Amendment_0001__3-14-2019.pdf

PDF 171 KB Posted

Attached to
Replace #2 Chiller at CEP, Bldg 37015 Federal contract opportunity
Solicitation number
W9115119B0005
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Hood

About this file

Amendment 01 to Solicitation 19-B-0005

View the file

Other files for this federal contract opportunity

Other files attached to Replace #2 Chiller at CEP, Bldg 37015, newest first.
File Type Posted
TECHNICAL_EXHIBIT_C_DRAWINGS-REVISED.pdf PDF
Tech_Exhibit_D-_AS-BUILTS._07_2005.PDF PDF
Solicitation_W91151-19-B-0005_Rpl__2Chiller_at_CEP_B_37015.pdf PDF
TECH_EXHIBIT_B_-_DRAWINGS_19-B-0005.pdf PDF
Attachment_1-Appendix_A_19-B-0005.pdf PDF
TECH_EXHIBIT_A_-_SPECIFICATION_19-B-0005.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

J

PAGE OF PAGES

1 6

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

14-Mar-2019

4. REQUISITION/PURCHASE REQ. NO.

0011285051

5. PROJECT NO.(If applicable)

AD005757P

6. ISSUED BY CODE W91151 7. ADMINISTERED BY (Ifother than item 6) CODE

MISSION AND INSTALLATION CONTRACTING

MISSION CONTRACTING OFFICE (MCO)

36000 DARNALL LOOP, ROOM 1300B

FORT HOOD TX 76544-5095

See Item 6

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.

W9115119B0005

X 9B. DATED (SEE ITEM 11)

26-Feb-2019

10A. MOD. OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILIT Y CODE

11. T HIS ITEM ONLY APPLIES TO AMENDMENT S OF SOLICIT ATIONS

X The above numbered solicitation is amended as set forth in Item14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT

TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNT ING AND APPROPRIAT ION DAT A (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES T HE CONT RACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONT RACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONT RACT /ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. T HIS SUPPLEMENT AL AGREEMENT IS ENT ERED INT O PURSUANT TO AUT HORIT Y OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT /MODIFICAT ION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The Purpose of this Amendment is to incorporate revised Technical Exhibit C - Drawings, Technical Exhibit D - As-Builts; Government Response to RFIs; and to change the Bid Opening Date and TIme. Bid Opening w ill be conducted at Shoemaker Center, Building 36000, Room 1463, Fort Hood, Texas 76544

Except as provided herein, all terms and conditions ofthe document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONT RACTING OFFICER (Type or print)

TEL: EMAIL:

15B. CONT RACT OR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNIT ED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

14-Mar-2019

EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

30-105-04 STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

W9115119B0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 28-Mar-2019 10:00 AM to 02-Apr-2019 10:30 AM. The description of performance has changed from 52.211-10 to FAR 52.211-10.

The required performance has changed from Replace # 2 Chiller at A/C Refrigeration Plant, Building 37015, this is an "Invitation for Bid" see section 00100 of this document for specific instructions A Bid Guarantee is required (See Section 00100, FAR Clause 52.228-1). Performance and payment bonds are required (See Section 00700, FAR Clause 52.228-15). As required by FAR 36.204, the estimated magnitude of this project is between $500,000.00 and $1,000,000.00. The NAICS for this acquisition is 238220, Plumbing, Heating, and Air- Conditioning Contractors (SB size standards $15 million) This Acquisition is 100% set aside for Women Owned Small Business concerns only; no large business bids will be accepted. The awarded of this contract will be required to provide a superintendent through completion of the project (see section 00700, FAR Clause 52.236-6).

Project Manager, Quality Control and Superintendent Position are considered key positions. These positions SHALL NOT be subcontracted and must work directly for the prime contractor. Bidders are required to provide a valid CAGE Code (Block 14 Facility), Point of contact (POC) and email address with their bid. Bidders are required to provide a CD copy of their bid document with their IFB submission. Bid Opening address MICC – Fort Hood, Bldg.

36000, Room 1551.

To Replace# 2 Chiller at A/C Refrigeration Plant, Building 37015This is an "Invitation for Bid" see section 00100 of this document for specific instructions A Bid Guarantee is required (See Section 00100, FAR Clause 52.228-1).

