B08 Attachment 0004_ PDISE Questions and Answers Amd 001.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
Amendment 0003 & 0004 - Project Manager Expeditionary Energy and Sustainment Systems (PM E2S2) Power Distribution Illumination Systems, Electrical (PDISE)
Solicitation number
W909MY-25-B-0001
Issued by

About this file

This is a Questions and Answers document containing 58 questions and responses related to solicitation W909MY-25-B-0001 for Power Distribution Illumination Systems, Electrical (PDISE) components and accessories. The majority of questions seek clarification on incorrect National Stock Numbers (NSNs) listed in the solicitation, with the government confirming the correct NSNs for various components including electrical feeder centers, cable assemblies, and distribution centers.

Key clarifications include: the ship-to destination is DLA Distribution Center in Tobyhanna, PA; inspection and acceptance is at origin rather than destination; 60-amp cables are not required for this procurement; the First Article Testing period is 12 months total with 6 months for fabrication and 6 months for testing; configuration management requirements are in place despite this being a build-to-print effort; and an Economic Price Adjustment clause will be added to address potential tariff impacts. Technical Data Package (TDP) questions revealed several drawing revision discrepancies that were clarified by the government. The file provides detailed corrections to numerous part numbers and specifications but does not modify the core requirements of the solicitation.

View the file

Other files

File Type Posted
W909MY25B0001 AMD 0003.pdf PDF
W909MY25B0001 AMD 0004.pdf PDF
W909MY-25-B-0001 IFB rollup.pdf PDF
W909MY-25-B-0001 AMD 0002 unlocked.pdf PDF
B08 EPA Clause for Section H.docx DOCX document
W909MY-25-B-0001 AMD 0001.pdf PDF
13230E7022F001.pdf PDF
PDISE IFB Attachments.zip ZIP file
W909MY-25-B-0001 IFB signed.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions

Item #Page / Section NumberDescriptionQuestion /RecommendationGovernment Response
Solicitation
1Page 2 / Section A / Number 5Optional Ordering PeriodOne 4 Year Optional Ordering Period: 366 – 1461 (Days After Award (DAA)) – this appears to be a three-year period, not four years:
1,461 DAA

