About this file

PHASE 1 RFP for W911KB-09-R-0026 FTW350 Warrior In Transition Complex Fort Wainwright Alaska.

View the file

Other files for this federal contract opportunity

Other files attached to Warrior in Transition Complex (FTW350), Fort Wainwright, Alaska, newest first.
File Type Posted
W911KB-09-R-0026_AM2.pdf PDF
W911KB-09-R-0026_AM1.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INV. NO. W911KB-09-R-0026

BID RFP

REQUEST FOR PROPOSAL

FTW350

WARRIOR IN TRANSITION COMPLEX

FT. WAINWRIGHT, ALASKA

SOLICITATION, OFFER, AND AWARD

SUPPLIES OR SERVICES AND PRICE/COSTS

CONSTRUCTION SPECIFICATIONS/STATEMENT OF WORK

INSPECTION AND ACCEPTANCE

SPECIAL CONTRACT REQUIREMENTS

CONTRACT CLAUSES

LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS

INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

August 2009

U.S. ARMY ENGINEER DISTRICT, ALASKA

CORPS OF ENGINEERS

P.O. BOX 6898

ELMENDORF AFB, ALASKA 99506-0898

INCREASE PROFIT SUBMIT VE CHANGES

DRAFT

TABLE OF CONTENTS

NOTE: The following Table of Contents includes all sections of the solicitation, not just those issued for Phase 1.

REQUEST FOR PROPOSAL

TABLE OF CONTENTS

SF1442

PROPOSAL SCHEDULE

00 21 00 INSTRUCTIONS, CONDITIONS AND NOTICES

TO OFFERORS

00 22 10 PHASE 1 OF 2 PHASE DESIGN-BUILD SELECTION PROCEDURES

00 22 20 PHASE 2 DESIGN-BUILD SELECTION PROCEDURE AND BASIS OF

AWARD

00 45 00 REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF

BIDDERS/OFFERORS

00 72 00 CONTRACT CLAUSES

00 73 00 SPECIAL CONTRACT REQUIREMENTS

00 73 46 WAGE DETERMINATION SCHEDULE

DIVISION 01 – GENERAL REQUIREMENTS

01 10 00 STATEMENT OF WORK

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 16 DESIGN AFTER AWARD

01 45 01.10 QUALITY CONTROL SYSTEMS (QCS)

01 45 04.00 10 CONTRACTOR QUALITY CONTROL

01 50 02 TEMPORARY CONSTRUCTION FACILITIES

01 57 20.00 10 ENVIRONMENTAL PROTECTION

01 62 35 RECYCLED/ RECOVERED MATERIALS

01 78 02.00 10 CLOSEOUT SUBMITTALS

APPENDIXES

APPENDIX A: GEOTECHNICAL FINDINGS REPORT

APPENDIX B: NOT USED

APPENDIX C: NOT USED

APPENDIX D: RESULTS OF FIRE FLOW TESTS

APPENDIX E: ENVIRONMENTAL INFORMATION

(CHEMICAL DATA REPORT)

APPENDIX F: CONCEPTUAL AESTHETIC CONSIDERATIONS

APPENDIX G: NOT USED

APPENDIX H: EXTERIOR SIGNAGE; ALSO REFERENCE UFC 3-120-01, AIR

FORCE SIGN STANDARD, FOR EXTERIOR SIGNAGE

APPENDIX I: ACCEPTABLE PLANTS LIST

APPENDIX J: DRAWINGS

APPENDIX K: FUEL COST INFORMATION

APPENDIX L: LEED PROJECT CREDIT GUIDANCE

APPENDIX M: LEED OWNER’S PROJECT REQUIREMENTS

APPENDIX N: NOT USED

APPENDIX O: NOT USED

APPENDIX P: NOT USED

APPENDIX Q: AREA COMPUTATION

APPENDIX AA: ADDITIONAL SPECIFICATIONS

01 19 30.01 29 SPECIAL ITEMS

01 22 00.00 10 MEASUREMENT AND PAYMENT

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 36 00.00 29 RADIOACTIVE MATERIALS PROCEDURES