Performance and payment bonds are required (See Section 00700, FAR Clause 52.228-15). As required by FAR 36.204, the estimated magnitude of this project is between $500,000.00 and $1,000,000.00. The NAICS for this acquisition is 238220, Plumbing, Heating, and Air-Conditioning Contractors (SB size standards $15 million) This Acquisition is 100% set aside for Women Owned Small Business concerns only; no large business bids will be accepted. The awarded of this contract will be required to provide a superintendent through completion of the project (see section 00700, FAR Clause 52.236-6). Project Manager, Quality Control and Superintendent Position are considered key positions. These positions SHALL NOT be subcontracted and must work directly for the prime contractor. Bidders are required to provide a valid CAGE Code (Block 14 Facility), Point of contact (POC) and email address with their bid. Bidders are required to provide a CD copy of their bid document with their IFB submission. Bid Opening address Shoemaker Center, Building 36000, Room 1463, Fort Hood, Texas 76544

TABLE OF CONTENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Exhibit A Tech Exhibit A -

Specification Exhibit B Tech Exhibit B -

Drawings Attachment 1 Attachment1 - Appendix

A

3313 11-JAN-2016

5 04-DEC-2018

111 11-JAN-2016

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Exhibit A Tech Exhibit A - Specification

Exhibit B Tech Exhibit B - Drawings

3313 11-JAN-2016

5 04-DEC-2018

Exhibit C Tech Exhibit C - Revised 5 04-DEC-2018 Drawings

Exhibit D Tech Exhibit D - As- Builts

Attachment 1 Attachment1 - Appendix A

9 01-JUL-2005

111 11-JAN-2016

The following have been modified:

INSTRUCTION TO OFFERORS

Any bids received in response to this solicitation SHALL carry a 120 day acceptance period before prices need to be verified, extended or re-negotiated.

1. Submission of Bids

The sealed bid shall be supported by a draft progress schedule that demonstrates the offeror's understanding of the work requirements, phasing of work between buildings, and estimated time frames for ordering and installing equipment. Bidders are required to provide a CD copy of their bid documents with their IFB submission.

2. Public Bid Openings

Please refer to Block 13A of the 1442. Anyone wishing to attend the bid opening MUST notify the Contracting Officer (roy.r.cantrell2.civ@mail.mil) and Contract Specialist (mark.c.green.civ@mail.mil) by email no later than 29 March 2019 at 10:00A.M. CST with a firm commitment to attend.

MAILING ADDRESS FOR SEALED BIDS

Mission and Installation Contracting Command-Fort Hood ATTN: Mark Green (Contracting Section) 36000 Darnall Loop, Room 1300B Fort Hood, Texas 76544-5095

PUBLIC BID OPENING

Shoemaker Center-MICC Fort Hood Bldg 36000, Darnall Loop, Room 1463 Fort Hood, TX 76544 02 April 2019 at 10:30a.m.CDT

3. Pre-requisites for Speciality Trade Licensure and Certification

Mechanical HVAC license Class A (with minimum 3-5 years of experience), Certification Master Plumber, License Master Electrician, Certification

In responding to this solicitation for bids, the bidder shall provide copies of certifications/training identified above and below as a part of the bid. Failure to provide this documentation will render the bid non- responsive and no further consideration will be given to that bidder for award of this contract. No substitution of the individual possessing the required pre-qualifications will be authorized without the written approval of the Contracting Officer, and no time will be allowed for the contractor to acquire the required training/certification after the contract is awarded.

4. Work Experience

The prime contractor shall demonstrate that it possesses general construction contract management by providing at least three examples of relevant work experience within the last 5 years in an awarded contract similar to the requirements stated in this solicitation. Documentation shall be submitted with the bid and include the contract number, the date of contract award, the customer's name and contact information, the awarded dollar value, the value of the contract at completion, a description of all work elements included in the contract, the number and type of specialty trades needed to complete the contract, the period of time allocated for completion of the work and actual time required to complete the work (include reasons for time extensions).

Federal work experience is preferred; however, the Government will accept work experience from both State and institutional and commercial contracts as well. No residential work experience will be considered appropriate for this purpose. Failure to provide this documentation will render the bid/offer non-responsive and no further consideration will be given to that bidder for award of this contract.

5. Pre-Bid and Pre-Construction Conferences

The Contracting Officer will conduct a pre-bid/pre-proposal conference in conjunction with the site visit. All potential bidders/offerors attending the site visit are highly encouraged to attend the pre-bid/pre-proposal conference. Information on the scheduled Site Visit is located in FAR 52.236-3 SITE VISIT (CONSTRUCTION) (FEB 1995) of this solicitation. Space limitations dictate that no more than two representatives from each company attend. The Contracting Officer will review solicitation submittal requirements, and other administrative matters critical for successful and timely performance of the work.

The Contractor shall attend a Government coordinated preconstruction conference within 10 calendar days of contract award. As a minimum, the conference shall be attended by the contractor’s appointed project manager, the superintendent, the QCM, and administrative personnel responsible for preparation of contract documents, certified payroll records and invoices. The contractor shall deliver letter appointments of its key personnel that include each individual’s duties, roles and responsibilities.