-366 DAA

1095 Days / 365 Days per year = 3 years

Please clarify.The option year is One - 4 year Optional Ordering Period: 366-1825 (Days After Award (DAA)). Please see the Invitation for Bid (IFB)
2Page 2 / Section A / Number 8"SHIP TO" LocationSection J, Attachment 0001. For planning purposes, the delivery location should be Tobyhanna Army Depot, PA 18466. This statement conflicts with the SHIP TO locations detailed in Section B which universally specify ABERDEEN TEST CENTER as the address for product deliveries. If the contractor is expected to pay the freight for product deliveries (FOB POINT: Destination), understanding the SHIP TO location will be important to our bidding process. Section F of the SOW specifies Tobyhanna Army Depot. Please clarify.The ship to destination is DLA Distribution Center, Tobyhanna, PA 18466-5059 ( DoDAAC W25G1W).
3Pages 5 through 49 / Section B / all itemsInspection and AcceptanceAll items 0001 through A015 show INSPECTION: Destination ACCEPTANCE: Destination. Is this correct? In this contractor's experience, Inspection and acceptance take place at "Origin" for PDISE and similar deliverables. Please clarify.The Inspection and Acceptance is Origin.
4Page 7 / Section B / Item 0005NSN# incorrectThe NSN # for M200 Electrical Feeder Center Assebmly is 6150-01-598-5455. The DRAFT lists the Drawing # 13229E6300 as the NSN. Please clarify.Confirmed: NSN is 6150-01-598-5455
5Page 8 / Section B / Item 0006NSN# incorrectThe NSN # for M100 Electrical Feeder Center Assebmly is 6150-01-598-5282. The DRAFT lists the Drawing # 13229E6325 as the NSN. Please clarify.Confirmed: NSN is 6150-01-598-5282
6Page 9 / Section B / Item 0007NSN# incorrectThe NSN # for M40 Electrical Distribution Center Assebmly is 6150-01-598-4796. The DRAFT lists the Drawing # 13229E6345 as the NSN. Please clarify.Confirmed: NSN is 6150-01-598-4796
7Page 9 / Section B / Item 0008NSN# incorrectThe NSN # for M46 Container, Storage, Utility is 8145-01-568-4834. The DRAFT lists the Drawing # 13229E6362 as the NSN. Please clarify.Confirmed: NSN is 8145-01-568-4834
8Page 10 / Section B / Item 0009NSN# incorrectThe NSN # for Cable Assembly GRP PC, 200 Amp/Phase is 6150-01-247-4768. The DRAFT lists the Drawing # 13226E7021 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4768
9Page 10 / Section B / Item 0010NSN# incorrectThe NSN # for Cable Assembly GRP PC, 100 Amp/Phase is 6150-01-265-6300. The DRAFT lists the Drawing # 13226E7020 as the NSN. Please clarify.Confirmed: NSN is 6150-01-265-6300
10Page 11 / Section B / Item 0011NSN# incorrectThe NSN # for Cable Assembly GRP PC, 40 Amp/Phase is 6150-01-265-6301. The DRAFT lists the Drawing # 13226E7019 as the NSN. Please clarify.Confirmed: NSN is 6150-01-265-6301
11Page 12 / Section B / Item 001260Amp Cable Required?Both M60 Electrical Distribution System, and M60 Electrical Distribution Assembly are not among the top-level items being solicited, yet this 60Amp cable assembly is required? Please confirm.60A cable not required for this procurement
12Page 12 / Section B / Item 0012NSN# incorrectThe NSN # for Cable Assembly GRP PC, 60 Amp/Phase is 6150-01-247-4778. The DRAFT lists the Drawing # 13226E7018 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4778, - Cable not required for this procurement
13Page 12 / Section B / Item 0013NSN# incorrectThe NSN # for Cable Assembly GRP S/F, 200 Amp/Phase, 25-ft is 6150-01-247-4782. The DRAFT lists the Drawing # 13226E7025 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4782
14Page 13 / Section B / Item 0014NSN# incorrectThe NSN # for Cable Assembly GRP S/F, 100 Amp/Phase, 50-ft is 6150-01-256-6304. The DRAFT lists the Drawing # 13226E7024 as the NSN. Please clarify.Confirmed: NSN is 6150-01-256-6304
