This document is a Performance Work Statement (PWS) for a federal contract opportunity to provide sampling and analysis of storm water and industrial wastewater at various locations within the U.S. Army Garrison (USAG) Yongsan-Casey.
The PWS outlines the contractor's responsibilities, including providing personnel, equipment, supplies, facilities, and other items necessary to collect and analyze water samples. The contractor must be familiar with storm water and industrial wastewater monitoring requirements, have prior experience, and use an accredited laboratory. The contract has a base year plus four option years, with set deliverables including sampling plans, analysis results, and annual reports. Specific performance standards and surveillance methods are provided. The solicitation number is W90VN824R0044 and the procuring agency is the Department of the Army Materiel Command Army Contracting Command.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KR-DPW-24-005, Sampling and Analysis of Storm Water and Industrial Wastewater from Various Location within USAG Yongsan-Casey, Performance Work Statement
(PWS)
Technical Exhibit
Technical Exhibit #1 – 6.0 Deliverables
DELIVERABLE FREQUENCY # OF COPIES MEDIUM/FORMAT DISTRIBUTION
A001 (Para. 2.1.1.1) Provide sampling plan.
One (1) time before first sampling
1 Electronic File Email/PDF
COR/ACOR
A002 (Para. 2.1.1.3) Provide analysis result, pictures, check list for USAG Yongsan- Casey
Two (2) times for Storm water a year and One (1) time for Industrial Wastewater a year
1 Electronic File Email/PDF
A003 (Para. 2.1.1.3) Provide final report.
One (1) time a year Three copies Two (2) hard copy and One
(1) Electronic file
Two (2) hard copy and One (1) electronic file
COR/ACOR
A004 (Para. 2.1.2.1.1) Phase In/Phase Out
Within 30 days of contract award: All documents shall be accepted by the KO
1 Hard Copy & 1 Electronic File
One (1) hard copy and One (1) electronic file
KO
A005 (Para 2.1.13) Manual Operations
Within 15 days of contract award:
Manual Operations Contingency Plan shall be accepted by the KO
1 Hard Copy & 1 Electronic File
One (1) hard copy and One (1) electronic file
KO
A006 (Para. 2.4.2.3.1) DoD Cybersecurity Awareness Training
All Contractor employees must complete the DoD Cybersecurity Awareness Training before issuance of network access and annually thereafter
One (1) copy of a certificate
One (1) hard copy COR
A007 (Para. 2.4.3.1) Safety Plan
Review and Acceptance: During phase in and within 10 days of commencement of work Revisions: five (5) calendar days prior to effective date of change
1 Electronic Copy
Email/PDF
A008 (Para. 3.3) Quality Control
Initial: within 30 days of contract award (or with the Contractor’s
1 Electronic Copy
Email/PDF COR/ACOR
Plan proposal if it is used in the evaluation process) Updates: All QCP updates shall be accepted by the COR
Technical Exhibit #2 – Location List and Area Map
Location List:
The work under this contract shall be performed at Camp Yongsan, Camp Casey, Camp Hovey, Rodriguez Live Fire Complex (RLFC), and Warrior Base in USAG Yongsan-Casey.
Area Map
Technical Exhibit #3, Sampling Points
Storm Water Sampling Points.