01 57 34.00 29 STORM WATER POLLUTION PREVENTION MEASURES

02 41 00 DEMOLITION (To be provided after completion of Chemical Data Report)

02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL

(To be provided after completion of Chemical Data Report)

02 82 14.00 10 ASBESTOS ABATEMENT (To be provided after completion of Chemical Data Report)

02 83 13.00 20 LEAD IN CONSTRUCTION

(To be provided after completion of Chemical Data Report)

31 09 20.00 29 FIELD TESTING OF SOILS FOR POL CONTAMINATION

(To be provided after completion of Chemical Data Report)

APPENDIX BB: DIVISION 01 SPECIFICATIONS SUPPLEMENTAL DATA

01 33 00 (Submittal Register only)

01 33 16 DESIGN AFTER AWARD Supplemental Data

01 57 20.00 10 ENVIRONMENTAL PROTECTION Supplemental Data

APPENDIX CC: PROJECT SPECIFIC REQUIREMENTS

6.1 General

6.2 Approved Deviations

6.3 Site Planning and Design

6.4 Site Engineering

6.5 Architecture

6.6 Structural

6.7 Thermal Performance

6.8 Plumbing

6.9 Site Electrical Systems

6.10 Facility Electrical Systems

6.11 Heating, Ventilating, and Air Conditioning

6.12 Energy Conservation

6.13 Fire Protection

6.14 Sustainable Design

6.15 Environmental

6.16 Permits

6.17 Demolition

6.18 Additional Facilities

APPENDIX DD: FORT WAINWRIGHT BARRACKS ROOM SIGNAGE STANDARD

APPENDIX EE: FORT WAINWRIGHT DISTRICT THERMAL

APPENDIX FF: DRAWINGS

PROJECT TITLE/LOCATION: FTW350 Warrior in Transition Complex, Fort Wainw right, Alaska NAICS: 236220 SIZE STANDARD: $33.5 Million

FULL AND OPEN COMPETITION - 2 PHASE BEST VALUE SOURCE SELECTION

DESCRIPTION OF WORK: Design/Construct a standard design Warrior in Transition (WIT) Complex at Fort Wainw right, Alaska. The WIT primary facility includes a Warriors in Transition Barracks, a Warriors in Transition Administrative and Operations Facility and a Soldier and Family Assistance Center (SFAC), w ith building information systems, Intrusion Detection Systems (IDS) installation, and Energy Management Control System (EMCS) and Fire/ Smoke Detection/ Annunciation/ Suppression Systems and connections to the installation’s central systems.

There w ill be a requirement to provide ATFP Measures. Supporting facilities include site w ork, lighting, information systems, parking, sidew alks, roads, curbs and gutters, storm drainage, site accessories, landscaping, and other site improvements. Demolition for this project includes demolition of existing buildings 3411 and 3413, supporting sidew alks, asphalt parking, service utilidors as needed, etc.

Subject to funds available & Congressional approval.

Reference Block 13D: Offer acceptance is from date of Phase 2 submission.

MICHELLE R MANDEL 907-753-2502

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

03-Aug-2009

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________540 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________3 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________03 Sep 2009 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

U.S. ARMY ENGINEER DISTRICT, AK

CEPOA-CT (W911KB)

PO BOX 6898

ELMENDORF AFB AK 99506-0898

W911KB

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

12:00 PM (hour) Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W911KB-09-R-0026 218

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

SECTION PS WARRIOR IN TRANSITION W911KB-09-R-0026

PROPOSAL SCHEDULE

WARRIOR IN TRANSITION COMPLEX

FT. WAINWRIGHT, ALASKA

Item No. Description Estimated Unit Unit Amount

Quantity Price

BASE ITEMS

0001. Design Warrior-In-Transition Complex, complete.

1 Lump sum $________ $________

0002. Demolish Buildings 3411 and 3413, complete 1 Lump sum $________ $________

0003. Construct Warrior-In-Transition Complex 32 person Barracks within the building 5-foot lines, complete. 1 Lump sum $________ $________