15Page 13 / Section B / Item 0015NSN# incorrectThe NSN # for Cable Assembly GRP S/F, 40 Amp/Phase, 100-ft is 6150-01-247-4779. The DRAFT lists the Drawing # 13226E7023-1 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4779
16Page 14 / Section B / Item 0016NSN# incorrectThe NSN # for Cable Assembly GRP S/F, 40 Amp/Phase, 50-ft is 6150-01-247-4781. The DRAFT lists the Drawing # 13226E7023-2 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4781
17Page 15 / Section B / Item 0017Duplicate Entry?The NSN detailed for Item 0017 is the Drawing # that is associated with the M46 Illunination System, Item 0004. Is this a duplicate entry? Please clarify.Item 0017 is a duplicate entry, removed from IFB
18Page 15 / Section B / Item 001860Amp Cable Required?Both M60 Electrical Distribution System, and M60 Electrical Distribution Assembly are not among the top-level items being solicited, yet this 60Amp cable assembly is required? Please confirm.60A cable not required for this procurement
19Page 15 / Section B / Item 0018NSN# incorrectThe NSN # for Cable Assembly GRP S/F, 60 Amp, 100-ft is 6150-01-247-4793. The DRAFT lists the Drawing # 13226E7022-1 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4793, - Cable is not required for this procurement
20Page 16 / Section B / Item 001960Amp Cable Required?Both M60 Electrical Distribution System, and M60 Electrical Distribution Assembly are not among the top-level items being solicited, yet this 60Amp cable assembly is required? Please confirm.60A cable not required for this procurement
21Page 16 / Section B / Item 0020NSN# incorrectThe NSN # for Cable Assembly GRP E, 20 Amp, 50-ft is 6150-01-256-3643. The DRAFT lists the Drawing # 13226E7032-1 as the NSN. Please clarify.Confirmed: NSN is 6150-01-256-3643
22Page 17 / Section B / Item 0021NSN# incorrectThe NSN # for Cable Assembly GRP E, 20 Amp, 25-ft is 6150-01-250-0044. The DRAFT lists the Drawing # 13226E7032-2 as the NSN. Please clarify.Confirmed: NSN is 6150-01-250-0044
23Page 18 / Section B / Item 0022NSN# incorrectThe NSN # for Cable Assembly, In-line GFCI is 6150-01-598-9748. The DRAFT lists the Drawing # 09-4103 as the NSN. Please clarify.Confirmed: NSN is 6150-01-598-9748
24Page 18 / Section B / Item 0023NSN# incorrect; Typo?The NSN # for Branch Circuit Trunk Assembly is 6150-01-251-9124. The DRAFT lists the Drawing # 13226E7307 as the NSN. If the Drawing # is intended, the last number appears to have been entered incorrectly. The drawing number is 13226E7034. Please clarify.Correct NSN is 9150-01-247-4783, DWG# is 13226E7037
25Page 19 / Section B / Item 0024NSN# incorrectThe NSN # for Receptacle Group, 2 Duplex Box is 6150-01-251-9125. The DRAFT lists the Drawing #13226E7040 as the NSN. Please clarify.Confirmed: NSN is 6150-01-251-9125
26Page 19 / Section B / Item 0025NSN# incorrectThe NSN # for Light, Utility is 6230-01-485-6375. The DRAFT lists the Drawing #13230E7018 as the NSN. Please clarify.Confirmed: NSN is 6230-01-485-6375
27Page 20 / Section B / Item 0026NSN# incorrect;
Drawing # doesn't match descriptionThe NSN # for Double Strap, Cable Carrier Assembly is 6150-01-596-0428. The DRAFT lists the Drawing #13227E5825 as the NSN. NOTE: Drawing #13227E5825 is belongs to the Single Strap, Cable Carrier Assembly. 13227E5821 is the Drawing number for the Double Strap, Cable Carrier Assembly. Perhaps item 0026 is intended to be the Single Strap, Cable Carrier Assembly (NSN# 4340-01-256-6299)? Please clarify.Correct Commodity name for Item 0026 should be "Single Strap Cable Assembly".

