This document provides details for a federal construction contract opportunity with the Department of the Army Materiel Command Mission and Installation Contracting Command at Fort Hood, Texas. The solicitation is for the construction of an administrative building to replace temporary trailers at Shorthorn Airfield on North Fort Hood. The project scope involves all labor, materials, equipment and services to construct a permanent structure. The acquisition is set aside solely for small businesses with a size standard of $36.5 million or less. The estimated price range for the construction is between $1,000,000 to $5,000,000. The wage determination is General Decision Number TX20200230 and bonds are required at 100% of the contract value. The bid documents include exhibits with specifications, drawings and provisions. The response date has been amended and questions from industry were answered regarding equipment details.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0011491999 1A101919P
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment to to answ er additional Request for Information (RFI) questions and add Tech Exhibit D - Revised Mechanical Schedule. See summary of changes for details.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Aug-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9115120B0012
X 9B. DATED (SEE ITEM 11)
05-Aug-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
27-Aug-2020
CODE
MICC - FORT HOOD
36000 DARNALL LOOP, ROOM 1300B
FORT HOOD TX 76544-5025
W91151 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9115120B0012
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
TABLE OF CONTENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Exhibit A Tech Exhibit A -
Specifications
3313 24-APR-2020
Exhibit B Tech Exhibit B - Revised Drawings
113 01-MAY-2020
Exhibit C Tech Exhibit C - DPW Division 1 Specifications
113 27-APR-2019
Attachment 1 Attachment 1 Appendix A
- Specifications
120 04-AUG-2016
to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Exhibit A Tech Exhibit A -
Specifications
3313 24-APR-2020
Exhibit B Tech Exhibit B - Revised Drawings
113 01-MAY-2020
Exhibit C Tech Exhibit C - DPW Division 1 Specifications
113 27-APR-2019
Exhibit D Tech Exhibit D - Revised Mechanical Schedule
1 27-AUG-2020
Attachment 1 Attachment 1 Appendix A
- Specifications
120 04-AUG-2016
The following have been added by full text:
REQUEST FOR INFORMATION 2
PRE-Bid RFI’s ROUND 2 Fort Hood- Shorthorn Airfield Administration Bldg W91151-20-B-0012
1. These questions are from a supplier.
Can you please RFI the following items?
1a. AHU-1 shows 140MBH capacity, which is higher than available with model TWE120. This would require a 12.5 ton system if 140MBH total capacity is the true requirement?
W9115120B0012
140 MBH is the requirement – reference revised drawing
1b. AHU-2 shows 208/3 heat, but 208/1 unit electrical. Please clarify which voltage is required?
208/3 is correct – see revised drawing
1c. COND-1 shows 20 SEER. SEER only applies to 5 ton size & below. This should be rated in EER, and be closer to 11.2?
11.2 EER is correct – see revised drawing
1d. COND-2 shows 20 SEER, but has a 14 SEER model listed. Please clarify if 20 SEER or 14 SEER is required?
14 SEER is correct – see revised drawing
2. Sheet ET601 details the need for one (1) 12-strand single mode fiber and a 25-pair copper cable. Is this something we (low voltage sub) are expected to install? If so, where does the cable originate? Obviously it terminates in the new Telecom room 111, but sheet ES101 only shows the conduit pathway as it connects the two buildings or the manhole, but doesn’t detail where the other end of the cables should go.
Cable will originate from Manhole
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been modified:
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
Portions of this solicitation are altered as follows:
Amendment P0001- Responses to Questions from Industry (RFIs), change to bid upload date, change to bid opening date and publication of Tech Exhibit B – Revised Drawings.
Amendment P0002 – Responses to additional RFI questions and addition of Tech Exhibit D – Revised Mechanical Schedule.
(End of Provision)
(End of Summary of Changes)