AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROJECT TITLE / LOCATION: F-35 CONSOLIDATED MUNITIONS ADMIN FACILITY, EIELSON AIR FORCE BASE (AFB), ALASKA (EIE386)
a. This amendment provides changes to the solicitation as indicated on the continuation pages of this document.
b. PHASE 2 PROPOSAL DUE DATE IS HEREBY EXTENDED UNTIL 16 FEBRUARY 2018 AT 1400 ALASKA TIME. Proposals shall be submitted in accordance w ith Section 00 21 00, paragraph 1.9, Proposal Format.
c. YOU ARE REQUIRED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE OF THE STANDARD FORM 1442.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 07-Feb-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911KB-17-R-0044
X 9B. DATED (SEE ITEM 11)
29-Sep-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
07-Feb-2018
CODE
U.S. ARMY ENGINEER DISTRICT, AK
CEPOA-CT (W911KB)
PO BOX 6898
JBER AK 99506-0898
W911KB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911KB-17-R-0044
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
a. The following drawings are substituted for the superseded documents/sections:
- A-601
- A-602
b. The following revised documents/sections are substituted for the superseded documents/sections. The identifier “AM#7” appears before and after new and/or revised materials, except as noted below.
SECTION 00 11 00 – PROPOSAL SCHEDULE
- Reissuing entire Proposal Schedule in AM#7
RFP Table of Contents – Part 2
- Added Section 02 82 13.00 10 – ASBESTOS ABATEMENT
SECTION 01 10 00 – STATEMENT OF WORK
- Revised paragraphs 3.7 and 3.8.1.6 (Reissuing pages 61 and 78)
c. The following sections are deleted:
NONE
d. The following documents are added:
SECTION 02 82 13.00 10 – ASBESTOS ABATEMENT
e. The following revisions are incorporated:
f. Other:
(End of Summary of Changes)
ALL OTHER TERMS AND CONDITIONS SHALL REMAIN THE SAME.
PROPOSAL SCHEDULE
F-35A CONSOLIDATED MUNITIONS ADMINISTRATIVE FACILITY
EIELSON AFB, ALASKA
BASE ITEMS
Item No.
Description Estimated Quantity
Unit Unit Price Amount
0001 Design Consolidated Munitions Administrative Facility, site work and utilities, Complete.
1 Job $_________ $_________
0002 Construct Consolidated Munitions Administrative Facility within the bldg. 5-foot lines, Complete.
1 Job $_________ $_________
0003 Construct site work and utilities beyond the bldg. 5-foot lines, Complete.
1 Job $_________ $_________
0004 Dispose of 2,500 Cubic Yards of POL Contaminated Soil, Complete *
2,500 CY $_________ $_________
0005 Disposal of 100 Cubic Yards of Barium Contaminated Soil, Complete *
100 CY $_________ $_________
0006 Dispose of 20,000 Cubic Yards of Non-Contaminated Soil, Complete. **
20,000 CY $_________ $_________
Total of Base Item 0001 to 0006 $_________
OPTION ITEMS
Item No.
Description Estimated Quantity
Unit Unit Price Amount
0007 Dispose of 2,500 Cubic Yards of POL Contaminated Soil, Complete *
2,500 CY $_________ $_________
0008 Disposal of 100 Cubic Yards of Barium Contaminated Soil, Complete *
100 CY $_________ $_________
0009 Unsatisfactory Material Excavation and Backfill. *** 100 CY $_________ $_________
AM#7…
Remove and dispose of Asbestos containing materials, Complete****
…AM#7 LF $_________ $_________
Total Optional Items 0007 to AM#7… 0010 …AM#7 $_________
F-35A CONSOLIDATED MUNTIONS ADMIN FACILITY
EIE386
W911KB-17-R-0044
AM#7
Proposal Schedule Page 1 of 2
Total of Base and Optional Items 0001 thru AM#7… 0010 …AM#7 $_________
Proposed Contract Duration: ____________________
For CLINs 0004, 0005, 0006, 0007, 0008, 0009, AM#7… and 0010 …AM#7 are estimated quantities. Equitable adjustments will be made in accordance with FAR CLAUSE 52.211-18, VARIATION IN ESTIMATED QUANTITY (APR 1984). No additional time will be added to the contract completion date if any of these options are exercised.
* For CLINs 0004 – 0005 and Option Item CLINs 0007 and 0008, the Contractor shall keep a record of the amount of contaminated soil being disposed of. This is the soil determined to be contaminated through the testing of soil from those areas identified in Appendix A/sheet C-101 as requiring 100% stockpiling and sampling. Soil determined to be clean shall be disposed of as shown on the drawing. For CLINs 0004 – 0005 and Option Item CLINs 0007 and 0008, these CLINs can be awarded at any time during the Construction Contract period. CLIN 0007 can be awarded up to two times and 0008 can be awarded up to five times.
**For CLIN 0006, the Contractor shall keep a record of the amount of non-contaminated soil being disposed of. This is soil from those areas identified in Appendix A/sheet C-101 as requiring 100% stockpiling which has been tested and determined to be clean. Soil shall be disposed on base at a clean soil disposal area within 3 miles of the stockpile area, as directed by the Contracting Officer.
*** Work on CLIN 0009 shall be the cost for work identified in Specs 01 10 00. The Contractor shall survey the extent of excavation and keep a record of the unsatisfactory material removed and disposed of. This CLIN can be awarded up to 10 times. For CLIN 0009, this option can be awarded at any time during the Construction Contract Period.
