About this file

This Performance Requirements Summary outlines the key performance objectives, standards, and thresholds for an overhead door preventative maintenance services contract at Fort Hood, Texas. The contractor must perform all required preventative maintenance, service calls, and replacement item work according to approved schedules and specified time requirements. Performance will be incentivized or penalized based on achieving thresholds of at least 96% for preventative maintenance and service calls, and 92% for replacement items. Deductions from payment will be calculated by multiplying the percentage of defective samples by the task value percentage and total contract cost. Government surveillance will verify contractor performance of all contract requirements.

View the file

Other files for this federal contract opportunity

Other files attached to Amendment- 00001 Overhead Door-Service, newest first.
File Type Posted
W91151-19-R-0016_Amend-0001__19-Feb-2020.pdf PDF
TE A - Revised Overhead Doors Pricing Schedule Blank_19-Feb-2020.xlsx XLSX spreadsheet
TE P - Contract for Sale of Utilities.doc DOC document
TE A - Overhead Doors Pricing Schedule.pdf PDF
TE C - Rolling Steel Manual Doors.xlsx XLSX spreadsheet
TE H - Sectional Manual Doors.xlsx XLSX spreadsheet
TE- 1A Fort Hood Main Cantonment Map.pdf PDF
TE R - Overhead Door Surveillance Checklist.doc DOC document
TE G - Sectional Chain Gear Driven Doors.xlsx XLSX spreadsheet
TE S - Comprehensive Overhead Door List.xls XLS spreadsheet
TE Q - Contractor Yard Site Map.pdf PDF
TE N - Hazardous Material Request.xls XLS spreadsheet
TE -1B West Fort Hood Cantonment Map.pdf PDF
TE J - Sectional Gear Driven Doors.xlsx XLSX spreadsheet
TE- 2 Special ServicesEvents..docx DOCX document
Solicitation W91151-19-R-0016 Overhead Doors.pdf PDF
TE T -Historical Data.xlsx XLSX spreadsheet
TE B - Rolling Steel Chain Driven Doors.xlsx XLSX spreadsheet
TE L - Hanger Gear Driven Doors.xlsx XLSX spreadsheet
TE- 1C North Fort Hood Cantonment Map.pdf PDF
TE K - Hanger Chain Gear Driven Doors.xlsx XLSX spreadsheet
TE F - Hanger Manual Doors.xlsx XLSX spreadsheet
TE U -Equipment and Supplies .docx DOCX document
TE M - Hangar Sectional Gear Driven Doors.xlsx XLSX spreadsheet
TE D-1 - Rolling Steel Chain Gear Driven Doors.xlsx XLSX spreadsheet
TE E - Sectional Chain Driven Doors.xlsx XLSX spreadsheet
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Exhibit T

Performance Requirements Summary

Performance Requirements Summary (PRS) provides the following information.

· Performance Objective: Defines what specific results or outcomes that will satisfy the overall requirement.

· Performance Standard: What level of performance is required to meet the Performance Objective

· Performance Threshold: The amount of deviation from 100% compliance that is acceptable

· Incentive / Disincentive: Clearly explains that good and poor performance will be reflected in some way, either monetarily or via Performance Evaluations.

PERFORMANCE OBJECTIVE

(PWS Paragraph)

PERFORMANCE STANDARD
PERFORMANCE THRESHOLD
TASK VALUE %
INCENTIVE / DISINCENTIVE
5.2 Preventive Maintenance
All required service is performed IAW the approved schedule.
4%
40%
Payment may be reduced if Performance Thresholds are exceeded (See explanation below)
5.3 Service Calls
All required service is performed within the specified time requirements.
4%
20%
CPAR ratings reflecting good or poor performance could affect decisions to exercise options or to make future contract awards
5.4 Replacement Items
All required service is performed as needed. This work will be identified from PM and Service Call work.
4%
40%

If the Contracting Officer determines that a reduction in payment is necessary, due to unacceptable or non-performance of work, then the deduction will be calculated in the following manner.

Formula for calculating deduction from contract payment based on PRS table (for each required service:

a. (Quantity of Samples that are Defective)/(Total Quantity of Samples) x 100% = X %

b. (X% - ALP) x (Task Value Percent) x (Total Contract Cost) = Total Deduction from payment

Note: Government surveillance of contractor performance is not limited to the Performance Objectives as outlined in this PRS. The government reserves the right to conduct compliance surveillance of any contractual requirement of this acquisition.

File details come from the government source that posted it. Updated .