Attachment_0002_-_RIPD_E4000-18-1-01_-_Timeline_of_Deliveries_-_(Rev.2)_-_5Jun19__.docx

DOCX document 20 KB Posted

Attached to
Automated Storage and Retrieval Systems (ASRS) System Upgrade
Solicitation number
W9098S19T0066
Issued by

About this file

Attachment 0002 - RIPD E4000-18-1-01 - Timeline of Deliveries - (Rev.2) - 5Jun19 _

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROCK ISLAND ARSENALDATE: 1-May-18
PROJECT: 18-1-01TIMELINE OF DELIVERIES
ASRS REBUILD

The following timeline is based upon the contract award date and the number of calendar days between events. Time allocations are maximums for each stage. It is acceptable to complete a stage in fewer days than shown on the timeline and move on to the next stage. Note: Early delivery of equipment is only allowable with RIA-JMTC prior approval with sufficient time to allow preparation of the planned equipment location.

The timeline for this project is as follows:

· Installation Documents Equipment Delivery minus 60 days

· MSDS Sheets Delivered Equipment Delivery minus 30 days

IT/ Software Portion

· Contract AwardContract Award
· Software/ IT ApprovalContract Award + 308 days
· Phase 2 Equipment DeliveryContract Award + 308 days
· Phase 2 Start of WorkPhase 2 Equipment Delivery + 7 days
· Phase 2 Completion/ Software ImplementationPhase 2 Start of Work + 56 days

Mechanical/Rebuild/Install Portion

· Contract AwardContract Award
· Phase 1 Equipment DeliveryContract Award + 77-days
· Phase 1 Start of WorkPhase 1 Equipment Delivery + 0-days
· Phase 1 CompletionPhase 1 Start of Work + 21-days
· Phase 3 Start of Equipment DeliveryPhase 1 Completion -7-days
· Phase 3 Equipment DeliveryPhase 1 Start of Equipment Delivery + 7-days
· Phase 3 Start of WorkPhase 3 Equipment Delivery + 0-days
· Phase 3 CompletionPhase 3 Start of Work + 21-days
· Phase 3 Equipment Testing/ RuntimePhase 3 Completion + 28-days
· Phase 4 Start of Equipment DeliveryPhase 3 Equipment Testing/ Runtime -7-days
· Phase 4 Equipment DeliveryPhase 3 Start of Equipment Delivery + 7-days
· Phase 4 Start of WorkPhase 4 Equipment Delivery + 0-days
· Phase 4 CompletionPhase 4 Start of Work + 21-days
· Phase 4 Equipment Testing/ RuntimePhase 4 Completion + 28-days
· Phase 5 Start of Equipment DeliveryPhase 4 Equipment Testing/ Runtime – 7-days
· Phase 5 Equipment DeliveryPhase 5 Start of Equipment Delivery +7-days
· Phase 5 Start of WorkPhase 5 Equipment Delivery + 0-days
· Phase 5 CompletionPhase 5 Start of Work + 21-days
· Phase 5 Equipment Testing/ RuntimePhase 5 Completion + 28-days
· Phase 6 Start of Equipment DeliveryPhase 5 Equipment Testing/ Runtime – 7-days
· Phase 6 Equipment DeliveryPhase 6 Start of Equipment Delivery +7 Days
· Phase 6 Start of WorkPhase 6 Equipment Delivery + 0-days
· Phase 6 CompletionPhase 6 Start of Work + 21-days
· Phase 6 Equipment Testing/ RuntimePhase 6 Completion + 28-days
· Phase 7 Start of Equipment DeliveryPhase 6 Equipment Testing/ Runtime – 7-days
· Phase 7 Equipment DeliveryPhase 7 Start of Equipment Delivery +7-days
· Phase 7 Start of WorkPhase 7 Equipment Delivery + 0-days
· Phase 7 CompletionPhase 7 Start of Work + 21-days
· Phase 7 Equipment Testing/ RuntimePhase 7 Completion + 28-days
· Phase 8 Start of Equipment DeliveryPhase 7 Equipment Testing/ Runtime – 7-days
· Phase 8 Equipment DeliveryPhase 8 Start of Equipment Delivery +7-days
· Phase 8 Start of WorkPhase 8 Equipment Delivery + 0-days
· Phase 8 CompletionPhase 8 Start of Work + 7-days
· System Testing/ RuntimePhase 8 Completion + 28-days
· Final AcceptanceSystem Testing/ Runtime + 7-days

Total Maximum Time from Award to Acceptance Contract Award + 385-days

· The objective of breaking out the phases like this is to limit downtime associated with this project. While one aisle is being upgraded, the other aisles shall remain functional so that RIA personnel can continue with their day to day work. In addition to compliance with the RIPD, RIA asks that the vendor makes a compliance statement with the Timeline of Deliveries. Equipment Testing/Runtime sequences are allotted so that while the upgraded aisle is being ran, RIA personnel can replace any parts that were removed from that aisle prior to work starting, as well as start pulling material/parts from the next aisle to be worked on. This is to ensure that there will be no work stoppages due to unavailable parts/material during the duration of aisle downtime. RIA understands that whole system “restarts/shut downs” may need to occur during completion of this project, however these should be only during necessary circumstances and kept to a minimum number of occurances.