Preproposal Slides for Repair Main Apron Access and Alert Pavements Buckley AFB CO
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-PROPOSAL CONFERENCE
20 MAY 2014
Buckley Air Force Base Aurora, Colorado
MSgt Lia Arthofer: Presentation Facilitator (on behalf of KO)
Lt Col William Smith: Base Civil Engineer
Lt Col Tom Nefe: Assistant Base Civil Engineer
Lt Col Tom Niichel: Contracting Officer Rep
Lt Col Crissie Fitzgerald: Contracting Officer Rep
Marilyn Hill: Contracting Officer (NGB-OPARC-S)
Anna Randall: Procurement Analyst-CTR (UBT, Inc.; NGB-OPARC-S)
Your Name
Company
Your Position in Company
Are you a Prime or Subcontractor?
Sequence 1 – 99 Calendar Days Sequence 2 – 149 Calendar Days Sequence 3 – 50 Calendar Days Sequence 4 – 53 Calendar Days Mobilization and Closeout – 81 Days TOTAL: 432 calendar days
Repair Main Apron Access and Alert Pavements
Magnitude - $10,000,000 - $25,000,000
One Firm-Fixed Price Contract will be awarded
Project is being solicited 100% Small Business Set Aside
The Contract will be awarded using Source Selection Tradeoff Procedures
Evaluation Factors – Technical, Past Performance and Price
On The Web - www.fbo.gov
Solicitation Exhibits Questions & Answers Document Amendments
Check Regularly & Refresh Web Page Plans & Specifications- must be registered and have password on FBO
Questions about this program or DD Form 2345 should be addressed to:
U.S./Canada Joint Certification Office DLA Logistics Information Services Federal Center, 74 Washington Ave., North Battle Creek, MI USA 49037-3084
Phone: (800) 352-3572 Email: jcp-admin@dla.mil
Export Controlled Materials Company must be certified (via an approved DD Form 2345) by the Joint Certification Program (JCP) administered by the DLA Logistic Information Service (DLIS)
The U.S./Canada Joint Certification Program (JCP) office reported to this office that once a company is certified with the JCP office (normally 7 to 12 business days), the company should contact FBO to have them add their JCP number to their FBO account. JCP has indicated that they are currently experiencing a three (3) week delay in addition to the normal waiting period.
Construction period is 432 days after
Notice to Proceed is issued
The Government intends to award
Without Discussions and there may not be a chance for Discussions, Corrections, or Revised Proposals.
Offerors are strongly encouraged to carefully read the requirements of the Solicitation and comply accordingly.
Section 00110 of the RFP details the required Information and Format for the proposal.
2 Volumes Are Required
VOL 1 – Price/Cost Proposal Pro forma documents Pricing information
VOL 2 – Two Parts Part 1- Technical Capability Proposal Part 2- Past/Present Performance Info
Offeror portion of SF1442
Section 00010 – Pricing Info – All line items Exhibit D
Section 00600 – Representations and Certifications (R&C)
Complete R&Cs in ORCA on the web Complete and Return DoD R&Cs in Section 0600 Complete & Include an Introductory page - Section 00110
Paragraph 3.5.1.2
Provide all:
labor, materials, equipment, transportation and supervision to demolish onsite pavements and drainage structures, structures and utilities; in accordance with the Drawings and Specifications (costs included in Base Bid).
Part I-Technical Capability
Comprised of four (4) sub factors:
1. Experience & Capability
2. Construction Schedule & Timeline
3. Construction Equipment & Plant
4. Material & Product Compliance Schedule
Technical Ratings
ACCEPTABLE:
Proposal meets the minimum requirements
UNACCEPTABLE:
Proposal does NOT clearly meet the minimum requirements
Subfactor 1 – Experience & Capability (Limited to 15 pages) Discuss the projects listed in the Exhibit A’s
Provide a narrative that discusses the management plan & approach
Discuss management plan regarding the full spectrum of activities
Discuss the Key Personnel, including their experience & education especially how it relates to the Specification Section 32 13 11
Describe how you will obtain the specified aggregate, testing procedures, etc.
Describe how you will ensure grade control & final elevations
Describe experience & capability in managing a project in the local Denver, CO area.
Subfactor 2 – Construction Schedule and Timeline (Limited to 5 pages)
Provide Construction Schedule using the
Critical Path Method (CPM)
Subfactor 3 – Construction Equipment & Plant
Concrete Operations
Equipment to Rubbilize PCC
Stabilization Equipment
Slip-Form Paver Equipment
Preformed Joint Seal Installation machine
Subfactor 4 – Material & Product Compliance
Read Spec carefully regarding the “or- equal” products
May make a positive statement if proposing the same product
Offerors who intend to propose “or-equal” products shall submit a section in the technical proposal listing the substitution
Exhibit A - Part 1- Performance Relevancy Questionnaires – Use Exhibit Format!
Complete not more than 5 documents for Relevant contracts completed or substantially completed (70%) in the last five years
Exhibit A - Part 2 - Describe compliance with
FAR 52.219-8, Utilization of Small Businesses
Send Questionnaires for the Exhibit A Projects to your references DO THIS EARLY – must be received by the
Contracting Office by the closing date.
If you do not have relevant past performance and are using experience of key personnel, predecessor companies, or subcontractors to obtain this, ensure you clearly state this in the proposal
To be considered, subcontractor must complete a consent form - Exhibit B
PROPOSAL DUE 1400 HOURS (2:00 P.M.), 17 JUNE 2014
Proposal Must Be Signed By Officer Of Your Company
No Facsimile Or Electronic Offers
Send or deliver to: (follow instructions in Sec 110)
USPFO-CO
Purchasing & Contracting, ATTN: Ms. Marilyn Hill
660 S. Aspen Street, Bldg. 1005, MS66 Buckley Air Force Base Aurora, CO 80011
Offerors must request access to the base
NLT 13 JUNE 2014.