Installation # Sampling Point Water Type Frequency
Casey
1 Gate 1 Outfall (Storm water) 2 Times/Year 2 Gate 3 Outfall (Storm water) 2 Times/Year 3 222 South Outfall (Storm water) 2 Times/Year 4 246 North Outfall (Storm water) 2 Times/Year 5 690 North Inlet (Storm water) 2 Times/Year 6 811 NE Inlet (Storm water) 2 Times/Year 7 1018 East Inlet (Storm water) 2 Times/Year 8 1116 North Inlet (Storm water) 2 Times/Year 9 1842 Inlet (Storm water) 2 Times/Year
10 2361 South Inlet (Storm water) 2 Times/Year 11 Casey Creek Inlet (Storm water) 2 Times/Year
Hovey
12 Bridge 579 Outfall (Storm water) 2 Times/Year 13 4399 East Inlet (Storm water) 2 Times/Year 14 3445 SW Inlet (Storm water) 2 Times/Year 15 3428 Inlet (Storm water) 2 Times/Year 16 3866 West Inlet (Storm water) 2 Times/Year
RLFC 17 Rodriguez Live Fire Complex Outfall (Storm water) 2 Times/Year W/Base 18 254 South Outfall (Storm water) 2 Times/Year
Yongsan
19 B#1344 Southwest Outfall (Storm water) 2 Times/Year 20 Stream Outfall B#1455 South Outfall (Storm water) 2 Times/Year 21 B#1607 Southeast Outfall (Storm water) 2 Times/Year 22 Stream Inlet B#2701 Northeast Outfall (Storm water) 2 Times/Year 23 B#4805 East Outfall (Storm water) 2 Times/Year 24 B#4815 Northeast Outfall (Storm water) 2 Times/Year 25 B#4280 Child Develop Center Outfall (Storm water) 2 Times/Year 26 B#5701 Northwest Outfall (Storm water) 2 Times/Year 27 B#5709 West Outfall (Storm water) 2 Times/Year 28 5717 Southwest Outfall (Storm water) 2 Times/Year
Total: 28 Points x 2 Times = 56 Points
Industrial Wastewater Sampling Points.
Installation # Sampling
Point Bldg Usage Water Type Frequency
Casey
1 38 Vehicle Storage Outfall (Industrial Wastewater) 1 Time/Year 2 93 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 3 94 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 4 105 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 5 343 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 6 481A Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 7 497 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 8 499A Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 9 627 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year
10 628 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 11 635 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 12 644 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 13 647A Heavy Shop Outfall (Industrial Wastewater) 1 Time/Year 14 647B Heavy Shop Outfall (Industrial Wastewater) 1 Time/Year 15 647C Heavy Shop Outfall (Industrial Wastewater) 1 Time/Year 16 648 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 17 775 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 18 786 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 19 793 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 20 794 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 21 882A Sewage Plant Outfall (Industrial Wastewater) 1 Time/Year 22 882B Sewage Plant Outfall (Industrial Wastewater) 1 Time/Year 23 891 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 24 1024 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 25 1064 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 26 1068A Gas Station (DLA) Outfall (Industrial Wastewater) 1 Time/Year 27 1068B Gas Station (AAFES) Outfall (Industrial Wastewater) 1 Time/Year 28 1158A Tank Wash Rack Outfall (Industrial Wastewater) 1 Time/Year 29 1158B Tank Wash Rack Outfall (Industrial Wastewater) 1 Time/Year 30 1171 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 31 1564 POL Tank Farm Outfall (Industrial Wastewater) 1 Time/Year 32 1751 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 33 1753 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 34 1758 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 35 1904 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 36 1937 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 37 2285 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 38 2286 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 39 2367 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 40 2526A Mainat Shop (TMP) Outfall (Industrial Wastewater) 1 Time/Year 41 2528 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 42 2604 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year
Installation # Sampling Point Bldg Usage Water Type Frequency
Hovey
43 3461 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 44 3468A Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 45 3468B Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 46 3469 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 47 3478 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 48 3482 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 49 3484 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 50 3505 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 51 4108 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 52 4125A Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 53 4125B Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 54 4130 Wash Plat Form Outfall (Industrial Wastewater) 1 Time/Year 55 4322A Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 56 4322B Motor Pool Outfall (Industrial Wastewater) 1 Time/Year 57 4367 Motor Pool Outfall (Industrial Wastewater) 1 Time/Year
Yongsan
58 1314 ORG Storage Bldg Outfall (Industrial Wastewater) 1 Time/Year 59 1344 Eng/Housing MNT Outfall (Industrial Wastewater) 1 Time/Year 60 5701 Maint Shop Outfall (Industrial Wastewater) 1 Time/Year 61 5709 Admin Outfall (Industrial Wastewater) 1 Time/Year 62 5711 Maint Shop Outfall (Industrial Wastewater) 1 Time/Year 63 5712 Maint Shop Outfall (Industrial Wastewater) 1 Time/Year 64 5713 Maint Shop Outfall (Industrial Wastewater) 1 Time/Year 65 5714 Maint Shop Outfall (Industrial Wastewater) 1 Time/Year 66 5741 OWS Outfall (Industrial Wastewater) 1 Time/Year 67 5742 OWS Outfall (Industrial Wastewater) 1 Time/Year 68 5743 OWS Outfall (Industrial Wastewater) 1 Time/Year
W/Base 69 285 Wash Rack (TSAK) Outfall (Industrial Wastewater) 1 Time/Year
Re-Sample +10 Resample after cleaning the oil/water separator if the analysis results exceed the criteria of KEGS.
