Attachment 0010 Formal RFP Questions_Answers Form.xlsx

XLSX spreadsheet 21 KB Posted

Attached to
ACC-RSA Logistic Support Facility Services (LSFS-1)
Solicitation number
W58RGZ-23-R-0036
Issued by

View the file

Other files

File Type Posted
Attachment 0002 LSFS-1 Cost Price Template.xlsx XLSX spreadsheet
Attachment 0016 Wage Determination No. 2015-4603 (Rev 22).pdf PDF
Attachment 0005 LSFS-1 Labor Category Requirement.xlsx XLSX spreadsheet
W58RGZ23R0036-0002.pdf PDF
Attachment 0006 Section L- Instructions_ Conditions and Notices to Offerors.pdf PDF
W58RGZ23R0036_AMD 0001.pdf PDF
Attachment 0013 Sample Order 2-UH60A FMS PMI and Unique Cockpit.pdf PDF
Attachment 0012 Sample Order 1.pdf PDF
Attachment 0006 Section L- Instructions_ Conditions and Notices to Offerors.pdf PDF
Attachment 0003 DD254 Security Classification (2).pdf PDF
Attachment 0004 Performance Work Statement.pdf PDF
Attachment 0009 Past Performance Questionnaire.docx DOCX document
Attachment 0013 Sample Order 2-UH60A FMS PMI and Unique Cockpit.pdf PDF
W58RGZ23R0036_Issued 6 Oct 2022.pdf PDF
Exhibit A Contract Data Requirements List (CDRL).pdf PDF
Atttachment 0015 Pre-Award Survey of Prospective Contractor Accounting System Checklist.pdf PDF
Attachment 0008 Section C - Description_Specification.pdf PDF
Attachment 0002 LSFS-1 Cost Price Template.xlsx XLSX spreadsheet
Attachment 0016 Wage Determination No. 2015-4603 (Rev 22).pdf PDF
Attachment 0013 Sample Order 2.pdf PDF
Attachment 0012 Sample Order 1.pdf PDF
Attachment 0004 Performance Work Statement.pdf PDF
Attachment 0006 Section L- Instructions_ Conditions and Notices to Offerors.pdf PDF
Attachment 0014 Cage Code and Cognizant DCMA_DCAA Info.xlsx XLSX spreadsheet
Attachment 0001 Document Summary List (DSL).pdf PDF
Attachment 0005 LSFS-1 Labor Category Requirement.xlsx XLSX spreadsheet
Attachment 0011 LSFMA Performance Cost Report.pdf PDF
Attachment 0003 DD254 Security Classification.pdf PDF
Attachment 0009 Past Performance Questionnaire.docx DOCX document
Attachment 0007 Section M-Evaluation Factors for Award.pdf PDF
Attachment 0010 Formal RFP Questions_Answers Form.xlsx XLSX spreadsheet
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

W58RGZ-23-R-0036
CONSOLIDATED RFP COMMENT / QUESTION FORM
Logistics Support Facility
Question #RFP AreaSOW Page ReferenceSOW Paragraph ReferenceAdditional Cross ReferenceDiscussionQuestionGovernment's Response
1Section C157.19PWSThe Contractor shall require access to foreign Government information.Please explain. Will any special certifications be required? What type of information?Paragraph deleted; currently revised to reflect as "RESERVED
2Section L1L.1.2.1Content RequirementTable of Contents and figures/illustrations pages count in the total page count. Indices, acronym lists, and definitions do not count in the total page count.Why are TOCs included in the page count? Can be very extensive when including full dilenation and graphics/illustrations - roughly 5 pages or more. Is it possible to only drill-down to the 3rd level to save space (e.g., C.1.1)Table of Contents and figures/illustrations page count removed from total page count. Atth 0006 updated
3Section L5L.3.1.1.1Corporate CapabilityCorporate Capability: Corporate Capability areas include: (i) Quality and Safety Management Systems, (ii) Facility and Equipment Requirements, (iii) Human Resource Plan.Do major subs have to provide?The Government will look to the prime contractor for fulfilling this requirement
4Section L11L.3.2.7.1.1Escalation RateDirect labor rates shall identify the baseline (takeoff point) plus projected escalation for each year.Is a rate provided by USG to ensure proposals are being compared equally? What is the rate?No. Offerors shall provide adequate data and rationale to support the realism of all cost elements proposed in support of CPFF CLIN(s) to include escalation factors.