Late proposals due to delays at the base entrance will not be an excusable delay.
Plan Accordingly For Base Access!
Reference Questionnaires are also due by 2:00 p.m., 17 June 2014.
Send Reference Questionnaires out
EARLY!
Return to Contracting Officer via E-mail at:
127wg.ngbzcparcomb@ang.af.mil
Exhibit A- Performance Relevancy Questionnaire
PART 1 (NTE 3) PART 2 (1)
Exhibit B - Subcontractor/Teaming Partner/Key Personnel Info & Consent Form (if applicable)
Exhibit C - Reference Questionnaire Package
Exhibit D - Option Information Form
Process is detailed in RFP section 00120
Carefully review section 00120 when preparing proposal
Comply with section 00100 and 00110 requirements
Failure to furnish a complete proposal may result in elimination from consideration
Best value is defined as an award based on the greatest overall benefit in response to the requirement.
Award is based on price and other non-cost related factors.
Technical Past/Present Performance Price
The Technical Factors are somewhat more important that Past Performance and when combined however, the non-cost factors are approximately equal to the Price Factor.
Technical will be evaluated first, Price Factor second and Past Performance last.
The Technical Factor evaluation will result in an offer being rated as “Acceptable” or “Unacceptable”. If deemed unacceptable, it will not continue in the competition.
If Price is determined to be reasonable & realistic, the offer will continue in the competition for a PP evaluation.
Submit a complete proposal in accordance with instructions – use formats provided.
Prime Contractors are responsible for coordination among the divisions with subcontractors.
Award is contemplated to be made without discussions - DO NOT anticipate a chance to make corrections or changes.
Your first proposal will most likely be your only proposal!
Read the solicitation requirements carefully!
Consider using Section 00120 to “rate” yourself before submitting the proposal –
IS IT COMPLETE?
When using a subcontractor to obtain/enhance relevancy, provide Subcontractor Consent Form, Exhibit B, or it will not be considered.
Award in this process does not necessarily mean the lowest price wins.
All amendments will be posted on the FBO web site
Check site regularly for changes & refresh the page
After closing, no information will be available until award Awards will be posted to the FBO website
Results should be announced in approximately 90 days
FAR 52.219-14 Limitations on Subcontracting apply; Small Business must perform 15% of cost of contract, not including the cost of materials, with its own employees.
Questions must be submitted via email to:
127wg.ngbzcparcomb@ang.af.mil
Submit questions NLT COB 10 June 2014
Questions received after 10 June 2014 may be held and addressed after RFP closing, with those offerors determined to be in the competitive range, if discussions are deemed necessary.
Do not call technical personnel or A&E.
This will delay getting an answer.
All questions, on a non-attribution basis, and the answers will be posted to www.fbo.gov.
If necessary, addendums issued by an amendment, will also be posted.
Check web site regularly. Do not forget to refresh web page.
www.fbo.gov www.acquisition.gov www.sam.gov orca.bpn.gov www.wdol.gov/wdol/scafiles/davisbacon/co.html
2:00 p.m.
17 June 2014
*REMINDER* YOU MUST HAVE REFERENCES
SENT IN BY THIS TIME AND DATE
Important information to know before we begin our site visit.
| W90FYQ-14-R-0002�CRWU 11-2010 �REPAIR MAIN APRON ACCESS AND ALERT PAVEMENTS |
| USPFO Colorado |
| Slide Number 3 |
| Slide Number 4 |
| PERIOD OF PERFORMANCE |
| SCOPE (WORK) OF CONTRACT |
| SCOPE (WORK) OF CONTRACT |
| SOLICITATION, PLANS�& SPECIFICATIONS |
| SOLICITATION, PLANS�& SPECIFICATIONS |
| SOLICITATION, PLANS�& SPECIFICATIONS |
| CONTRACT PERIOD |
| IMPORTANT REMINDER�The following is a brief overview of the proposal requirements |
| DISCLAIMER �The following is a brief overview of the proposal requirements |
| SUBMISSION REQUIREMENTS |
| SUBMISSION REQUIREMENTS |
| VOLUME 1- Price/Cost |
| VOLUME 1- Price/Cost |
| VOLUME 2 - PART I �Technical Capability�NO PRICING/COST IN THIS VOLUME |
| �����������������VOLUME 2 - PART I �Technical Capability |
| VOLUME 2 - PART I�Technical Capability (CONT’D) |
| VOLUME 2 - PART I�Technical Capability (CONT’D) |
| VOLUME 2 - PART I�Technical Capability (CONT’D) |
| VOLUME 2 - PART I�Technical Capability (CONT’D) |
| VOLUME 2 PART II - Past/Present Performance Information�NO PRICING/COST IN THIS VOLUME |
| VOLUME 2 PART II - Past/Present Performance Information (CONT’D)�NO PRICING/COST IN THIS VOLUME |
| PROPOSAL DUE DATES |
| PROPOSAL DUE DATES |
| REFERENCES |
| EXHIBITS |
| PROPOSAL EVALUATION |
| BEST VALUE |
| EVALUATION FACTORS |
| IMPORTANT REMINDERS |
| IMPORTANT REMINDERS |
| IMPORTANT REMINDERS |
| IMPORTANT REMINDERS |
| HOW QUESTIONS �WILL BE HANDLED |
| ANSWERS TO QUESTIONS |
| HELPFUL WEBSITES |
| PROPOSALS DUE� NO LATER THAN |
| SITE VISIT SAFETY BRIEFING |
| QUESTIONS |
File details come from the government source that posted it. Updated .