0004. Construct Warrior-In-Transition Complex Small One-Company Headquarters within the building 5-foot lines, complete. 1 Lump sum $________ $________

0005. Construct Warrior-In-Transition Complex Soldier and Family Assistance Center (SFAC) within the building 5-foot lines, complete. 1 Lump sum $________ $________

0006. Construct site work for Warrior-In-Transition Complex beyond Building 5-foot lines, complete. 1 Lump sum $________ $________

Total of Base Items 0001 thru 0006 $________

PS - 1

SECTION PS WARRIOR IN TRANSITION W911KB-09-R-0026

OPTIONAL ITEMS

0007. OPTION 1: Remove, Sample, and Stockpile POL Contaminated Soil. * 100 Cubic Yard $________ $________

Total of Optional Items 0001 $________

Total of Base and Optional Items 0001 thru 0007 $________

Proposed Contract Duration (Calendar Days) __________________________________

*Includes construction of containment cells, complete. Shall be the cost of work identified in Specifications Sections 02 61 13 "Excavation and Handling of Contaminated Material"; 01 57 20.00 10 "Environmental Protection"; and Appendix A "Handling/Management of Contaminated Soil" (found in RFP Appendix BB - 01 57 20.00 10 Supplemental Data); and is in addition to the requirements of the normal project excavation and the field screening identified in Specification Section 31 09 20.00 29 "Field Screen Testing of Soils for POL Contamination" (Subject to FAR Clause 52.211-18 Variation in Quantity)

EVALUATION OF OFFERS

1. AWARD: Award will be made in accordance with SECTION 00 22 10, Phase 1 of 2-Phase Design-Build Selection Procedures and SECTION 00 22 20, Phase 2 Design-Build Selection Procedures and Basis for Award.

2. INCOMPLETE OFFERS: Failure to submit an offer on all items in the schedule constitutes an incomplete offer. Incomplete offers may be rejected. Lump sum or unit prices must be shown for each item within the schedule.

3. EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.

4. SPECIAL CONDITION: If a modification to a offer based on unit prices is submitted which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the proposal schedule must be stated. If it is not stated, the offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the proposal schedule.

-- END OF PROPOSAL SCHEDULE --

PS - 2

SECTION 00 21 00 W911KB-09-R-0026

Section 00 21 00 Page 1

SECTION 00 21 00

SECTION 00 21 00

REV 2.4 - 30 NOV 2008

INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

1.0 GENERAL INFORMATION

1.1 GENERAL DESCRIPTION OF WORK

1.2 CONTRACT COST CEILING LIMITATION FOR DESIGN AND CONTRUCTION COSTS

1.3 GOVERNMENT SECURITY REQUIREMENTS

1.4 COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS

1.5 OFFEROR'S QUESTIONS AND COMMENTS

1.6 SMALL BUSINESS SIZE STANDARD/NAICS CODE

1.7 PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

1.8 PRE-PROPOSAL CONFERENCE

1.9 ACCURACY IN PROPOSALS

1.10 PROPOSAL SUBMITTALS

1.11 PROPOSAL FORMAT

1.12 JOINT VENTURE PROPOSAL REQUIREMENTS

1.13 SUBCONTRACTING PLAN/ SUBCONTRACTING GOALS REGARDING THE UTILIZATION OF

SMALL BUSINESS CONCERNS

1.14 SOLICITATION PROVISIONS

Section 00 21 00 Page 2

1.0 GENERAL INFORMATION

1.1. GENERAL DESCRIPTION OF WORK

The scope of project includes all work required to [design and] construct a Warrior in Transition Complex located at Fort Wainwright, AK. The work shall be in accordance with Request for Proposal documents.