5Section C46.3.3Flight Safety Parts CC - NONCONFORMING CRITICAL CHARACTERISTICSNon-conformances of CCs shall not be dispositioned "use as is" or "repair" through contractor action, rework to print is acceptable.Explain statement.Non-Conformaning critical characteristics may be reworked to print.
6Section C66.6.1Flight Safety Parts CC - CalibrationThe supplier's M&TE shall be made available for use by the Government, as neededWhat is meant by "as needed?" How often does the USG anticipate the use of supplier M&TE to ensure operations are not disrupted? Does this apply to 2nd-tier subs/vendors as well?During the Government's surveillance of Flight Safety Parts - Critical Characteristics (CC) the Government would use the same M&TE the contractor used to validate the CC. The Government will look to the prime contractor for fulfilling this requirement
7Section LL.3.3For Past Performance, Section L.3.3 states the prime offeror can submit up to three contracts and each major subcontractor can submit no more than one contract.Are offerors/subcontractors allowed to use an IDIQ contract as ONE Past Performance instance, yet within that narrative be allowed to specifically cite/discuss multiple individual Delivery Orders performed under that IDIQ?Offerors can submit a total of three stand-alone contracts and/or individual task orders in their proposals.
8Section LL.3.3, L.3.3.1.1, L.3.3.1.2, M.3.3.2L.3.3 states that offerors shall submit Past Performance contracts "along with the record of performance." Section M (M.3.3.2) refers to "the offeror’s record of performance ... as it relates to all solicitation requirements, including cost, schedule, performance and management of subcontractors.”Can the Government please clarify what is to be submitted by offerors as each contract’s “record of performance?” Is this simply referring to the collective information required: Contract Description including cost and schedule data (L.3.3.1.1), Performance Narrative including schedule or performance deviations and warranty returns (L.3.3.1.2), and Past Performance Questionnaire (L.3.3.2)?Paragraph was written IAW with new provisions of FY 21 NDAA and remain as written.
9Section LL.3.3, L.3.3.1.1, L.3.3.1.2, M.3.3.2L.3.3 states that offerors shall submit Past Performance contracts "along with the record of performance." Section M (M.3.3.2) refers to "the offeror’s record of performance ... as it relates to all solicitation requirements, including cost, schedule, performance and management of subcontractors.”Also: Section L does not require information about management of subcontractors (unless implied as part of L.3.3.1.2), but Section M includes this as part of the “record of performance” (M.3.3.2). Can the Government please specify what set of information constitutes the “record of performance” which offerors must submit with each contract?Pargraph was written IAW with new provisions of FY 21 NDAA and remain as written.