AM#7… **** For CLIN 0010, the Contractor shall keep a record of the amount of material being removed and disposed of. This CLIN can be awarded up to 5 times. This option can be awarded at any time during the Construction Contract period. …AM#7
EVALUATION OF OFFERS.
1. AWARD: Award will be made in accordance with Section 00 22 20 - EVALUATION
FACTORS FOR AWARD.
2. INCOMPLETE OFFERS: Failure to submit an offer on all items in the schedule constitutes an incomplete offer. Incomplete offers may be rejected. Lump sum or unit prices must be shown for each item within the schedule.
3. EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.
-- END OF PROPOSAL SCHEDULE --
EIE386
W911KB-17-R-0044
Proposal Schedule Page 2 of 2 i
REQUEST FOR PROPOSAL
TABLE OF CONTENTS – PART 2
GENERAL REQUIREMENTS AND TECHNICAL PROVISIONS
DIVISION 01 – GENERAL REQUIREMENTS
01 10 00 STATEMENT OF WORK
01 19 30.02 29 SPECIAL ITEMS FOR EIELSON AFB PROJECTS
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 16.00 29 DESIGN AFTER AWARD
01 35 26 GOVERNMENT SAFETY REQUIREMENTS
01 36 00.00 29 RADIOACTIVE MATERIALS PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.00 29 CONTRACTOR QUALITY CONTROL
01 50 00.04 29 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS FOR EIELSON
AFB PROJECTS
01 57 20.01 29 ENVIRONMENTAL PROTECTION
01 57 34.00 29 STORM WATER POLLUTION PREVENTION MEASURES
01 58 00 PROJECT IDENTIFICATION
01 74 19.01 29 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00.15 TOTAL BUILDING COMMISSIONING
DIVISION 02 – EXISTING CONDITIONS
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
AM#7…
02 82 13.00 10 ASBESTOS ABATEMENT …AM#7
DIVISION 31 – EARTHWORK
31 09 20.00 29 FIELD SCREEN TESTING OF SOILS FOR CHEMICAL CONTAMINATION
01 10 00
3.7 HEATING, VENTILATION AND AIR CONDITIONING (HVAC)
The services covered by this section include all labor, material, supplies, and incidental work required for the design, installation and testing of all heating, ventilation, and air conditioning systems supporting the FY18 F-35A Consolidated Munitions Admin Facility Project at Eielson AFB. The contractor shall perform design and construction services as required to provide a complete and usable facility.
The planned facility will support the increase in mission and population associated with the bed-down of F-35 aircraft by providing administrative spaces for Munitions Command, Control, Operations, Mobility, Line Delivery, Storage, Conventional Munitions Training, and Munitions Support Equipment Maintenance functions. Additionally, three open bay area will be constructed to provide Heated Vehicle Storage, Conventional Munitions Training, and Munitions Support Equipment Maintenance activities. The building site is adjacent to an existing utilidor with steam, condensate, domestic water, fire protection water, and a forced main sanitary sewer.
NOTE: The adjacent utilidor and its enclosed utilities are to be upgraded under a separate project (EIE405). Anticipated construction period is between May 2018 and September AM#7… 20192018 for portion of EIE405 serving this project site. …AM#7 The construction contractor shall not anticipate connection to, or use of, steam or condensate lines, water, or sewer prior to AM#7…01 September 20192018. …AM#7 The contractor shall be responsible for providing its own temporary utilities for freeze-proofing, heating, pressure testing, flushing, etc. prior to this date.
The mechanical design and construction shall be coordinated with all other trades. The facility and equipment shall be permanent construction. The contractor shall reference the listed applicable design criteria, standards for equipment and material selection. The contractor is required to provide equipment, materials, and installation methods according to the un-edited versions of the UFGS (Unified Facilities Guide Specifications). Where multiple materials and methods are provided for in the UFGS, all options are available to contractor with the exception of specific requirements called for in this RFP.
The design shall be provided in accordance with the requirements of this document and shall use the referenced applicable technical criteria and standards.
Technical Criteria and Standards
3.7.1.1 The Contractor’s Designer of Record (DOR) shall submit the Mechanical design drawings, design analysis, and specifications for the F-35A Consolidated Munitions Admin Facility Project in accordance with Section 01 33 16.00 29 Design After Award, and as required in other parts of this RFP.
3.7.1.2 See Paragraph 4.0 for Applicable Criteria.
Energy Conservation
3.7.2.1 Energy conservation measures shall be incorporated in the design of this project. The building mechanical systems shall comply with ASHRAE 90.1-2010 and meet EPACT 2005. HPSB (High Performance Sustainable Building), LEED, and Air Force MILCON sustainability requirements apply (see Paragraph 3.13 SUSTAINABILITY for details).
3.7.2.2 The facility shall be designed to achieve a minimum of 10 LEED points under EAC1 (Energy and Atmosphere Credit 1) by using 30 percent less energy relative to the baseline ASHRAE 90.1 2007 building.
3.7.2.3 The Contractor shall provide a sustainable design that takes into account the energy and environmental impacts of operating and maintaining the building. All designs, drawings, and specifications shall specify materials and systems that reduce the need for maintenance, and/or require less water, energy, and toxic chemicals and cleaners to maintain.
F-35A CONSOLIDATED MUNTIONS ADMIN FACILITY
EIE386
01 10 00
3.8.1.4 Site Lighting shall be LED type, and provided for personnel entryways, and for overhead doors. Provide pole mounted LED fixtures to illuminate walkways, parking lots, and driveways.