General Description of Work: Design/Construct a standard design Warrior in Transition (WIT) Complex at Fort Wainwright, Alaska. The WIT primary facility includes a Warriors in Transition Barracks, a Warriors in Transition Administrative and Operations Facility and a Soldier and Family Assistance Center (SFAC), with building information systems, Intrusion Detection Systems (IDS) installation, and Energy Management Control System (EMCS) and Fire/ Smoke Detection/ Annunciation/ Suppression Systems and connections to the installation’s central systems. There will be a requirement to provide Antiterrorism/ Force Protection Measures. Sustainable Design and Development (SDD) and Energy Policy Act of 2005 features will be included. Supporting facilities include site work, lighting, information systems, parking, sidewalks, roads, curbs and gutters, storm drainage, site accessories, landscaping, and other site improvements. Demolition for this project includes demolition of existing buildings 3411 and 3413, supporting sidewalks, asphalt parking, service utilidors as needed, miscellaneous site features, including roads, utilities, sidewalks, paving, curbs, and similar items not in the contract, which if damaged by the Contractor shall be replaced in kind at no cost to the Government. The project is already registered with the US Green Building Council under LEED-NC 2.2. In accordance with Section 01 33 16, Design After Award, paragraph 3.5.4, LEED Documentation, the contractor will be responsible for assigning a LEED Accredited Professional, responsible to track LEED planning, performance and documentation for each LEED credit through construction closeout.

1.2. CONTRACT COST CEILING LIMITATION FOR DESIGN AND CONSTRUCTION COSTS

The design and construction costs will be subject to the funds available for this project. The total contract award shall not exceed $24,000,000 for this contract. Offerors are notified that they are under no obligation to approach this ceiling and that it is unlikely additional funds will be made available for award should the cost limitation be exceeded.

1.3. GOVERNMENT SECURITY REQUIREMENTS

The Offeror(s) must ensure that ALL mail sent to the Alaska District District, U.S. Army Corps of Engineers, either pre-contract or post-contract award, has a return mailing address on the outside of the envelope, package, box, etc.

ANY MAIL addressed to the U.S. Army Corps of Engineers, including but not limited to bids, modifications to bids, proposals, revised proposals, bonds, correspondence, etc., will be REJECTED by the US Army Corps of Engineers mail room facility located at PO Box 6898, Elmendorf AFB, AK, 99506-6898 if it does not contain a return mailing address. There will be no exceptions.

1.4. COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS

Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the Federal Business Opportunities website at: www.fbo.gov http://www.fbo.gov/�

Section 00 21 00 Page 3

Query Solicitation No. W911KB-09-R-0026

It shall be the contractor’s responsibility to check the websites for any amendments. The offeror shall submit in the proposal all requested information specified in this solicitation. There will be no public opening of the proposals received as a result of this solicitation.

A list of interested vendors (potential offerors and subcontractors) is available on the federal business opportunities web site (registration required) is available at: http://www.fbo.gov/ via Quick Search (Solicitation No. W911KB- 09-R-0026).

1.5. OFFEROR'S QUESTIONS AND COMMENTS

Questions and/or comments relative to these documents should be submitted via e-mail or mailed to:

Contract Specialist – Primary POC

U.S. Army Corps of Engineers, Alaska District

ATTN: Donna West

CEPOA-CT, PO BOX 6898 ELMENDORF AFB, AK 99506-6898

Phone: (907) 753-2502 Fax: (907) 753-2544

Email: Donna.L.Westl@usace.army.mil

Note: All questions and/or comments should reach the above referenced Contracting Office no later than seven (7) calendar days prior to proposal due date, in order that they may be given consideration or actions taken prior to receipt of offers.

1.5.1 Bidder Inquiry

1.5.1.1 Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet.

1.5.1.1.1 To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

1.5.1.1.2 From this page you may view all bidder inquiries or add inquiry. A complete listing of all inquiries and answers will be issued by amendment after the Phase 2 inquiry period closes.

