CRWU_10-2010_Pre-Proposal_Tech.pdf

PDF 358 KB Posted

Attached to
Repair Main Apron Access and Alert Pavements, Buckley AFB, Aurora, Colorado
Solicitation number
W90FYQ-14-R-0002
Issued by

About this file

Preproposal Technical information.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

I n t e g r i t y - S e r v i c e - E x c e l l e n c e

CRWU 11-2010

Pre-Proposal Conference

20 May 2014

Buckley AFB

Overview

• Demolish Concrete

• Approximately 25,000 CY PCC

• Replace Concrete sections on Taxi-lanes and Alert Area

• Approximately 47,000 SY PCC

• Grade Bio-swale area and detention pond

• Install Storm Drainage System

• Replace Approx. 36’x 25’ Asphalt Shoulder

• Establish Pavement Markings

• Crush waste concrete and haul to spoils area

Construction Access

I n t e g r i t y - S e r v i c e - E x c e l l e n c e 4

S4S3

S2B

S1A

S1B

S2A

S2C

S2C Opt

Construction Phasing

• The COE’s will conduct a mandatory Pavement Workshop, here at Buckley, prior to any work (Ref. Spec Sec 01000 and 32 13 11)

• The workshop will be 2 days on PCC

• Various individuals are required to attend portions of the workshop. See the specifications

Pavement Workshop

• Estimate Award End of Jul 2014

• Estimate Notice to Proceed 15 Aug 2014

• Mobilization/Schedule/Submittals – 33 days

• Start Construction Sequence 1A/Apron Drainage

Area Approx. 17 Sep 2014

• Construction Sequence 3 & 4 Alert Area can be done simultaneous with Seq 1 & 2

• Winter exclusion

• Estimate Sequence 2 start Spring 2015

• Construction Completion 22 Oct 2015

Construction Schedule