3.8.1.5 Facility Lighting shall be LED type fixtures. Provide exit and egress LED lighting with emergency battery packs.
3.8.1.6 Facility Security – Rough-in AM#7… access control CCTV system at the entrance to the facility and at the entrance to the Munitions Control with CCTV rough in. …AM#7 Provide Electronic Key Access System in accordance with AM#7… 3.4.2.12.1 3.4.2.13 …AM#7 in this RFP. No Intrusion detection is required.
3.8.1.7 Intercom – An intercom system shall not be required.
3.8.1.8 HBO outlets for POV - Provide headbolt outlets (HBO) for POV vehicles arranged to match the new parking areas. The standard Eielson HBO design shall be used.
3.8.1.9 Facility Telecommunications service to the new facility shall consist of new underground copper and fiber cables. There is an existing communications ductbank running from building 3446 to building 3425. Fiber shall be picked up at building 3425, and extended to building 3446 via this existing ductbank (where there is an existing comm manhole to the east of Bldg 3446). The fiber cables shall then be routed across Industrial Drive, and then extended to new building in a new ductbank provided under this contract. Coordination with EIE405 and the associated extension and routing of new utiliduct across Industrial Drive at this location is strongly encouraged. Coordination with the EIE378 Project (F-35 Aircraft Weather Shelter Squad #1) may be necessary, as well. New Copper OSP shall be routed from an existing manhole between the new parking area and Industrial Drive. Extend cables along Industrial Drive to meet fiber conductors, and then route all conductors together to the new Munitions Administration Facility Electrical Room. All new underground copper and fiber cable shall be encased in schedule 80 PVC at a minimum depth of 36 inches. All installations that cannot achieve this depth, and where they pass under roadways or railways must be concrete encapsulated.
3.8.1.10 A lightning protection analysis shall be performed to ascertain whether or not a lightning protection system is required, as identified in Letter from Gary Kitkowski, Department of the Army, of 16 December 2014, in the Appendix.
3.8.2 Site Power
3.8.2.1 Provide power to the facility, tapping from the existing 7200 volt 3-wire 3-phase aerial located to the south of the site. Referring to V-101, Feeder #1 (the upper circuit) will be upgraded under project EIE378. Work on this feeder may impact work under this contract. It is anticipated that Feeder #2 (the lower circuit) will be the source of power for this contract. A new Feeder #15 will be constructed under project EIE378, and will pass through the staging area. Outages associated with Feeder 2 and EIE378 are anticipated. Contractor shall coordinate with this project.
3.8.2.2 Medium voltage circuits – Medium voltage cables shall be 15kv single copper conductor, 133% ethylene-propylene-rubber (EPR) insulation, copper shield and a nonmetallic jacket installed in raceway. A full-sized, 600 Volt, XHHW-2, insulated copper neutral shall be provided for future conversion to 12,470 volt. All underground medium voltage circuits shall be installed in concrete encased duct bank. Above ground medium voltage circuits shall be installed in PVC coated rigid steel conduit.
3.8.2.3 Secondary Circuits – Circuits shall be 600 volt, copper conductor, with XHHW-2 insulation installed in raceway. Raceway installed under traffic areas shall be concrete encased, thin-wall PVC or factory PVC coated rigid steel conduit. Above grade secondary circuits shall be installed in rigid steel conduit.
F-35A CONSOLIDATED MUNITIONS ADMIN FACILITY W911KB-17-R-0044
EIE386 AM#7
SECTION TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 82 13.00 10
ASBESTOS ABATEMENT (ADDED BY AM#7)
PART 1 GENERAL
1.1 PAYMENT PROCEDURES
1.2 REFERENCES
1.3 DEFINITIONS
1.3.1 Amended Water
1.3.2 Asbestos-Containing Material (ACM)
1.3.3 Authorized Person
1.3.4 Building Inspector
1.3.5 Class I Asbestos Work
1.3.6 Class II Asbestos Work
1.3.7 Class III Asbestos Work
1.3.8 Class IV Asbestos Work
1.3.9 Clean Room
1.3.10 Competent Person
1.3.11 Contractor/Supervisor
1.3.12 Critical Barrier
1.3.13 Decontamination Area
1.3.14 Demolition
1.3.15 Disposal Bag
1.3.16 Disturbance
1.3.17 Equipment Room or Area
1.3.18 Fiber
1.3.19 Friable ACM
1.3.20 Glovebag
1.3.21 High-Efficiency Particulate Air (HEPA) Filter
1.3.22 Intact
1.3.23 Model Accreditation Plan (MAP)
1.3.24 Negative Initial Exposure Assessment
1.3.25 NESHAP
1.3.26 Nonfriable ACM
1.3.27 Nonfriable ACM (Category I)
1.3.28 Nonfriable ACM (Category II)
1.3.29 Permissible Exposure Limits (PELs)
1.3.29.1 PEL-Time Weighted Average(TWA)
1.3.29.2 PEL-Excursion Limit
1.3.30 Regulated Area
1.3.31 Removal
1.3.32 Repair
1.3.33 Surfacing ACM
1.3.34 Thermal System Insulation (TSI) ACM
1.3.35 Transite
1.3.36 Worker
1.4 SYSTEM DESCRIPTION
1.4.1 Abatement Work Tasks
1.4.2 Unexpected Discovery of Asbestos
Section 02 82 13.00 10
1.4.3 Wallboard/Joint Compound (NOT USED)
1.5 SUBMITTALS