10Section LL.3.2.7.2.5Some of the requirements in Section L.3.2.7.2.5 on the bottom of page 13 appear to be illegible or missing.Will the Government please issue the complete requirement for Section L.3.2.7.2.5?Attachment 0006 updated
11Section CPWS 7.19The title "Foreign Government Information” was replaced with "Reserved"; however, there is still a requirement stated.Should the title of this still be "Foreign Government Information", or should the requirement itself be removed and the title remain as "Reserved"?Removed and remain RESERVED; PWS updated
12Section H14OCI States "If you are a prime contractor / Subcontractor on the EXPRESS contract, you are considered to have an OCI with the LSFMA program that will require a mitigation plan that, at a minimum, divests you from working on the EXPRESS contract for any current or future work supporting a particular program office once the program office commences effort generating an LSFMA requirement."This OCI rquirement limits for this opportunity. We suggest removing the AMCOM EXPRESS OCI references.AMCOM EXPRESS OCI references removed; Paragraph updated
13Section H8This solicitation is subject to the Service Contracts labor Standards and has incorporated WD 2015-4603. This solicitation also incorporates FAR Clause 52.222-43 (FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT LABOR STANDARDS--PRICE ADJUSTMENT (MULTIPLE YEAR AND OPTION CONTRACTS) and 52.222-44 (FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT LABOR STANDARDS--PRICE ADJUSTMENT) Section H in regards to labor rates states:
H-8. CONTRACT RATE PRICING Rates (Competitive and Sole Source): The IDIQ Rate Tables of the Attachment 0002- LSFS-1 Cost/Price Template will establish Not- to[1]Exceed (NTE) rates for task orders and will include the following: CPFF base labor rates, FFP base labor rates, Direct Labor Wrap Rates, Material/ODC Wrap Rates, Fee/Profit Rates, Facilities Capital Cost of Money (FCCOM) Rates and Storage Rates. These NTE rates shall be used for all sole source requirements (inclusive of change orders, over and above, etc.) and competitive requirements for the duration of the contract and will be binding rate, not be subject to negotiation. The successful offerors will be permitted to bid lower rates in a manner that best suits their company's needs so long as their proposed rates do not exceed the rates included in their Attachment 0002- LSFS-1 Cost/Price Template submission.How does the government intend on complying with FAR 52.222-43 and FAR 52.222-44 when binding celling rates for out years have been established?FFP labor wage adjustments for SCLS WD applicable labor categories will be made in accordance with FAR 52.222-43/52.222-44.
14Section H8This solicitation is subject to the Service Contracts labor Standards and has incorporated WD 2015-4603. This solicitation also incorporates FAR Clause 52.222-43 (FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT LABOR STANDARDS--PRICE ADJUSTMENT (MULTIPLE YEAR AND OPTION CONTRACTS) and 52.222-44 (FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT LABOR STANDARDS--PRICE ADJUSTMENT) Section H in regards to labor rates states:
H-8. CONTRACT RATE PRICING Rates (Competitive and Sole Source): The IDIQ Rate Tables of the Attachment 0002- LSFS-1 Cost/Price Template will establish Not- to[1]Exceed (NTE) rates for task orders and will include the following: CPFF base labor rates, FFP base labor rates, Direct Labor Wrap Rates, Material/ODC Wrap Rates, Fee/Profit Rates, Facilities Capital Cost of Money (FCCOM) Rates and Storage Rates. These NTE rates shall be used for all sole source requirements (inclusive of change orders, over and above, etc.) and competitive requirements for the duration of the contract and will be binding rate, not be subject to negotiation. The successful offerors will be permitted to bid lower rates in a manner that best suits their company's needs so long as their proposed rates do not exceed the rates included in their Attachment 0002- LSFS-1 Cost/Price Template submission.Will the contractor have an opportunity to revise celling rates in the event a new wage adjustment is incorporated during the time period the ceiling rates already proposed are in effect?FFP labor wage adjustments for SCLS WD applicable labor categories will be made in accordance with FAR 52.222-43/52.222-44.
15Section H8This solicitation is subject to the Service Contracts labor Standards and has incorporated WD 2015-4603. This solicitation also incorporates FAR Clause 52.222-43 (FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT LABOR STANDARDS--PRICE ADJUSTMENT (MULTIPLE YEAR AND OPTION CONTRACTS) and 52.222-44 (FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT LABOR STANDARDS--PRICE ADJUSTMENT) Section H in regards to labor rates states:
H-8. CONTRACT RATE PRICING Rates (Competitive and Sole Source): The IDIQ Rate Tables of the Attachment 0002- LSFS-1 Cost/Price Template will establish Not- to[1]Exceed (NTE) rates for task orders and will include the following: CPFF base labor rates, FFP base labor rates, Direct Labor Wrap Rates, Material/ODC Wrap Rates, Fee/Profit Rates, Facilities Capital Cost of Money (FCCOM) Rates and Storage Rates. These NTE rates shall be used for all sole source requirements (inclusive of change orders, over and above, etc.) and competitive requirements for the duration of the contract and will be binding rate, not be subject to negotiation. The successful offerors will be permitted to bid lower rates in a manner that best suits their company's needs so long as their proposed rates do not exceed the rates included in their Attachment 0002- LSFS-1 Cost/Price Template submission.Does the government intend for the contractor to use an escalation factor in establishing the FFP SCA covered labor categories instead of relying on the price adjustment clause?No. FFP labor wage adjustments for SCLS WD applicable labor categories will be made in accordance with FAR 52.222-43/FAR 52.222-44.
