| ROCK ISLAND ARSENAL | DATE: 1-May-18 | |
| PROJECT: 18-1-01 | TIMELINE OF DELIVERIES | |
| ASRS REBUILD |
The following timeline is based upon the contract award date and the number of calendar days between events. Time allocations are maximums for each stage. It is acceptable to complete a stage in fewer days than shown on the timeline and move on to the next stage. Note: Early delivery of equipment is only allowable with RIA-JMTC prior approval with sufficient time to allow preparation of the planned equipment location.
The timeline for this project is as follows:
· Installation Documents Equipment Delivery minus 60 days
· MSDS Sheets Delivered Equipment Delivery minus 30 days
IT/ Software Portion
| · Contract Award | Contract Award |
| · Software/ IT Approval | Contract Award + 308 days |
| · Phase 2 Equipment Delivery | Contract Award + 308 days |
| · Phase 2 Start of Work | Phase 2 Equipment Delivery + 7 days |
| · Phase 2 Completion/ Software Implementation | Phase 2 Start of Work + 56 days |
Mechanical/Rebuild/Install Portion
| · Contract Award | Contract Award |
| · Phase 1 Equipment Delivery | Contract Award + 77-days |
| · Phase 1 Start of Work | Phase 1 Equipment Delivery + 0-days |
| · Phase 1 Completion | Phase 1 Start of Work + 21-days |
| · Phase 3 Start of Equipment Delivery | Phase 1 Completion -7-days |
| · Phase 3 Equipment Delivery | Phase 1 Start of Equipment Delivery + 7-days |
| · Phase 3 Start of Work | Phase 3 Equipment Delivery + 0-days |
| · Phase 3 Completion | Phase 3 Start of Work + 21-days |
| · Phase 3 Equipment Testing/ Runtime | Phase 3 Completion + 28-days |
| · Phase 4 Start of Equipment Delivery | Phase 3 Equipment Testing/ Runtime -7-days |
| · Phase 4 Equipment Delivery | Phase 3 Start of Equipment Delivery + 7-days |
| · Phase 4 Start of Work | Phase 4 Equipment Delivery + 0-days |
| · Phase 4 Completion | Phase 4 Start of Work + 21-days |
| · Phase 4 Equipment Testing/ Runtime | Phase 4 Completion + 28-days |
| · Phase 5 Start of Equipment Delivery | Phase 4 Equipment Testing/ Runtime – 7-days |
| · Phase 5 Equipment Delivery | Phase 5 Start of Equipment Delivery +7-days |
| · Phase 5 Start of Work | Phase 5 Equipment Delivery + 0-days |
| · Phase 5 Completion | Phase 5 Start of Work + 21-days |
| · Phase 5 Equipment Testing/ Runtime | Phase 5 Completion + 28-days |
| · Phase 6 Start of Equipment Delivery | Phase 5 Equipment Testing/ Runtime – 7-days |
| · Phase 6 Equipment Delivery | Phase 6 Start of Equipment Delivery +7 Days |
| · Phase 6 Start of Work | Phase 6 Equipment Delivery + 0-days |
| · Phase 6 Completion | Phase 6 Start of Work + 21-days |
| · Phase 6 Equipment Testing/ Runtime | Phase 6 Completion + 28-days |
| · Phase 7 Start of Equipment Delivery | Phase 6 Equipment Testing/ Runtime – 7-days |
| · Phase 7 Equipment Delivery | Phase 7 Start of Equipment Delivery +7-days |
| · Phase 7 Start of Work | Phase 7 Equipment Delivery + 0-days |
| · Phase 7 Completion | Phase 7 Start of Work + 21-days |
| · Phase 7 Equipment Testing/ Runtime | Phase 7 Completion + 28-days |
| · Phase 8 Start of Equipment Delivery | Phase 7 Equipment Testing/ Runtime – 7-days |
| · Phase 8 Equipment Delivery | Phase 8 Start of Equipment Delivery +7-days |
| · Phase 8 Start of Work | Phase 8 Equipment Delivery + 0-days |
| · Phase 8 Completion | Phase 8 Start of Work + 7-days |
| · System Testing/ Runtime | Phase 8 Completion + 28-days |
| · Final Acceptance | System Testing/ Runtime + 7-days |
Total Maximum Time from Award to Acceptance Contract Award + 385-days
· The objective of breaking out the phases like this is to limit downtime associated with this project. While one aisle is being upgraded, the other aisles shall remain functional so that RIA personnel can continue with their day to day work. In addition to compliance with the RIPD, RIA asks that the vendor makes a compliance statement with the Timeline of Deliveries. Equipment Testing/Runtime sequences are allotted so that while the upgraded aisle is being ran, RIA personnel can replace any parts that were removed from that aisle prior to work starting, as well as start pulling material/parts from the next aisle to be worked on. This is to ensure that there will be no work stoppages due to unavailable parts/material during the duration of aisle downtime. RIA understands that whole system “restarts/shut downs” may need to occur during completion of this project, however these should be only during necessary circumstances and kept to a minimum number of occurances.