Correct NSN for Item 0026 should be "4340-01-256-6299"

28Page 21 / Section B / Item 0027No NSN # listed; duplicate descriptionItem 0027 is described as Double Strap, Cable Carrier Assembly. This is the same description as Item 0026 which looks like it should have been described as "Single Strap". The NSN for the Double Strap, Cable Carrier Assembly is 6150-01-596-0428; and the Drawing # is 13227E5821.NSN for Item 0027 is missing and should be "5975-01-596-0428"
29Page 21 / Section B / Item 0027NSN# incorrectThe NSN # for Strap is 5340-01-250-0045. The DRAFT lists the Drawing #13226E7044 as the NSN. Please clarify.Confirmed: NSN is 5340-01-250-0045
30Page 22 / Section B / Item 'N/A'Missing Item?Reference #s 18 and 20 above which are 60Amp cable assemblies. If these items are indeed required, wouldn't Cable Assembly, 60 kW, B Unit, W19 be required as well? NSN# 6150-01-440-5706; Drawing # 13229E5741. Please clarify.This Cable NSN: 6150-01-440-5706 is not required for this procurement.
31Page 28 / Section B / Item 1005NSN# incorrectThe NSN # for M200 Electrical Feeder Center Assebmly is 6150-01-598-5455. The DRAFT lists the Drawing # 13229E6300 as the NSN. Please clarify.Confirmed: NSN is 6150-01-598-5455
32Page 29 / Section B / Item 1006NSN# incorrectThe NSN # for M100 Electrical Feeder Center Assebmly is 6150-01-598-5282. The DRAFT lists the Drawing # 13229E6325 as the NSN. Please clarify.Confirmed: NSN is 6150-01-598-5282
33Page 30 / Section B / Item 1007NSN# incorrectThe NSN # for M40 Electrical Distribution Center Assebmly is 6150-01-598-4796. The DRAFT lists the Drawing # 13229E6345 as the NSN. Please clarify.Confirmed: NSN is 6150-01-598-4796
34Page 30 / Section B / Item 0008NSN# incorrectThe NSN # for M46 Container, Storage, Utility is 8145-01-568-4834. The DRAFT lists the Drawing # 13229E6362 as the NSN. Please clarify.Confirmed: NSN is 8145-01-568-4834
35Page 31 / Section B / Item 1009NSN# incorrectThe NSN # for Cable Assembly GRP PC, 200 Amp/Phase is 6150-01-247-4768. The DRAFT lists the Drawing # 13226E7021 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4768
36Page 31 / Section B / Item 1010NSN# incorrectThe NSN # for Cable Assembly GRP PC, 100 Amp/Phase is 6150-01-265-6300. The DRAFT lists the Drawing # 13226E7020 as the NSN. Please clarify.Correct NSN is 6150-01-256-6300
37Page 32 / Section B / Item 1011NSN# incorrectThe NSN # for Cable Assembly GRP PC, 40 Amp/Phase is 6150-01-265-6301. The DRAFT lists the Drawing # 13226E7019 as the NSN. Please clarify.Correct NSN is 6150-01-256-6301
38Page 32 / Section B / Item 101260Amp Cable Required?Both M60 Electrical Distribution System, and M60 Electrical Distribution Assembly are not among the top-level items being solicited, yet this 60Amp cable assembly is required? Please confirm.This Cable NSN: 6150-01-247-4778 is not required for this procurement.
39Page 32 / Section B / Item 1012NSN# incorrectThe NSN # for Cable Assembly GRP PC, 60 Amp/Phase is 6150-01-247-4778. The DRAFT lists the Drawing # 13226E7018 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4778, -Cable is not required for this procurement
40Page 33 / Section B / Item 1013NSN# incorrectThe NSN # for Cable Assembly GRP S/F, 200 Amp/Phase, 25-ft is 6150-01-247-4782. The DRAFT lists the Drawing # 13226E7025 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4782
41Page 34 / Section B / Item 1014NSN# incorrectThe NSN # for Cable Assembly GRP S/F, 100 Amp/Phase, 50-ft is 6150-01-256-6304. The DRAFT lists the Drawing # 13226E7024 as the NSN. Please clarify.Confirmed: NSN is 6150-01-256-6304