1.6 QUALITY ASSURANCE
1.6.1 Written Qualifications and Organization Report
1.6.2 Specific Requirements
1.6.3 Federal, State or Local Citations on Previous Projects
1.6.4 Preconstruction Conference
1.7 SAFETY
1.7.1 Asbestos Hazard Abatement Plan Appendix
1.7.2 Activity Hazard Analyses Appendix
1.8 SECURITY
1.8.1 Licenses, Permits and Notifications
1.8.2 Regulated Areas
1.8.3 Warning Signs and Tape
1.8.4 Warning Labels
1.9 MEDICAL SURVEILLANCE REQUIREMENTS
1.9.1 Respiratory Protection Program
1.9.2 Respiratory Fit Testing
1.9.3 Respirator Selection and Use Requirements
1.9.4 Personal Protective Equipment
1.9.5 Whole Body Protection
1.9.5.1 Coveralls
1.9.5.2 Gloves
1.9.5.3 Foot Coverings
1.9.5.4 Head Covering
1.9.5.5 Protective Eye Wear
1.10 HYGIENE
1.10.1 Single Stage Decontamination Area
1.10.2 Smoking
PART 2 PRODUCTS
2.1 ENCAPSULANTS
2.2 ENCASEMENT PRODUCTS
2.3 EXPENDABLE SUPPLIES
2.3.1 Duct Tape
2.3.2 Disposal Containers
2.3.3 Sheet Plastic
2.3.3.1 Flame Resistant
2.3.3.2 Reinforced
2.3.4 Leak-tight Wrapping
2.4 EQUIPMENT
2.4.1 Scales
2.4.2 Tools
2.4.3 Rental Equipment
2.4.4 Air Monitoring Equipment
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 PROTECTION OF ADJACENT WORK OR AREAS TO REMAIN
3.3 BUILDING VENTILATION SYSTEM AND CRITICAL BARRIERS (NOT USED)
3.4 METHODS OF COMPLIANCE
3.4.1 Mandated Practices
3.4.2 Control Methods
3.4.3 Unacceptable Practices
3.4.4 Class II Work
3.4.5 Specific Control Methods for Class II Work
3.4.5.1 Roofing Material (NOT USED)
3.4.5.2 Cementitious Siding and Shingles or Transite Panels (NOT
USED)
3.4.6 Class I Asbestos Work Response Action Detail Sheets
3.4.7 Class II Asbestos Work Response Action Detail Sheets
3.5 FINAL CLEANING AND VISUAL INSPECTION
3.6 EXPOSURE ASSESSMENT AND AIR MONITORING
3.6.1 General Requirements
3.6.2 Initial Exposure Assessment
3.6.3 Negative Exposure Assessment
3.6.4 Independent Environmental Monitoring (NOT USED)
3.6.5 Environmental Air Monitoring During Abatement
3.6.6 Air-Monitoring Results and Documentation
3.7 CLEARANCE CERTIFICATION
3.8 CLEANUP AND DISPOSAL
3.8.1 Title to ACM Materials
3.8.2 Collection and Disposal of Asbestos
3.8.3 Records and Management Plan
3.8.3.1 Asbestos Waste Shipment Records
3.8.3.2 Asbestos Management Plan
ATTACHMENTS:
Table 1
"Certificate of Workers Acknowledgment"
Training course completion certificates
Table 3
Table 2
-- End of Section Table of Contents --
SECTION 02 82 13.00 10
ASBESTOS ABATEMENT (ADDED BY AM#7)
PART 1 GENERAL
1.1 PAYMENT PROCEDURES
Submit copies of weight bills and delivery tickets for payment to the Contracting Officer during the progress of the work. Furnish scale tickets for each load of ACM weighed and certified. These tickets must include tare weight; identification mark for each vehicle weighed; and date, time and location of loading and unloading. Tickets must be furnished at the point and time individual trucks arrive at the worksite. A master log of all vehicle loading must be furnished for each day of loading operations.
Before the final statement is allowed, file with the Contracting Officer certified weigh bills and/or certified tickets and manifests of all ACM actually disposed by the Contractor for this contract.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D4397 (2016) Standard Specification for Polyethylene Sheeting for Construction, Industrial, and Agricultural Applications
ASTM E1368 (2014) Visual Inspection of Asbestos Abatement Projects
COMPRESSED GAS ASSOCIATION (CGA)
CGA G-7 (2014) Compressed Air for Human Respiration; 6th Edition
INTERNATIONAL SAFETY EQUIPMENT ASSOCIATION (ISEA)
ANSI/ISEA Z87.1 (2015) Occupational and Educational Personal Eye and Face Protection Devices
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 701 (2015) Standard Methods of Fire Tests for Flame Propagation of Textiles and Films
NATIONAL INSTITUTE FOR OCCUPATIONAL SAFETY AND HEALTH (NIOSH)
NIOSH NMAM (2016; 5th Ed) NIOSH Manual of Analytical Methods
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
EP 1110-1-11 (1992; Change 1 1997) Engineering and Design -- Asbestos Abatement Guideline Detail Sheets
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 340/1-90/018 (1990) Asbestos/NESHAP Regulated Asbestos Containing Materials Guidance
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.134 Respiratory Protection
29 CFR 1910.147 Control of Hazardous Energy (Lock Out/Tag Out)
29 CFR 1926.1101 Asbestos
29 CFR 1926.32 Safety and Health Regulations for Construction - Definition
40 CFR 61 National Emission Standards for Hazardous Air Pollutants
40 CFR 763 Asbestos
42 CFR 84 Approval of Respiratory Protective Devices
49 CFR 107 Hazardous Materials Program Procedures
49 CFR 171 General Information, Regulations, and Definitions
49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements
49 CFR 173 Shippers - General Requirements for Shipments and Packagings
1.3 DEFINITIONS
1.3.1 Amended Water
Water containing a wetting agent or surfactant with a surface tension of at least 29 dynes per square centimeter.