6. Subcontractor List

Offerors shall submit a list of proposed subcontractors as an attachment to their bid. If offeror does not intend on utilizing subcontractors (self-perform), offeror shall state so in their bid. Failure to provide this listing or statement will render the quote nonresponsive and eliminate the offer from further consideration for award.

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Amendment 0001 – this amendment has revised drawings; As-builts 2005; change the bid opening date to 02 April 2019 at 10:30a.m. CDT; and adds the Government response to Industry.

(End of Provision)

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

RFI'S

W91151-19-B-0005 Replace #2 Chiller at CEP, Building 37015

Responses to Questions from Industry (RFIs)

1. Drawing M-601 Water Cooled Magnetic Bearing Chiller Schedule the CAP TONS shows 1,300. Are they requesting a 1300 ton or 1-300 ton chiller?

Ans. The government wants a 1300 ton chiller, Trane Brand name.

2. Are we to pull out existing wire?

Ans. Yes. Remove and replace existing elec. wiring.

3. Are we to use existing conduit?

Ans. Yes. Existing conduit can be reused.

4. Are we to pull in 2000 amperage wire for new chiller?

Ans. Yes.

5. Are we to install new 2000 amperage breaker in existing switchgear?

Ans. Yes.

6. Are all outages on existing switchgear to be on off hours or weekends?

Ans. All outages will be coordinated through the COR. All work will be done during normal hours.

An outage for the switchgear needs to be scheduled on weekends with the COR.

7. During the site visit it was discussed to leave the existing chilled and condenser water piping in place and only replace the pipe necessary to replace the chiller. Please confirm that this is the intent.

Ans. yes, the contractor will be responsible to reconnect piping and ensure proper condenser water and chilled water piping connections before ordering the new chiller. Also, the contractor will be responsible to replace all sensors, gauges, valves, thermometers...etc at new chiller.

8. During the site visit it was conveyed that only a Trane magnetic bearing chiller model CVHF 1300. This chiller type is a new product offering for Trane. We typically are cautious on installing new product lines that do not have a proven track record in the field. Will other chiller manufactures be acceptable provided that they meet or exceed the scheduled performance?

Ans. No, the government needs to install a Trane Chiller.

9. The new chiller specified indicates R134a type refrigerant. It was noticed during the site visit that all other chillers use R123 as the refrigerant and the refrigerant detection system is specific to that refrigerant.

Please confirm that the intent is to provide a new refrigerant leak detection system appropriate for the new chiller refrigerant type.

Ans. SEE revised drawings, sheet M-601, the new chiller will be equipped with R514 refrigerant per manufacturer specs. Also, see sheet M-101 for installation of a new refrigerant leak detection system appropriate for the new chiller refrigerant type.

10. Please confirm that if the existing electrical conductors are sufficient in size for the new chiller load that they will be allowed to be reused.

Ans. NO, the contractor will provide new electrical conductors for the new chiller as stated in sheet M-101.

11. Please provide Electrical As-Builts of facility.

Ans. The government will provide electrical as-built for info purposes only- (attachment A).

12. Technical Exhibit A Specifications includes several specifications and submittal requirements that do not appear applicable to this project. Please confirm this is a boiler plate document and only submittals and specifications that apply will be used for this project.

Ans. Concur.

13. There are requirements in the Specification for a Project Superintendent, Quality Control Manager, and Site Safety and Health Officer. Specification Section 01 45 01.00 20 indicates this requirement in Paragraph 3.1 Please confirm whether one person can serve all three of these roles for this project since it is a smaller project being performed in a limited area.

Ans. No, the government required the contractor to follow the specification requirements for a Project Superintendent, Quality Control Manager, and Site Safety and Health Officer as stated in Section 01 45 01.00 20.

14. Is the intent of the contract to provide uninterrupted service to the building during construction or is a cooling outage during construction acceptable? Are temporary chillers required to be carried in the contractor cost?

Ans. There is no need for a temporary chiller and any outage will be coordinated with the COR ahead of time.

15. In the Solicitation Document, under Pre-Requisites for Specialty Trade Licensure and Certification it lists Mechanical HVAC license, Master Plumber, and Master Electrician license to be submitted. Based on the Statement of Work there does not appear to be any plumbing work on this project. As such, will a Master Plumber license be required?

Ans. No.

16. The chiller for this project is expected to have a 10-12 week lead time. Will the contractor be able to negotiate when the NTP start date will occur based on lead time of the chiller to ensure the project can be completed within 120 days of NTP as required.

Ans. No. the contractor will be responsible for any time delays and will be charged per LD (LIQUIDED DAMAGES).

(End of Summary of Changes)