42Page 34 / Section B / Item 1015NSN# incorrectThe NSN # for Cable Assembly GRP S/F, 40 Amp/Phase, 100-ft is 6150-01-247-4779. The DRAFT lists the Drawing # 13226E7023-1 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4779
43Page 35 / Section B / Item 1016NSN# incorrectThe NSN # for Cable Assembly GRP S/F, 40 Amp/Phase, 50-ft is 6150-01-247-4781. The DRAFT lists the Drawing # 13226E7023-2 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4781
44Page 35 / Section B / Item 1017Duplicate Entry?The NSN detailed for Item 1017 is the Drawing # that is associated with the M46 Illunination System, Item 0004. Is this a duplicate entry? Please clarify.Item 0017 is a duplicate entry, removed from IFB.
45Page 36 / Section B / Item 101860Amp Cable Required?Both M60 Electrical Distribution System, and M60 Electrical Distribution Assembly are not among the top-level items being solicited, yet this 60Amp cable assembly is required? Please confirm.60A cable not required for this procurement
46Page 36 / Section B / Item 1018NSN# incorrectThe NSN # for Cable Assembly GRP S/F, 60 Amp, 100-ft is 6150-01-247-4793. The DRAFT lists the Drawing # 13226E7022-1 as the NSN. Please clarify.Confirmed: NSN is 6150-01-247-4793, -Cable is not required for this procurement
47Page 37 / Section B / Item 101960Amp Cable Required?Both M60 Electrical Distribution System, and M60 Electrical Distribution Assembly are not among the top-level items being solicited, yet this 60Amp cable assembly is required? Please confirm.60A cable not required for this procurement
48Page 37 / Section B / Item 1020NSN# incorrectThe NSN # for Cable Assembly GRP E, 20 Amp, 50-ft is 6150-01-256-3643. The DRAFT lists the Drawing # 13226E7032-1 as the NSN. Please clarify.Correct NSN is 6150-01-250-3643
49Page 38 / Section B / Item 1021NSN# incorrectThe NSN # for Cable Assembly GRP E, 20 Amp, 25-ft is 6150-01-250-0044. The DRAFT lists the Drawing # 13226E7032-2 as the NSN. Please clarify.Confirmed: NSN is 6150-01-250-0044
50Page 38 / Section B / Item 1022NSN# incorrectThe NSN # for Cable Assembly, In-line GFCI is 6150-01-598-9748. The DRAFT lists the Drawing # 09-4103 as the NSN. Please clarify.Confirmed: NSN is 6150-01-598-9748
51Page 39 / Section B / Item 1023NSN# incorrect; Typo?The NSN # for Branch Circuit Trunk Assembly is 6150-01-251-9124. The DRAFT lists the Drawing # 13226E7307 as the NSN. If the Drawing # is intended, the last number appears to have been entered incorrectly. The drawing number is 13226E7034. Please clarify.Correct NSN is 9150-01-247-4783, DWG# is 13226E7037
52Page 39 / Section B / Item 1024NSN# incorrectThe NSN # for Receptacle Group, 2 Duplex Box is 6150-01-251-9125. The DRAFT lists the Drawing #13226E7040 as the NSN. Please clarify.Confirmed: NSN is 6150-01-251-9125
53Page 40 / Section B / Item 1025NSN# incorrectThe NSN # for Light, Utility is 6230-01-485-6375. The DRAFT lists the Drawing #13230E7018 as the NSN. Please clarify.Confirmed: NSN is 6230-01-485-6375
54Page 41 / Section B / Item1026NSN# incorrect;
Drawing # doesn't match descriptionThe NSN # for Double Strap, Cable Carrier Assembly is 6150-01-596-0428. The DRAFT lists the Drawing #13227E5825 as the NSN. NOTE: Drawing #13227E5825 is belongs to the Single Strap, Cable Carrier Assembly. 13227E5821 is the Drawing number for the Double Strap, Cable Carrier Assembly. Perhaps item 0026 is intended to be the Single Strap, Cable Carrier Assembly (NSN# 4340-01-256-6299)? Please clarify.Correct Commodity name for Item 1026 should be "Single Strap Cable Assembly".