1.3.2 Asbestos-Containing Material (ACM)
Any materials containing more than one percent asbestos.
1.3.3 Authorized Person
Any person authorized by the Contractor and required by work duties to be present in the regulated areas.
1.3.4 Building Inspector
Individual who inspects buildings for asbestos and has EPA Model Accreditation Plan (MAP) "Building Inspector" training; accreditation required by 40 CFR 763, Subpart E, Appendix C, has EPA/State certification/license as a "Building Inspector".
1.3.5 Class I Asbestos Work
Activities defined by OSHA involving the removal of thermal system insulation (TSI) and surfacing ACM.
1.3.6 Class II Asbestos Work
Activities defined by OSHA involving the removal of ACM which is not thermal system insulation or surfacing material. This includes, but is not limited to, the removal of asbestos - containing wallboard, floor tile and sheeting, roofing and siding shingles, and construction mastic. Certain "incidental" roofing materials such as mastic, flashing and cements when they are still intact are excluded from Class II asbestos work. Removal of small amounts of these materials which would fit into a glovebag may be classified as a Class III job.
1.3.7 Class III Asbestos Work
Activities defined by OSHA that involve repair and maintenance operations, where ACM, including TSI and surfacing ACM, is likely to be disturbed.
Operations may include drilling, abrading, cutting a hole, cable pulling, crawling through tunnels or attics and spaces above the ceiling, where asbestos is actively disturbed or asbestos-containing debris is actively disturbed.
1.3.8 Class IV Asbestos Work
Maintenance and custodial construction activities during which employees contact but do not disturb ACM and activities to clean-up dust, waste and debris resulting from Class I, II, and III activities. This may include dusting surfaces where ACM waste and debris and accompanying dust exists and cleaning up loose ACM debris from TSI or surfacing ACM following construction.
1.3.9 Clean Room
An uncontaminated room having facilities for the storage of employees' street clothing and uncontaminated materials and equipment.
1.3.10 Competent Person
In addition to the definition in 29 CFR 1926.32(f), a person who is capable of identifying existing asbestos hazards as defined in 29 CFR 1926.1101, selecting the appropriate control strategy, has the authority to take prompt corrective measures to eliminate them and has EPA Model Accreditation Plan (MAP) "Contractor/Supervisor" training; has EPA/State certification/license as a "Contractor/Supervisor".
1.3.11 Contractor/Supervisor
Individual who supervises asbestos abatement work and has EPA Model Accreditation Plan "Contractor/Supervisor" training; has EPA/State certification as a "Contractor/Supervisor".
1.3.12 Critical Barrier
One or more layers of plastic sealed over all openings into a regulated area or any other similarly placed physical barrier sufficient to prevent airborne asbestos in a regulated area from migrating to an adjacent area.
1.3.13 Decontamination Area
An enclosed area adjacent and connected to the regulated area and consisting of an equipment room, shower area, and clean room, which is used for the decontamination of workers, materials, and equipment that are contaminated with asbestos.
1.3.14 Demolition
The wrecking or taking out of any load-supporting structural member and any related razing, removing, or stripping of asbestos products.
1.3.15 Disposal Bag
A 6 mil thick, leak-tight plastic bag, pre-labeled in accordance with 29 CFR 1926.1101, used for transporting asbestos waste from containment to disposal site.
1.3.16 Disturbance
Activities that disrupt the matrix of ACM, crumble or pulverize ACM, or generate visible debris from ACM. Disturbance includes cutting away small amounts of ACM, no greater than the amount which can be contained in 1 standard sized glovebag or waste bag, not larger than 60 inches in length and width in order to access a building component.
1.3.17 Equipment Room or Area
An area adjacent to the regulated area used for the decontamination of employees and their equipment.
1.3.18 Fiber
A fibrous particulate, 5 micrometers or longer, with a length to width ratio of at least 3 to 1.
1.3.19 Friable ACM
A term defined in 40 CFR 61, Subpart M and EPA 340/1-90/018 meaning any material which contains more than 1 percent asbestos, as determined using the method specified in 40 CFR 763, Polarized Light Microscopy (PLM), that when dry, can be crumbled, pulverized, or reduced to powder by hand pressure.
1.3.20 Glovebag
Not more than a 60 by 60 inch impervious plastic bag-like enclosure affixed around an asbestos-containing material, with glove-like appendages through which material and tools may be handled.
1.3.21 High-Efficiency Particulate Air (HEPA) Filter
A filter capable of trapping and retaining at least 99.97 percent of all mono-dispersed particles of 0.3 micrometers in diameter.
1.3.22 Intact
ACM which has not crumbled, been pulverized, or otherwise deteriorated so that the asbestos is no longer likely to be bound with its matrix. Removal of "intact" asphaltic, resinous, cementitious products does not render the ACM non-intact simply by being separated into smaller pieces.
1.3.23 Model Accreditation Plan (MAP)
USEPA training accreditation requirements for persons who work with asbestos as specified in 40 CFR 763.
1.3.24 Negative Initial Exposure Assessment
A demonstration by the Contractor to show that employee exposure during an operation is expected to be consistently below the OSHA Permissible Exposure Limits (PELs).
1.3.25 NESHAP
National Emission Standards for Hazardous Air Pollutants. The USEPA NESHAP regulation for asbestos is at 40 CFR 61, Subpart M.