Total: 69 Points + 10 (Re-Sample) = 79
Technical Exhibit #4 – Sample Parameters, Analysis Methods, Frequency and Quantity
Storm Water
Parameters Sample Type Frequency Sample
Number
QA
Samples
(Duplicate)
Equip /Field Blank
Total Sample Number
Arsenic (Total) Grab 2 Times/Year 28 4 4 72
Chromium (Total) Grab 2 Times/Year 28 4 4 72
Copper (Total) Grab 2 Times/Year 28 4 4 72
Iron (Total) Grab 2 Times/Year 28 4 4 72
Lead (Total) Grab 2 Times/Year 28 4 4 72
Oil and Grease Grab 2 Times/Year 28 4 4 72 pH Grab 2 Times/Year 28 4 4 72
Selenium (Total) Grab 2 Times/Year 28 4 4 72
Total Suspended Solid Grab 2 Times/Year 28 4 4 72
TPH-Diesel Range Grab 2 Times/Year 28 4 4 72
TPH-Gasoline Range Grab 2 Times/Year 28 4 4 72
Turbidity Grab 2 Times/Year 28 4 4 72
Zinc (Total) Grab 2 Times/Year 28 4 4 72
Industrial Wastewater
Parameters Sample Type Frequency Sample
Number
QA
Samples
(Duplicate)
Equip /Field Blank
Total Sample Number
Alkyl Benzene Sulfonate (ABS) (mg/L) Grab 1 Time/Year 79 6 8 93
Arsenic (mg/L) Grab 1 Time/Year 79 6 8 93
Cadmium (mg/L) Grab 1 Time/Year 79 6 8 93
Chromium (mg/L) Grab 1 Time/Year 79 6 8 93
Parameters Sample Type Frequency Sample
Number
QA
Samples
(Duplicate)
Equip /Field Blank
Total Sample Number
Copper (mg/L) Grab 1 Time/Year 79 6 8 93
Cyanide (mg/L) Grab 1 Time/Year 79 6 8 93
Fluorine (mg/L) Grab 1 Time/Year 79 6 8 93
Hexavalent Chromium (mg/L) Grab 1 Time/Year 79 6 8 93
Lead (mg/L) Grab 1 Time/Year 79 6 8 93
Mercury (mg/L) Grab 1 Time/Year 79 6 8 93
Normal Hexane Extracts:
- Mineral Oil (mg/L) Grab 1 Time/Year 79 6 8 93
- Animal/Vegetable Oil (mg/L) Grab 1 Time/Year 79 6 8 93
PCB (mg/L) Grab 1 Time/Year 79 6 8 93 pH Grab 1 Time/Year 79 6 8 93
Phenolic Substance (mg/L) Grab 1 Time/Year 79 6 8 93
Soluble Iron (mg/L) Grab 1 Time/Year 79 6 8 93
Soluble Manganese (mg/L) Grab 1 Time/Year 79 6 8 93
Tetrachloroethylene (mg/L) Grab 1 Time/Year 79 6 8 93
Total Nitrogen (mg/L) Grab 1 Time/Year 79 6 8 93
Total Phosphorous (mg/L) Grab 1 Time/Year 79 6 8 93
Total Suspended Solids (mg/L) Grab 1 Time/Year 79 6 8 93
Trichlorethylene (mg/L) Grab 1 Time/Year 79 6 8 93
Zinc (mg/L) Grab 1 Time/Year 79 6 8 93
Technical Exhibit #5 – Performance Requirements summary (PRS) Matrix
Required Services/ Performance Object
PWS
Paragraph
Number Performance
Standard
Maximum Allowable Degree of
Deviation from Requirement (AQL Level)
Method of Surveillance
Deduct Schedule
Prepare sampling tools and equipment and submit a sampling plan
2.1.1.1 The contractor
provided all necessary items and sampling plan.
COR will inspect items and review plan after contract is awarded.
95% Compliance and performance standard
The COR will visually inspect sampling tool and equipment.
Contractor shall re-performance within two
(2) weeks.
Perform required sampling of storm water and industrial wastewater
2.1.1.2 The contractor will
provide manpower to perform water sampling according to the sampling plan.
95% Compliance and performance standard
Random and Split Sampling
Contractor shall re-performance within two
(2) weeks.
Submit analysis result
2.1.1.3 The contractor
provided analysis results with
100% Compliance and
100% Inspection
Contractor re-performance sampling points’ picture, visual check list after all sampling finished within 10 calendar days. Quality assurance results should be done for analysis.
performance standard within one
(1) month
Submit final report for total sampling and analysis
2.1.1.3 The contractor
provided final report within 10 calendar days after completing the report in response to Government comments.
100% Compliance and performance standard
Review and acceptance the data by
COR.
Contractor re-performance within one
(1) week
The Contractor will ensure that the licenses or certificates are kept current. Copies of these licenses or certifications will be provided to the COR
2.4.4.1 The contractor
provided current and valid licenses or certificates and training. COR will check out them upon starting from first sampling to last sampling.
100% Compliance and performance standard.
The COR will review 100% of Contractor certifications.
Contractor shall re-submit current and valid licenses or certificate within two
(2) weeks.
Technical Exhibit #6 – Contract Requirements
1.0 Requirements
1.1 Period of Performance (PoP). Base year with four (4) option years.
Base Year Period: 1 Aug 24 – 31 Jul 25 1st Option Year Period: 1 Aug 25 – 31 Jul 26 2nd Option Year Period: 1 Aug 26 – 31 Jul 27 3rd Option Year Period: 1 Aug 27 – 31 Jul 28 4th Option Year Period: 1 Aug 28 – 31 Jul 29
1.2 Contractor’s Qualification. The contractor shall be familiar with storm water and industrial wastewater monitoring requirements as specified in USFK Regulation 201-1 and all other local and US rules and regulations. Contractor should analyze samples by laboratory which has valid certificate of “National Environmental Laboratory Accreditation Program (NELAP-국가 환경실험실 인증 프로그램)” issued by National Environmental Laboratory Accreditation Conference Institute (국가 환경실험실 인증협회).
1.3 Prior Work Experience. The Contractor shall have at least two years of experience in the sampling and analysis of storm water and industrial wastewater for the U.S. Government or in the local economy within the last five (5) years.
| Technical Exhibit |
| Technical Exhibit #1 – 6.0 Deliverables |
| Technical Exhibit #2 – Location List and Area Map |
| Location List: |
| Area Map |
| Technical Exhibit #4 – Sample Parameters, Analysis Methods, Frequency and Quantity |
| Technical Exhibit #5 – Performance Requirements summary (PRS) Matrix |
| Technical Exhibit #6 – Contract Requirements |
| 1.0 Requirements |
| 1.1 Period of Performance (PoP). Base year with four (4) option years. |
| Base Year Period: 1 Aug 24 – 31 Jul 25 |
| 1st Option Year Period: 1 Aug 25 – 31 Jul 26 |
| 2nd Option Year Period: 1 Aug 26 – 31 Jul 27 |
| 3rd Option Year Period: 1 Aug 27 – 31 Jul 28 |
| 4th Option Year Period: 1 Aug 28 – 31 Jul 29 |
| 1.2 Contractor’s Qualification. The contractor shall be familiar with storm water and industrial wastewater monitoring requirements as specified in USFK Regulation 201-1 and all other local and US rules and regulations. Contractor should analyze sampl... |
| 1.3 Prior Work Experience. The Contractor shall have at least two years of experience in the sampling and analysis of storm water and industrial wastewater for the U.S. Government or in the local economy within the last five (5) years. |
File details come from the government source that posted it. Updated .