16+A21:U21Section LAtt. 0006 Section L Page 8L.1.2.1, L.3.1.1.2, and L.3.1.1.3Att. 0002L.1.2.1 states, "No price information shall be presented in any part of the past performance or technical proposal. AND L.3.1.1.2 and L.3.1.1.3 state, "A milestone chart, projected spending rate, and estimated man-hours should be included. These requirements contradict each other.Will the Government remove the requirement for a projected spending rate from L.3.1.1.2 and L.3.1.1.3?Requirement for projected spending rate remove; Atth 0006 updated
17Section C, Section LAtt. 0012 PWS page 511.0Section L, Att. 0002Sample Order 1 PWS states, "The contractor shall provide option pricing to complete all above reference requirements for the below periods for complete Contract Years (CY) from award, with no fractionalization for Fiscal years."
Please clarify pricing is NOT required with sample order responses.Pricing is not required for sample order; Sample PWS updated
18Section C, Section LAtt. 0013 PWS page 813.1Section L, Att. 0002Sample Order 2 PWS states, "4.3 For proposal purposes the contractor shall provide a bill of materials (BOM) and pricing for contractor provided consumables. AND 13.1 Options for additional aircraft shall be priced on a range quantity cost basis."Please clarify pricing is NOT required with sample order responses.Pricing is not required for sample order; Sample PWS updated
19Section LAtt. 0006 Section L Page 2L.1.2.1N/AL.1.2.1 states, "Each volume of the proposal shall consist of a Table of Contents, Summary Section, and the Narrative discussion." AND "Table of Contents and figures/illustrations pages count in the total page count."Please remove the Table of Contents and figures/illustrations pages from the total counted pages.Table of Contents and figures/illustrations page count removed from total page count. Atth 0006 updated
20Section LAtt. 0006 Section L Page 2 and Pages 7, 8L.1.2.1, L.3.1.1.2, and L.3.1.1.3N/AL.1.2.1 requires a page limitation on the technical volume (50 pages). L.3.1.1.2 and L.3.1.1.3 Sample Orders 1 and 2 require technical elements such as "detailed estimates of labor by category, detailed estimates of material..."Please allow bill of material, basis of estimate, integrated master schedule to be included as appendices that are not included in the 50 page count for the technical volume.Non Concur. The requirement remains as written.
21Section LAtt. 0002, Tab 4 and Tab 6, Section L.3.2.2 Page 8L.3.2.2N/AAtt. 0006 Section L 3.2.2 states, "It may be necessary for the offeror to revise the number of rows and columns in the LSFS-1 Cost/Price Template to reflect differences or nuances in the offeror’s accounting system and estimating practices."

Att. 0002 Tab 6 Total Proposed does not accommodate the differences and nuances in our accounting system and estimating practices.

In addition to adding columns and rows, we also intend to modify calculations within the following tabs: Tab. 4 Prime Wrap Rate Tables and Tab 6 Total Proposed. These modifications are required to accurately reflect differences and nuances in our accounting system and estimating practices. Please confirm that these types of modifications are acceptable.Modifications to Attachment 0002 LSFS-1 Cost Price Template are allowed in order to accommodate an Offerors accounting and estimating practice (Refer to RFP Section L.3.2.2). The offeror is responsible for ensuring that all calculations within Attachment 0002 LSFS-1 Cost Price Template worksheets are accurate and reflective of the offeror's proposed price.