1.5.1.1.3 Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

1.5.1.1.4 The Solicitation Number is : W911KB-09-R-0026

1.5.1.1.5 The Bidder Inquiry Key is: Y2USMM-YGE428

Section 00 21 00 Page 4

1.5.1.2 The Bidder Inquiry System will be unavailable for new inquires 5 days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

1.5.1.3 Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

1.5.1.4 The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

1.5.1.5 Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

1.6. SMALL BUSINESS SIZE STANDARD/NAICS CODE

See SF1442 for the small business size standard/NAICS Code.

1.7. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

This Request for Proposal (RFP) does not commit the Government to pay, as a direct charge, any costs incurred in the preparation and submission of a proposal. However, a stipend may be authorized for unsuccessful Phase 2 offerors in accordance with Section 00 22 20.

1.8. PRE-PROPOSAL CONFERENCE

A pre-proposal conference/site visit is not currently scheduled for this project. Offerors interested in a pre-proposal conference or site visit should submit a request with in 10 calendar days after the issuance of this solicitation to:

U.S. Army Corps of Engineers, Alaska District ATTN: Donna West

CEPOA-CT, PO BOX 6898 ELMENDORF AFB, AK 99506-6898

Phone: (907) 753-2502 Fax: (907) 753-2544 Email: Donna.L.Westl@usace.army.mil

1.9. ACCURACY IN PROPOSALS

Proposals must set forth full, accurate, and complete information as required by this RFP, (including attachments).

The penalty for making false statements is prescribed in 18 U.S.C. 1001.

1.10. PROPOSAL SUBMITTALS

Due to heightened security at Government installations, those offerors who have their proposals hand-delivered shall contact Michelle Mandel, Contract Specialist, at (907) 753-2502 or Donna West, Contracting Officer, at (907) 753-2761 or the Contracting Office Main Desk, at (907) 753-2540, prior to delivering to the address shown below.

Proposals will be received until the date and time specified on the SF1442 or subsequent amendment at:

As stated on Standard Form SF 1442: Proposals will be received until until the date and time stated on the SF1442

Section 00 21 00 Page 5 or subsequent amendment at:

Mailing Address:

U.S. Army Corps of Engineers, Alaska District ATTN: CEPOA-CT (Donna West) PO Box 6898 Elmendorf AFB, Alaska 99506-0898

Physical Address:

U.S. Army Corps of Engineers, Alaska District ATTN: CEPOA-CT (Donna West) 2204 3rd Street Elmendorf AFB, Alaska 99506

The Packaging that contains the Proposals shall be marked:

”Proposals for Solicitation Number: W911KB-09-R-0026, DO NOT OPEN”

Recent terrorist threats have resulted in more time-consuming sign-in and escort procedures and may impact the timely delivery of offers. See FAR 52.215-1 for rules concerning late proposals.

Visitors to Army Posts and Air Force Bases

All vehicle occupants are required to wear seatbelts. Violators will lose their Base/Post driving privileges for this offense. Cell phone usage by vehicle operators while driving on base/post is prohibited. Violators will lose their Base/Post driving privileges for this offense.

Visitors to Elmendorf Air Force Base

If a firm does not have a current pass to obtain entry to Elmendorf AFB, the firm may obtain a pass using the following procedures:

The visitor will have to go to the Boniface Gate for the vehicle pass* on day one. Someone from USACE (or a CAC Card Holder) will have to meet visitor(s) at the gate for the initial sponsorship and sign in before the pass is approved; this applies to anyone not on the Entry/Extended Authorization List (EAL = 90 days or more)

After initial access the visitor will be able to enter without someone physically being at the gate; this is good for the duration of the pass that is issued. Ensure that the visitor is prepared to provide the required documentation for the vehicle, proper id and sponsor with approved ID in order to sign in.