Correct NSN for Item 0026 should be "4340-01-256-6299"

55Page 41 / Section B / Item 1027No NSN # listed; duplicate descriptionItem 0027 is described as Double Strap, Cable Carrier Assembly. This is the same description as Item 0026 which looks like it should have been described as "Single Strap". The NSN for the Double Strap, Cable Carrier Assembly is 6150-01-596-0428; and the Drawing # is 13227E5821.NSN for Item 0027 is missing and should be "5975-01-596-0428"
56Page 42 / Section B / Item 1027NSN# incorrectThe NSN # for Strap is 5340-01-250-0045. The DRAFT lists the Drawing #13226E7044 as the NSN. Please clarify.Confirmed: NSN is 5340-01-250-0045
57Page 22 / Section B / Item 'N/A'Missing Item?See item #s 18, 20, 45, and 47 above which are 60Amp cable assemblies. If these items are indeed required, wouldn't Cable Assembly, 60 kW, B Unit, W19 be required as well? NSN# 6150-01-440-5706; Drawing # 13229E5741. Please clarify.This Cable NSN: 6150-01-440-5706 is not required for this procurement.
58W909MY-25-B-0001IFBCan you please provide an unlocked IFB so the fill-ins can be completed?Price Model (attachment 0002) is locked with fillable areas highlighted in yellow. The IFB is open and editable in PDF.
Section L&M
16 - Section LsubmissionWill a DoD SAFE link be provided for the submission?The government will provide the Request a Drop off with DoD SAFE and instruction in the revised draft IFB.
26 - Section LsubmissionAre 2 electronic versions of each volume required?Please see Section L of the updated IFB. Only one electronic version of each volume is required.
36 - Section LtypoSuggest changing submission title for Volume 1 to "Volume 1 - Technical Proposal"Please see Section L of the updated IFB.
46 - Section Lno volume IIIThere is no suggested title listed or format required for Volume IIIPlease see Section L of the updated IFB.
5GeneralWill the table of contents and summary count against the page count requirementThe Table of Contents and Summary are excluded from the page count. The summary shall be a brief and limited to 5 pages. The summary shall only included information abstracted from the Volume's narrative.
6Solicitation Page 95 Section M.1Tariff ImplicationsThe Government's expressed objective is to determine which bid offers the lowest price. This offeror has worked very hard to negotiate the best pricing possible from material suppliers. Now, several suppliers of high-dollar / cost-driver components have issued statements about the tariffs currently being discussed / imposed by the US Governemnt on foreign sources of component materials. Suppliers are stating if they are unable to fully mitigate the impact of these tariffs, they will be forced to pass on the impact through price adjustments. What will be the Governmnent's response to tariff-related ambiguity and impactful price increases that may follow the bid response date?The Government will add a EPA clause to the IFB to allow for contract price adjustments in the event of changes in the contractor’s established prices. Please see amended IFB.
7Solicitation Page 95; Section M.2.1Section C?This section requries compliance to Section C. The solicitation doesn't include a Section C. Please clarify.Section C refers to Attachment 0001 , the PDISE Statement of Work ( SOW)
SOW
1SOW - Attachment 1Provisioning Requirements StatementRequired PPL, EDFP, TMs, MAC and RPSTL but there is no pricing line. Are these already developed and not required?As the systems in question are fully matured, the development of provisioning material, including the Provisioning Parts List (PPL), Engineering Data For Provisioning (EDFP), Technical Manuals (TMs), Maintenance Allocation Chart (MAC), and Repair Parts and Special Tools List (RPSTL), is not required at this stage. These documents and materials have already been developed during prior phases of the program, ensuring that they meet all necessary specifications and requirements.

Attachment 1, which is included with this response, provides reference documentation to confirm the completion of these items. Since the systems are fully mature, no additional provisioning or material development is necessary, and these items are considered finalized.

2SOW 3.3FAWhere will the FA be delivered if testing is the responsibility of the contractor?The location for the delivery and testing of the FA (First Article) units will be at the contractor’s discretion, based on their internal testing and quality assurance processes. The contractor is responsible for ensuring that the FA units meet all the operational and functional requirements outlined in the Statement of Work (SOW) and in compliance with the relevant standards such as MIL-DTL-53126.
3SOW 3.5.1CIVRWill the CIVR be completed before testing begins?No, the CIVR (Configuration Item Verification Review) will not be conducted before testing. The CIVR will take place after all testing has been successfully completed and passed. The purpose of the CIVR is to confirm that the final product adheres to the technical specifications and requirements outlined in the Technical Data Package (TDP) and the Statement of Work (SOW).

The CIVR process ensures that the product has been manufactured, assembled, and tested in accordance with the defined standards, and that all design and performance criteria are met. It acts as a final verification step, validating the alignment between the built product and the documentation provided in the TDP and SOW. This review will include a detailed inspection of the product's quality, compliance with regulatory standards, and confirmation that all necessary testing and validation activities have been completed per the contractual requirements.

4GeneralPlease provide the most current TDP for all linesThe government will provide via SAFE.apps.mil. The TDP with the current drawings will be provided to vendors upon request. Request shall be sent to the KO, Ms. Jessica Hawkins and Ms. Mary Suda at jessica.l.hawkins27.civ@army.mil and mary.a.suda.civ@army.mil
1P8 / 3.3First ArticleThe first sentence states that fabrication and testing, among other activities, should be completed within 12 months. The third sentence specifies that the FAT units must be delivered no later than 180 days. Does this mean the Government intends for the FAT units to be built within 6 months (180 days) and then tested internally for an additional 6 months? This would result in the FAT phase being completed within 12 months.Yes, that is correct. The FA (First Article) period is designed to span 12 months in total, with a timeline for fabrication, testing, and evaluation. The first 6 months of this 12-month period will be dedicated to the fabrication and production of the FA units. During this phase, the contractor will focus on completing the manufacturing, assembly, and integration of the FAT units in alignment with the technical specifications outlined in the TDP and SOW.

