ATT 7 Q_A after the site visit_1 JULY.docx

DOCX document 837 KB Posted

Attached to
Amendment - 51 CES GROUND MAINTENANCE SERVIE IN OSAN AIRBASE, REPUBLIC OF KOREA
Solicitation number
W90VN6-25-R-A00500001
Issued by

About this file

This document is an Amendment to a Ground Maintenance Services Solicitation for Osan Air Base in the Republic of Korea (Solicitation Number: W90VN6-25-R-A00500001). The amendment includes several key modifications: adding FAR 52.232-18, updating the Performance Work Statement (PWS), and changing specific Contract Line Item (CLIN) descriptions from "Except alpha site" to "Alpha site" for several line items related to Munitions Storage Area maintenance.

The amendment includes a detailed Q&A document addressing technical specifications and contract requirements. Notable details include language proficiency requirements for the Contract Manager (TOEIC Speaking and Reading/Listening test scores), pricing breakdown instructions requiring detailed pricing per acreage and ground type, and clarification of ground maintenance areas. The solicitation covers maintenance of various ground types including Airfield BASH Area (412.95 acres), Munitions Storage Areas, Improved Areas, Semi-improved Areas, and Unimproved Areas, with specific maintenance requirements for each zone. The contract is being managed by the Department of the Army Materiel Command Army Contracting Command.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Summary of Amendment

1. Added FAR 52.232-18.

2. Updated the PWS.

3. Amended Solicitation : CLINs description - CLIN0003AB, CLIN1003AB, CLIN2003AB, CLIN3003AB, CLIN4003AB description have been changed from ‘Except alpha site’ to ‘Alpha site.’

4. Amended Addendum to FAR 52.212.1 instruction to offerors and Addendum to FAR 52.212.2 Evaluation.

5. Added attachment 7 for Q & A

Questions after a site visit on 23 JUNE 2025 Q1. In accordance with PWS 1.13.2, the CM shall be scored higher than “Intermediate Low (90 score)” level for TOEIC Speaking test and 500 score (with minimum of 225 score for reading and 275 score for listening) for TOEIC Reading & Listening test.

Shall an Awardee submit a qualified TOEIC scores of the proposed CM after award?

If so, when does an Awardee have to submit a qualified TOEIC scores of the proposed CM after award?

Answer.

The offerors are not expected/required to submit TOEIC scores until they are awarded. The contractor shall submit the copies of the score certificate within 1 month. A week or two delays may be permitted given the time it takes for TOEIC organization to issue TOEIC certificates. The contractor shall replace the initial CM with another CM with eligible TOEIC scores along with other required qualifications, if the initial CM does not qualify some of the requirements.

Q2. VOLUME III: FACTOR 4 - Price The offeror shall submit a price breakdown of the Contract Line items in Excel format along with the offeror’s cost proposal.

Shall an offeror submit just one consolidated price breakdown for FACTOR 4 - Price, or shall an offeror submit price breakdowns per Contract Line Item including one consolidated price breakdown?

Answer.

The offerors are expected/required to submit price breakdown for each and every CLIN. Specifically, the price breakdown shall manifest prices PER ACREAGE on different types of grounds. This will be one of the reference points for KO to implement possible modifications for updated acreages/quantities of different types/sizes of requirements. Therefore, the offerors shall structure the price breakdown to include labor/material/equipment price and indirect price along with profit. However, the offerors may use the Base year CLINs price breakdown along with escalation/inflation rate, if any, in writing price breakdown for the following Option Year CLINs for the sake of simplicity.

Q3. Is a Grounds Maintenance Technician "Mechanic for equipment or tools" or Craftsman Landscape Architecture (조경기능사)?

The grounds maintenance technician referred in the PWS does not necessarily mean “Craftsman Landscape Architecture (조경기능사)”. However, presenting those certificates would strengthen the proposal given the technician with relevant certificates are actually hired for the performance of this contract.

Question 4. Is 7-B a BASH Area?

Answer.

The above 7-B area in question is Semi-Improved (BASH) Airfield light fixture/other fixture area with 2”-4” requirement. However, it still falls under the CLIN of “Maintain Airfield BASH Area” and PWS of para. 5.1.2 for BASH area. Please see the table below for your understanding including other ground types.

Requirements (CLIN)
Ground type
Acreage
Remarks
X001, X002
Airfield BASH Area
412.95
Airfield Light Fixture, etc.
4.11
X003AA, X004AA
Munitions Storage Area (MSA) – Except Alpha Site
138.02
Echo/Delta/Preload
X003AB, X004AB
Munitions Storage Area (MSA) – Alpha Site
54.10
Alpha
X005, X006
Improved Area
272.14
X007, X008
Semi-improved Area
296.67
X009
Un-improved Area
108.29

Question 5.

Is an upper area near Davis Gate an Improved area?

Is a lower area near Davis Gate an Unimproved area?

The North side of Davis Gate will be considered Semi-Improved (BASH) 7”-14”, while the South Side will be considered Unimproved 10”-14”.

Question 6.

Regarding line-item no.0003AB Maintain MSA (Growing season) - Except alpha site.

The phrase 'except alpha site' seems unclear. I believe it should be simply 'alpha site' instead. Could you please verify it.

6. CLIN0003AB, CLIN1003AB, CLIN2003AB, CLIN3003AB, CLIN4003AB description have been changed from ‘Except alpha site’ to ‘Alpha site.’