*Short Term Pass = less than 90 day pass *Long Term Pass = more than 90 day/EAL issued Installation Access ID Card (Joint Base Elmendorf Richardson Card for non-CAC card holders)

1.11. PROPOSAL FORMAT

a Written materials: 8 ½” x 11” format, using 10 point or larger font size, in bound volumes, using 3-ring binders (except that Pro Forma material and price proposal shall be submitted in a closed manila envelope). Each bound

Section 00 21 00 Page 6 volume will contain a Title Sheet on the cover for ready identification of the proposal and a full table of contents, separated by Tabs, as prescribed herein

(i) The prime, consortium, or joint venture’s name, address, a signature of the official that can bind the firm and a telephone number shall appear in the lower left corner of the title page of any document/volume to be evaluated.

(ii) Volume number, section and date submitted shall appear in the bottom right corner of each page (along with the revision number for the amended page, if necessary).

(a) Drawing sheets: Use 11” x 17” for full size drawings.

(b) Electronic Format: Provide two CDs in read-only format, preferably using .pdf files. All price breakdown information to aide in the price evaluation shall be submitted in Excel format.

(c) Number of copies: Submit one original and Three (3) copies of drawings and printed matter (Bound Volumes), as well as One (1) CDs. For Pro Forma information required in Phase 2: Submit the original and one copy and one separate CD.

1.12. JOINT VENTURE PROPOSAL REQUIREMENTS

When proposing as a joint venture, all members of the joint venture shall sign the SF 1442 unless a written agreement by the joint venture is furnished with the proposal designating one firm with the authority to bind the other member(s) of the joint venture. In addition, a copy of the joint venture agreement shall be submitted with the Phase 1 proposal. Failure to comply with the foregoing requirements may eliminate the proposal from further consideration. If this is an 8(a) or HubZone joint venture, the offeror shall ensure that it complies with the applicable requirements of 13 CFR Part 124 and 13 CFR Part 126, respectively.

When proposing as a Limited Liability Company (LLC), a member authorized to bind the LLC shall sign the SF1442. A copy of the LLC Certificate of Organization, Articles of Organization and the Operating Agreement shall be submitted with the Phase 1 proposal.

1.13. SUBCONTRACTING PLAN/ SUBCONTRACTING GOALS REGARDING THE UTILIZATION OF

SMALL BUSINESS CONCERNS

(a) Application. This clause applies to all offerors submitting proposals.

(b) Federal Acquisition Regulations (FAR). Attention is directed to the following FAR and DFARS provisions contained in this solicitation:

52.219-8, Utilization of Small Business Concerns (Alternate I)

52.219-9, Small Business Sub Contracting Plan (Alternate I) (applies only to Large Business)

52.219-16, Liquidated Damages – Small Business Subcontracting Plan (applies only to Large Business)

252.226-7001, Utilization of Indian Organizations, Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns

Section 00 21 00 Page 7

(c) Goals. The U.S. Army Corps of Engineers considers the following goals reasonable and achievable for the performance of the resultant contract:

(i) 70.0 % of subcontracted amount contract amount with small business concerns.

(ii) 6.2 % of subcontracted amount contract amount with those small business concerns owned and controlled by socially and economically disadvantaged individuals.

(iii) 7.0 % of subcontracted amount contract amount with those small business concerns owned and controlled by women.

(iv) 0.9 % of subcontracted amount contract amount with those small business concerns owned and controlled by Service-Disabled Veterans.

(v) 9.8 % of subcontracted amount contract amount with those small business concerns owned and controlled by HUBZones.

(vi) 3.0 % of subcontracted amount contract amount with those small business concerns owned and controlled by Veterans, colleges and universites.

1.14. SOLICITATION PROVISIONS

The following Clauses are incorporated by full text.