1.3.26 Nonfriable ACM
A NESHAP term defined in 40 CFR 61, Subpart M and EPA 340/1-90/018 meaning any material containing more than 1 percent asbestos that, when dry, cannot be crumbled, pulverized or reduced to powder by hand pressure.
1.3.27 Nonfriable ACM (Category I)
A NESHAP term defined in 40 CFR 61, Subpart E and EPA 340/1-90/018 meaning asbestos-containing packings, gaskets, resilient floor covering, and asphalt roofing products containing more than 1 percent asbestos.
1.3.28 Nonfriable ACM (Category II)
A NESHAP term defined in 40 CFR 61, Subpart E and EPA 340/1-90/018 meaning any material, excluding Category I nonfriable ACM, containing more than 1 percent asbestos.
1.3.29 Permissible Exposure Limits (PELs)
1.3.29.1 PEL-Time Weighted Average(TWA)
Concentration of asbestos not in excess of 0.1 fibers per cubic centimeter of air (f/cc) as an 8 hour time weighted average (TWA).
1.3.29.2 PEL-Excursion Limit
An airborne concentration of asbestos not in excess of 1.0 f/cc of air as averaged over a sampling period of 30 minutes.
1.3.30 Regulated Area
An OSHA term defined in 29 CFR 1926.1101 meaning an area established by the Contractor to demarcate areas where Class I, II, and III asbestos work is conducted; also any adjoining area where debris and waste from such asbestos work accumulate; and an area within which airborne concentrations of asbestos exceed, or there is a reasonable possibility they may exceed, the permissible exposure limit.
1.3.31 Removal
All operations where ACM is taken out or stripped from structures or substrates, and includes demolition operations.
1.3.32 Repair
Overhauling, rebuilding, reconstructing, or reconditioning of structures or substrates, including encapsulation or other repair of ACM attached to structures or substrates.
1.3.33 Surfacing ACM
Asbestos-containing material which contains more than 1 percent asbestos and is sprayed-on, troweled-on, or otherwise applied to surfaces, such as acoustical plaster on ceilings and fireproofing materials on structural members, or other materials on surfaces for acoustical, fireproofing, or other purposes.
1.3.34 Thermal System Insulation (TSI) ACM
ACM which contains more than 1 percent asbestos and is applied to pipes, fittings, boilers, breeching, tanks, ducts, or other interior structural components to prevent heat loss or gain or water condensation.
1.3.35 Transite
A generic name for asbestos cement wallboard and pipe.
1.3.36 Worker
Individual (not designated as the Competent Person or a supervisor) who performs asbestos work and has completed asbestos worker training required by 29 CFR 1926.1101, to include EPA Model Accreditation Plan (MAP) "Worker" training; accreditation if required by the OSHA Class of work to be performed or by the state where the work is to be performed.
1.4 SYSTEM DESCRIPTION
This section covers all operations in which asbestos-containing materials (ACM) are encountered. These procedures and equipment are required to protect workers and building occupants from airborne asbestos fibers and ACM dust and debris. Activities include OSHA Class II work operations.
This section also includes containment, storage, transportation and disposal of the generated ACM wastes. Submit Detailed Drawings in accordance with EP 1110-1-11 and containing descriptions, and site layout to include worksite containment area(s), decontamination units other temporary waste storage facility, access tunnels, location of temporary utilities (electrical, water, sewer) and boundaries of each regulated area. When the detail sheets are not attached to this specification, the Contractor can get them from the web at:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerPamphlets/EP_1110
1.4.1 Abatement Work Tasks
The specific ACM to be abated is identified on Table 1. A summary for each work task including the appropriate RESPONSE ACTION DETAIL SHEET (item to be abated and methods to be used) and SET-UP DETAIL SHEETS (containment techniques to include safety precautions and methods) is included in Table 1, "Individual Work Task Data Elements" at the end of this section.
1.4.2 Unexpected Discovery of Asbestos
For any previously untested building components suspected to contain asbestos and located in areas impacted by the work, notify the Contracting Officer (CO) who will have the option of ordering up to 3 bulk samples to be obtained at the Contractor's expense and delivered to a laboratory accredited under the National Institute of Standards and Technology (NIST) "National Voluntary Laboratory Accreditation Program (NVLAP)" and analyzed by PLM. If the asbestos content is less than 10 percent, as determined by a method other than point counting, the asbestos content must be verified by point counting. Any additional components identified as ACM that have been approved by the CO for removal must be removed and will be paid for by an equitable adjustment to the contract price under the CONTRACT CLAUSE titled "changes". Sampling must be conducted by personnel who have successfully completed the EPA Model Accreditation Plan (MAP) "Building Inspector" training course and is EPA/State certified/licensed as a "Building Inspector".
1.4.3 Wallboard/Joint Compound (NOT USED)
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Detailed Drawings; G
SD-03 Product Data
Asbestos Waste Shipment Records; G
Weight Bills and Delivery Tickets
Encapsulants; G
Respiratory Protection Program; G
Cleanup and Disposal; G
Qualifications; G
Licenses, Permits and Notifications
Asbestos Management Plan; G
SD-06 Test Reports
Exposure Assessment and Air Monitoring
SD-07 Certificates
Encapsulants; G
Medical Surveillance Requirements
1.6 QUALITY ASSURANCE
In addition to detailed requirements of this specification, work performed under this contract must comply with EM 385-1-1, applicable federal, state, and local laws, ordinances, criteria, rules and regulations regarding handling, storing, transporting, and disposing of asbestos waste materials. Matters of interpretation of standards must be submitted to the appropriate administrative agency for resolution before starting work.
Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements must apply. The following state and local laws, rules and regulations regarding demolition, removal, encapsulation, construction alteration, repair, maintenance, renovation, spill/emergency cleanup, housekeeping, handling, storing, transporting and disposing of asbestos material apply: Alaska.
1.6.1 Written Qualifications and Organization Report
Submit a written qualifications and organization report providing evidence of qualifications of the Contractor, Contractor's Project Supervisor, Designated Competent Person, supervisors and workers; Designated IH;
independent testing laboratory; all subcontractors to be used including disposal transportation and disposal facility firms, subcontractor supervisors, subcontractor workers; and any others assigned to perform asbestos abatement and support activities. Include in the report an organization chart showing the Contractor's staff organization chain of command and reporting relationship with all subcontractors. The report must be signed by the Contractor, the Contractor's onsite project manager, Designated Competent Person, Designated IH, designated testing laboratory and the principals of all subcontractors to be used. Include the following statement in the report: "By signing this report I certify that the personnel I am responsible for during the course of this project fully understand the contents of 29 CFR 1926.1101, 40 CFR 61, Subpart M, and the federal, state and local requirements for those asbestos abatement activities that they will be involved in."
1.6.2 Specific Requirements
Designate in writing, personnel meeting the following qualifications:
a. Asbestos Abatement Contractor: Certified/licensed to perform asbestos-related activities.
b. Designated Competent Person: Qualified in accordance with 29 CFR 1926.32 and 29 CFR 1926.1101, has EPA MAP "Contractor/Supervisor" training accreditation, has EPA/State certification/license as a "Contractor/Supervisor" and is experienced in the administration and supervision of asbestos abatement projects, including exposure assessment and monitoring, work practices, abatement methods, protective measures for personnel, setting up and inspecting asbestos abatement work areas, evaluating the integrity of containment barriers, placement and operation of local exhaust systems, ACM generated waste containment and disposal procedures, decontamination units installation and maintenance requirements, site safety and health requirements, notification of other employees onsite, etc. The Designated Competent Person must be responsible for compliance with applicable federal, state and local requirements, the Contractor's Accident Prevention Plan (APP) and Asbestos Hazard Abatement Plan (AHAP). Submit the "Contractor/Supervisor" course completion certificate and the most recent certificate for required refresher training, EPA/State certification/license with the employee "Certificate of Worker Acknowledgment". Submit evidence that this person has a minimum of 2 years of on-the-job asbestos abatement experience relevant to OSHA competent person requirements. The Designated Competent Person must be onsite at all times during the conduct of this project.
c. Project and Other Supervisors:
d. Designated Industrial Hygienist: Resume for the Industrial Hygienist (IH) selected to prepare the Contractor's AHAP, prepare and perform training, direct air monitoring and assist the Contractor's Competent Person in implementing and ensuring that safety and health requirements are complied with during the performance of all required work. The Designated IH must be a person who is board certified in the practice of industrial hygiene as determined and documented by the American Board of Industrial Hygiene (ABIH), has EPA MAP "Contractor/Supervisor" training accreditation, has EPA/State certification/license, and has a minimum of 2 years of comprehensive experience in planning and overseeing asbestos abatement activities. Submit the "Contractor/Supervisor" course completion certificate and the most recent certificate for required refresher training and EPA/State certification/license with the employee "Certificate of Worker Acknowledgment". The Designated IH must be completely independent from the Contractor according to federal, state, or local regulations; that is, must not be a Contractor's employee or be an employee or principal of a firm in a business relationship with the Contractor negating such independent status. A copy of the Designated IH's current valid ABIH certification shall be included. The Designated IH must visit the site at least once per week for the duration of asbestos activities and must be available for emergencies. In addition, submit resumes of additional IH's and industrial hygiene technicians (IHT) who will be assisting the Designated IH in performing onsite tasks. IHs and IHTs supporting the Designated IH must have a minimum of 2 years of practical onsite asbestos abatement experience. Indicate the formal reporting relationship between the Designated IH and the support IHs and IHTs, the Designated Competent Person, and the Contractor.
e. Asbestos Abatement Workers: Meet the requirements contained in 29 CFR 1926.1101, 40 CFR 61, Subpart M, and other applicable federal, state and local requirements. Worker training documentation must be provided as required on the "Certificate of Workers Acknowledgment".
Training documentation is required for each employee who will perform OSHA Class II, asbestos abatement operations. Such documentation must be submitted on a Contractor generated form titled "Certificate of Workers Acknowledgment", to be completed for each employee in the same format and containing the same information as the example certificate at the end of this section. Training course completion certificates (initial and most recent update refresher) required by the information checked on the form must be attached.
f. Physician: Resume of the physician who will or has performed the medical examinations and evaluations of the persons who will conduct the asbestos abatement work tasks. The physician must be currently licensed by the state where the workers will be or have been examined, have expertise in pneumoconiosis and must be responsible for the determination of medical surveillance protocols and for review of examination/test results performed in compliance with 29 CFR 1926.1101.
The physician must be familiar with the site's hazards and the scope of this project.
g. Independent Testing Laboratory: identify the independent testing laboratory selected to perform the sample analyses and report the results. The testing laboratory must be completely independent from the Contractor as recognized by federal, state or local regulations.