The subsequent 6 months will be allocated for comprehensive testing and evaluation of the FAT units to ensure that the FAT units meet all performance criteria and are fully operational before delivery. The testing period allows for verification of the units’ compliance with contractual and operational requirements, and also provides the opportunity to address any issues or adjustments identified during the testing process.

In summary, the FAT phase will be completed within a 12-month period, with the first 6 months focused on fabrication and the remaining 6 months dedicated to testing and validation.

2P9 / 3.4TDPWe respectfully request access to the technical data package for all configuration items and accessories.The government will provide via SAFE.apps.mil. The TDP with the current drawings will be provided to vendors upon request. Request shall be sent to the KO, Ms. Jessica Hawkins and Ms. Mary Suda at jessica.l.hawkins27.civ@army.mil and mary.a.suda.civ@army.mil
3P13 / 3.9Configuration ManagementSection 3.9 contains a fairly robust configuration management requirement for a build-to-print effort. Why is this the case? Does the government anticipate the need for the generation and submittal of ECPs during the execution of the contract because there are issues with the current baseline? If so, what are the areas of concern within the technical data that will / might require attention?At this time, we do not anticipate any major changes that would necessitate the submission of ECPs. The current baseline design has been thoroughly validated, and the system has proven reliability. However, given the dynamic nature of hardware production and external factors, such as supply chain variability or part obsolescence, there could be minor adjustments or variations needed in the materials or components used.

The robust configuration management (CM) requirements in Section 3.9 are in place to ensure that, even for a build-to-print effort, any necessary changes or adjustments can be efficiently managed throughout the contract lifecycle. While the design is fully matured, with over 30,000 units produced in the past, it is important to maintain a structured CM process to address any unforeseen issues that might arise during production or testing. This includes the ability to manage Engineering Change Proposals (ECPs) if required.

Areas of concern that might trigger minor changes include:

Supply Chain Disruptions: Unexpected delays or shortages in components could require substitution or re-sourcing, potentially leading to variations in part specifications or suppliers.

Quality Variations: Even with established parts and materials, quality issues (e.g., deviations in batch production or manufacturing tolerances) may necessitate slight adjustments to ensure system integrity and compliance.

Component Obsolescence: If a component becomes obsolete or is no longer available, a suitable replacement might be needed, which could require minor design updates or configuration adjustments.

In all cases, any changes would be managed through the established CM process, with full documentation, review, and approval as necessary. The goal is to ensure that all modifications, however minor, are tracked and controlled to maintain the integrity of the product and compliance with the contractual requirements.