52.211-14 Notice of Priority Rating for National Defense, Emergency Preparedness, and Energy Program Use

APR 2008

52.215-1 Instructions to Offerors – Competitive Acquisition JAN 2004 52.216-1 Type of Contract APR 1984 52.217-5 Evaluation of Options JUL 1990 52.222-5 Davis – Bacon Act – Secondary Site of the Work JUL 2005 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment

Opportunity for Construction

FEB 1999

52.225-12 Notice of Buy American Act Requirement – Construction Materials Under Trade Agreements

FEB 2009

52.233-2 Service of Protest SEP 2006 52.236-27 Site Visit (Construction) FEB 1995 – Alternate I FEB 1995 52.236-28 Preparation of Proposals – Construction OCT 1997 52.252-1 Solicitation Provisions Incorporated by Reference FEB 1998 252.209-7001 Disclosure Of Ownership Or Control By The Government Of A Terrorist

Country

JAN 2009

252.236-7008 Contract Prices – Bidding Schedules DEC 1991

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be N/A DX rated order; C2 DO rated order

Section 00 21 00 Page 8 certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.

(End of provision)

52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2004)

(a) Definitions. As used in this provision--

“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.

“In writing or written” means any worded or numbered expression which can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.

“Proposal modification” is a change made to a proposal before the solicitation's closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.

“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.

“Time”, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.

(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).

(c) Submission, modification, revision, and withdrawal of proposals. (1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror.

Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.

(2) The first page of the proposal must show--

(i) The solicitation number;

(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);

(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;

(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror's behalf with the Government in connection with this solicitation; and

(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office.

Section 00 21 00 Page 9

(3) Submission, modification, or revision, of proposals.

(i) Offerors are responsible for submitting proposals, and any modifications, or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.

(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and--

(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or

(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or

(3) It is the only proposal received.

(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.

(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.

(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.

(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.

(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.

(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.

(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.

(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.

(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.

(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).

Section 00 21 00 Page 10

(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall--

(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed--in whole or in part--for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of--or in connection with-- the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and

(2) Mark each sheet of data it wishes to restrict with the following legend: Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.

(f) Contract award. (1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.

(2) The Government may reject any or all proposals if such action is in the Government's interest.

(3) The Government may waive informalities and minor irregularities in proposals received.

(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.

(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government's best interest to do so.

(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.

(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.

(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.

(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.

(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:

(i) The agency's evaluation of the significant weak or deficient factors in the debriefed offeror's offer.

Section 00 21 00 Page 11

(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.

(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.

(iv) A summary of the rationale for award.

(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.

(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed-Price contract resulting from this solicitation.

52.217-5 EVALUATION OF OPTIONS (JUL 1990)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

52.222-5 DAVIS-BACON ACT--SECONDARY SITE OF THE WORK (JUL 2005)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Davis-Bacon Act, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

Section 00 21 00 Page 12

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

8.7% Anchorage 6.9% Alaska

15.1% (Locations outside city of Anchorage)

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Fairbanks, Alaska.

52.225-12 NOTICE OF BUY AMERICAN ACT REQUIREMENT-- CONSTRUCTION MATERIALS

UNDER TRADE AGREEMENTS (FEB 2009)

Section 00 21 00 Page 13

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American Act-- Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).

(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American Act should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American Act before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American Act, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers. (1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of the foreign construction material for which an exception was requested-- (i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

Donna West, Contracting Officer U.S. Army Engineer District, Alaska

CEPOA-CT

2204 3rd Street, Room 30 Elmendorf AFB, Alaska 99506

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

Section 00 21 00 Page 14

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-- To Be Determined

(c) Participants will meet at—

Alaska District Northern Area Office 3025 Montgomery Road Fort Wainwright, Alaska 99703

52.236-28 PREPARATION OF PROPOSALS--CONSTRUCTION (OCT 1997)

(a) Proposals must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a proposal must initial each erasure or change appearing on any proposal form.

(b) The proposal form may require offerors to submit proposed prices for one or more items on various bases, including--

(1) Lump sum price;

(2) Alternate prices;

(3) Units of construction; or

(4) Any combination of paragraphs (b)(1) through (b)(3) of this provision.

(c) If the solicitation requires submission of a proposal on all items, failure to do so may result in the proposal being rejected without further consideration.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .