.
However, the planned soil boring activities should take into account the possibility of encountering soil contaminated with chemical agent, to include mustard. Work at these areas can be conducted under a work plan and without a Chemical Site Plan (CSP). Work will require agent monitoring and worker protection. If an intact CWM item is identified in the field, work will stop and a contingency plan will be initiated.
Risk Assessment / Probability Assessment 5-1
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
5.0 Historical Information
5.1 Site-Specific Work to Date Summary
• 2001 historical records review and site reconnaissance detailed in Archive Search
Report (ASR), by CELMS.
• 2003 site reconnaissance detailed in CWM Scoping and Security Study Report, by Parsons, 2006.
• 2004 site reconnaissance detailed in CWM Scoping and Security Study Report, by Parsons, 2006.
• 2004 historical aerial photo analysis detailed in the Special Assessment GIS-Based Historical Photographic Analysis by the Topographic Engineering Center (TEC).
5.2 References
• CELMS 2001. Archives Search Report Findings for Fort Glenn, Umnak Island, Alaska. September.
• Ferris and Bivens 2002. SSG Tom Ferris & SGT John Bivens. 24-29Jul02 Combined Incident to Kodiak and Fort Glenn, Alaska. July.
• Parsons 2006. Site Specific Chemical Warfare Materiel Scoping and Security Study Report, Formerly Used Defense Site (FUDS) Site Inspection Report: Fort Glenn.
Draft Final Revision 2. August 20.
• U.S. Army Engineer Research and Development Center, Topographic Engineering Center. 2004. Fort Glenn – Umnak Island, Alaska: Special Assessment GIS-Based Historical Photographic Analysis. June.
Risk Assessment / Probability Assessment 6-1
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
6.0 Photographic Analysis - Historical Documentation and Maps
1. Fort Glenn Army Airfield. (Parsons 2004)
Risk Assessment / Probability Assessment 6-2
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
2. Ft Glenn, AK, Potential Hazard Areas, Map A.
3. Ft Glenn, AK, Potential Hazard Areas Overview Map.
Risk Assessment / Probability Assessment 6-3
I:\Fort Glenn\4. Deliverables\4.6 CSS and CSP\4.6.3 Probability Assessment\Revised Final\PA_Possible CWM Storage Area_Final_Rev1
4. 1942 Deer Point Area (ERDC-TEC, 2004). The CWM Storage Area is at the middle circle of the three circles on the left side marked “disturbed ground”.
5. Photos of Possible CWM Storage Area. (Ferris and Bivens, 2002)
DISTURBED GROUND
Prepared By:
Risk AssessmentlProbability Determination for the Former Fort Glenn Areas
Possible CWM Storage Area
J!.~"'~ 4 . l~lZ-"-
John Heinicke ~ Project Manager DRS, Inc.
arIes Twing Chief, Chemical Warfare Design enter U.S. Army Corps of Engineers, Huntsville Center ram Manager U.S. Army Corps of Engineers, Alaska District
?Z3{J1? roved .
r- 02 ~I
'lJ1f"r) Reinhard W. Koenig Colonel, U.S: Army U.S. Army Corps of Engineers, Alaska District
Risk Assessment I Probability Assessment Ammunition Storage Area, Former Fort Glenn, Umnak Island, AK Q:\1611\0581\Probabiliry Assessment\Revised Fina\\PA_Possible CWM Storage Nea_Final_Rev2
3-6-2012 Date
3 ~f{ J2.
Date
POA STAFF ACTION SUMMARY 1. CONTROL# 2. Suspense 2012-03-28
PM-12-039 3. Today's Date 2012-03-07
4. Subject Former Fort Glenn-Umnak Island Risk Assessment/Probability Assessment Final Revision Fl0AK02980S
5. Office Symbol 6. Action Officer 7. Telephone # 8. E-mail
PM-ESP-FUDS Carey Cossaboom (907)753-2689 carey .c.cossaboom@usace.army .mil
COORDINATION
9. Division 10. Name 11. Concur/Nonconcur 12. Comments 13. Date l~m __ m..J DC COL Reinhard W. Koenig r;J 3 Atll'l -
I~ ___ m __ ; DDC LTC James R. Stone ~- 1- (/tP.c. Il
[~ __ mm_: DPM Larry McCallister I":
L-Ao..--/L. {../}'V\. -
0 EA -_ . ...... ____ ,. __ J
0 EN -
D CO -
14. Routing [g] DC [g] DOC [g] DPM 10 EN 10 co
15. For: Information 01 Read-Ahead 0 1 Decision 0 1 Approval 0 T Signature [g]
16. PURPOSE/BOnOM LINE/DISCUSSION:
1. PURPOSE: To assess the likelihood that hazardous chemical warfare materiel (CWM) will be encountered in the field while conducting fieldwork at the Fort Glenn FUDS.
2. BOTTOM LINE: At the Ammunitions Storage Area, the risk of encountering hazardous CWM is high. Therefore, a Chemical Siting Plan (CSP) which includes full monitoring and mitigation support will be required to conduct work here. The risk of encountering hazardous CWM at the Possible CWM Storage Area and the Decontamination Areas A and B is low and will not require that work be done under a CSP. IfCWM is encountered at these areas, work will stop and a contingency plan will be initiated.
3. DISCUSSION: A former Ordnance Officer at Fort Glenn (he is also a retired university professor) recalled burying CWM at Fort Glenn in 1942. Geophysical investigations in 2004 revealed magnetic anomalies in the subsurface of the Ammunitions Storage Area that could be caused by a cache of ordnance that was described by the former Ordnance Officer. These magnetic anomalies have not yet been investigated. The plan is to investigate them in 2013.
4. RESOURCE IMPACT: None. Huntsville USACE (HNC) has issued a contract to create the CSP and conduct this work.
5. ROUTING: PM»ESP»Smith»OC»DPM»DDC»DC
6. Control Number: PM-12-039
17. Releaser: Clare Jaeger ~j ofCh-~~
18. Recommendation: The Colonel should sign the three G:a"babilh? Assessments for Fort Glenn.
19. Action: 1 Approved 0 1 See Me o 1 Other
POA FORM 1-R, APR 2010 PREVIOUS EDITIONS ARE OBSOLETE.
PROPONENT: DE
VERSION 1.0
| RISK ASSESSMENT/PROBABILITY ASSESSMENT POSSIBLE CWM STORAGE AREA |
| Title Page |
| Table of Contents |
| List of Tables |
| Acronyms and Abbreviations |
| 1.0 Introduction |
| Table 1 - Mishap Risk Management Process Probability Categories |
| Table 2 - Mishap Risk Management Process Severity Categories |
| Table 3 - Standardized Army Risk Matrix |
| Table 4 - Risk Matrix Codes and Descriptions |
| 2.0 History of Possible CWM Storage Area |
| 3.0 Probability of Encountering CWM |
| 4.0 Summary and Conclusion |
| 5.0 Historical Information |
| 6.0 Photographic Analysis - Historical Documentation and Maps |
| Signature Page |
File details come from the government source that posted it.