TDP
1excel file M40 PDISE TDPL, Item No. 56TDPReview of the TDP, we found a discrepancy in the M40 directory. In the excel file M40 PDISE TDPL, Item No. 56, Drawing Number 13229E6353, lists Revision M. However, in the PDF sub-directory of M40, the drawing file 13229E6353P001.pdf is Drawing No. 13229E6353, Revision P. Could you confirm the correct revision of Drawing No. 13229E6353 that we should be using?Revision P is the correct revision of Drawing No. 13229E6353, and it should be used. Please proceed with using Revision P for this drawing as it is the most up to date.
2Drawing 13226E7023 Cable AssembleTDPDrawing 13226E7023 Cable Assemble, Grp S/F, 40/60 Amp/Phase specifies Connectors FN 1 – MS90556C32405P and FN 2 – MS90557C32405S. Please provide clarification, should the connector specifications be FN 1 – MS90556C32413P and FN 2 – MS90557C32413S.Concur. In accordance with MS90565, FN 1 should read MS90556C32413P, and FN 2 should read MS90557C32413S.
3Drawing 13226E7019 Cable AssembleTDPDrawing 13226E7019 Cable Assembly, Grp PC, 40/60 Amp/Phase specifies cable FN 2 – M3432-04HDF(4/4-4/8R)1290. Please provide clarification, SHOULD the cable specification be FN 3 – M3432-04HDF(4/1-4/8R)1620.
Concur. In accordance with MS90565, FN 2 should read M3432-04HDF(4/4-4/12R)1290.
4Drawing 13226E7024 Cable AssemblyTDPDrawing 13226E7024 Cable Assembly, Grp S/F, 100 Amp/Phase specifies cable FN 3 – M3432-04HDF(4/1-3/8R)1620. Please provide clarification, SHOULD the cable specification be FN 3 – M3432-04HDF(4/1-4/8R)1620.Concur. In accordance with MS14055, FN 3 should read M3432-04HDF(4/1-4/8R)1620.
5Drawing numbers 13230E7019 Packaging, PDISE M200 A/P, 13230E7020 Packaging, PDISE M100 A/P, and 13230E7021 Packaging, PDISE M40/M60 A/TDPDrawing numbers 13230E7019 Packaging, PDISE M200 A/P, 13230E7020 Packaging, PDISE M100 A/P, and 13230E7021 Packaging, PDISE M40/M60 A/P specify cleat lumber in accordance with ASTM D 6199, Class 2, Group III. After review, crate supplier has identified that the lumber species specified in Group III have very limited supply and are prohibitively expensive. Supplier recommended Group II lumber species as a replacement as it is the industry standard for this type of shipping container IAW government specs. Please clarify if the more cost-effective Group II lumber species would be an acceptable alternative.We will maintain the current lumber specification at this time. Any changes require an impact assessment to ensure compliance and quality standards.
6excel file M40 PDISE TDPLTDP13214E8326 TDP Stated Revision "N", drawing supplied is Revision "M." 13226E7044 TDP Stated Revision "D" dreawing supplied is Revision "C"For 13214E8326 use "M"

For 13226E7044 use "C" 7 M46 TDP TDP 13226E7041 TDP Stated Revision "D", drawing supplied is Revision "C." 13226E7042 TDP Stated Revision "B", drawing supplied is Revision "A." 13226E7044 TDP Stated Revision "D", drawing supplied is Revision "C." For 13226E7041 use "C" For 13226E7042 use "A" For 13226E7044 use "C"

8M100 TDPTDP13214E8326 TDP Stated Revision "N", drawing supplied is Revision "M."For 13214E8326 use "M"
9M200 TDPTDP13214E8326 TDP Stated Revision "N", drawing supplied is Revision "M."For 13214E8326 use "M"
10Drawing 13227E5812TDPDrawing 13227E5812 is missing pages 2 & 3 of the document.

Page 1 only shows the -1, -2, -3

We need out to the -9.We have the complete DWG 13227E5812 with all pages and will send out to all interested vendor
11MIL-DTL-53126 Section 4.7.1MIL-STD-705 Call-out?MIL-STD-705 is a generator specification. PDISE is not a generator. How does this specification (i.e.. TM512.2d / 710.1d) apply? Please clarify.MIL-STD-705 is the standard for Mobile Electric Power Systems which consists of Mobile Electic Power Distribution Systems.

For TM 512.2d please reference the portion which applies to testing PDISE circuit breaker for Overload Current and follow 3.3.6 and 3.3.8 of SOW for actual testing requirements.

For TM 710.1d please reference the portion which applies to testing circuit breaker and follow instruction to test PDISE circuit breaker operation (rated load) at 135°F (57°C) for 2 hours (continuously).

12 TDP Incomplete Drawing Drawing # 13230E7022 Rev F - Page 2 was not provided. Consequently, "dash number" details are not available. We have the complete Drawing 13230E7022 Rev F - inclusive of page 2. On 03 MAR 25 it was was sent to any vendor that had previously requested the TDPs via DoDsafe and is available on SAM.gov in response to industry questions.