Written verification of the following criteria, signed by the testing laboratory principal and the Contractor, must be submitted:
(1) Phase contrast microscopy (PCM): The laboratory is fully equipped and proficient in conducting PCM of airborne samples using the methods specified by 29 CFR 1926.1101, OSHA method ID-160, the most current version of NIOSH NMAM Method 7400 as shown in Table 3 at the end of this Section. The laboratory must be currently judged proficient (classified as acceptable) in counting airborne asbestos samples by PCM by successful participation in each of the last 4 rounds in the American Industrial Hygiene Association (AIHA) Proficiency Analytical Testing (PAT) Program or by participating in the AIHA PAT Program, and being judged proficient in counting samples.
(2) Polarized light microscopy (PLM): The laboratory is fully equipped and proficient in conducting PLM analyses of suspect ACM bulk samples in accordance with 40 CFR 763, Subpart E, Appendix E;
the laboratory is currently accredited by NIST under the NVLAP for bulk asbestos analysis and will use analysts with demonstrated proficiency to conduct PLM analyses.
h. Disposal Facility, Transporter: Written evidence that the landfill to be used is approved for asbestos disposal by the USEPA and state and local regulatory agencies. Copies of signed agreements between the Contractor (including subcontractors and transporters) and the asbestos waste disposal facility to accept and dispose of all asbestos containing waste must be provided. The Contractor and transporters must meet the DOT requirements of 49 CFR 171, 49 CFR 172, and 49 CFR 173 as well as registration requirements of 49 CFR 107 and other applicable state or local requirements. The disposal facility must meet the requirements of 40 CFR 61, Sections .154 or .155, as required in 40 CFR 61 150(b), and other applicable state or local requirements.
1.6.3 Federal, State or Local Citations on Previous Projects
The Contractor and all subcontractors must submit a statement, signed by an officer of the company, containing a record of any citations issued by
Federal, State or local regulatory agencies relating to asbestos activities (including projects, dates, and resolutions); a list of penalties incurred through non-compliance with asbestos project specifications, including liquidated damages, overruns in scheduled time limitations and resolutions;
and situations in which an asbestos-related contract has been terminated (including projects, dates, and reasons for terminations). If there are none, a negative declaration signed by an officer of the company must be provided.
1.6.4 Preconstruction Conference
The Contractor and the Contractor's Designated Competent Person, Project Supervisor, and Designated IH must meet with the Contracting Officer (CO) prior to beginning work at a safety preconstruction conference to discuss the details of the Contractor's submitted APP to include the AHAP and AHAs appendices. Deficiencies in the APP will be discussed. Onsite work must not begin until the APP has been accepted.
1.7 SAFETY
Prepare a written comprehensive site-specific Accident Prevention Plan (APP) at least 30 days prior to the preconstruction conference. The APP must be in accordance with the format and requirements in Appendix A of EM 385-1-1. The APP must incorporate an Asbestos Hazard Abatement Plan (AHAP), and Activity Hazard Analyses (AHAs) as separate appendices into one site-specific document. The APP must take into consideration all the individual asbestos abatement work tasks identified in Table 1. See Section 01 35 26 GOVERNMENT SAFETY REQUIREMENTS for additional requirements.
1.7.1 Asbestos Hazard Abatement Plan Appendix
The AHAP must include, but not be limited to, the following:
a. The personal protective equipment to be used;
b. The location and description of regulated areas including clean and dirty areas,access tunnels, and decontamination unit ;
c. Initial exposure assessment in accordance with 29 CFR 1926.1101;
d. Level of supervision;
e. Method of notification of other employers at the worksite;
f. Abatement method to include containment and control procedures;
g. Interface of trades;
h. Sequencing of asbestos related work;
i. Storage and disposal procedures and plan;
j. Type of wetting agent and asbestos encapsulant;
l. Air monitoring methods (personal, environmental );
m. Bulk sampling and analytical methods (if required);
n. A detailed description of the method to be employed in order to control the spread of ACM wastes and airborne fiber;
o. Fire and medical emergency response procedures;
p. The security procedures to be used for all regulated areas.
1.7.2 Activity Hazard Analyses Appendix
AHAs for each major phase of work, must be submitted and updated during the project. The AHAs format must be in accordance with Figure 1-1 of EM 385-1-1. The analysis must define the activities to be performed for a major phase of work, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. Work must not proceed on that phase until the AHA has been accepted and a preparatory meeting has been conducted by the Contractor to discuss its contents with everyone engaged in the activities, including the onsite Government representatives. The AHAs must be continuously reviewed and, when appropriate, modified to address changing site conditions or operations.
1.8 SECURITY
Fenced and locked security area must be provided for each regulated area.
A log book must be kept documenting entry into and out of the regulated area. Entry into regulated areas must only be by personnel authorized by the Contractor and the CO. Personnel authorized to enter regulated areas must be trained, medically evaluated, and wear the required personal protective equipment.
1.8.1 Licenses, Permits and Notifications
Obtain necessary licenses, permits and notifications in conjunction with the project's asbestos abatement, transportation and disposal actions and timely notification furnished of such actions as required by federal, state, regional, and local authorities. Notify the Regional Office of the USEPA state's environmental protection agency responsible for asbestos air emissions local air pollution control district/agency state OSHA program and the CO in writing, at least 10 days prior to the commencement of work, in accordance with 40 CFR 61, Subpart M, and state and local requirements to include the mandatory "Notification of Demolition and Renovation Record" form and other required notification documents. Notify by Certified Mail, Return Receipt Requested. Furnish copies of the receipts to the CO, in writing, prior to the commencement of work. The associated fees/costs for licenses, permits, and notifications are is contract.
1.8.2 Regulated Areas
All Class II, asbestos work must be conducted within regulated areas. The regulated area must be demarcated to minimize the number of persons within the area and to protect persons outside the area from exposure to airborne asbestos.