22Page 5para 4.2SO 2Para 4.2 (Perform Repairs) instructs the contractor to perform required repairs and correct all deficiencies noted during PMI 1/2. Also, the contractor must replace any TBO item which has less than 480 hours remaining.Without knowing what repairs are required per aircraft and which TBO items must be replaced, how much scope (labor hours) should the offerors propose to this requirement per aircraft? There is no definition of what is considered "in scope" and what could be considered "over and above" for this requirement.The PWS allows 'for proposal purposes' 480 hours to correct all write-ups. This includes all man hours for repairs, TBO replacements, etc… 4.2 defines Scope as Correct all deficiencies and perform required repairs noted during the inspection phase of the PMI. Apply required safety and maintenance messages.
23Attachment 0016SCA MappingThe Government has provided comments within the Attachment 0016 Wage Determination that provide mappings to some of the RFP Labor Categories. Is it the Government's intent to have offerors utilize only these SCA LCAT mappings, or are offerors providing their own mappings?Please refer to Attachment 0006 Section L.3.2.7.1.10 for further direction
24Attachment 0002SCA EscalationAre offerors directed to apply escalation for all labor categories, or can some (I.E. SCA) be omitted from the application?The basis of proposed cost elements to include escalation factors applied to CPFF labor wages is at the discretion of the Offeror. Please Note: It is not the Governments intent for FAR 52.222-43 or FAR 52.222-44 as prescribed by FAR 22.1006(c)(1) to be a directive to Offerors in regards to the CPFF CLINs. Please refer to L.3.2.7. for further information.
25Attachment 0005LCAT DescriptionWill the government provide a description/requirements for the "Stress Analyst" Labor Category?Stress Analyst is not a labor category outlined in Attch 5
26Attachment 0006Page CountIn order to provide sufficient detail to cover the robust requirements prescribed in Sections L and M, would the government please exclude the Table of Contents and Lists of Figures, Illustrations, and Tables from page count for Volume II – Factor 1 Technical and Volume IV Factor 3 – Past Performance?Table of Contents and figures/illustrations page count removed from total page count. Atth 0006 updated
27Solicitation A-1, Attachment 0003j) DD254, Security Classification incorporated at Attachment 0003, Section J reflects the security clearance requirement. The need for additional DD Form 254s will be included in the TOs to which they apply.Is Attachment 0003 DD254 Security Classification required at the time of proposal submission? If yes, can the government please provide an updated DD254 to include the correct solicitation numberYes;Pen and change made to reflect new RFP number.
28Attachment 0006, L.3.2.3SF33Please confirm that the SF33 and continuation sheets (with pricing amounts) only go in Volume V - Solicitation, Offer and Award
Documents, and Certifications / Representations and do not need to be included in Volume III - Factor 2 Cost/Price.Please refer to solicitation Section L.4 for instructions regarding Section A- Standard Form 33 (SF 33), Solicitation, Offer and Award.
29Attachment 0006, L.3.1.1.2, L.3.1.1.3The technical approach shall include: detailed estimates of labor by category, detailed estimates of material, with supporting rationale, schedule, management plan, identification of critical areas and risk, and the methodology necessary to verify the requirements.Can the government define what "requirements" are in this context?Requirements in this context refers to the Scope of work defined in each Sample Task Order PWS.
30Attachment 0002FBLRAre FBLR's provided within the Price Template reflective of work required within the Redstone Area of Responsibility, or various CONUS locations?Fully Burdened Labor Rates (FBLRs) are not requested in the Attachment 0002. Please refer to Attachment 0004 Performance Work Statement and solicitation Section H for information regarding perfromance locations.
31Attachment 0016Work LocationsThe Government has provided comments within the Attachment 0016 Wage Determination for Limestone & Madison County. With work locations including multiple counties within the Redstone Area of Responsibility (AOR), are offerors required to submit Direct Labor Rates compliant with SCA requirements for all counties included within the AOR?Yes. Madison and Limestone Counties were the only Wage Determinations provided as a baseline; however, Section L provides instructions for any other Wage Determinations and/or CBA not included.
32Attachment 0013Page 8para 10Sample Order 2The USG lists 6 MWOs and/or installations to be applied for each of the 5 aircraft.The USG did not provide GFI for the IDGB or Improved Flight Control MWOs / Installation instructions. Without these documents the labor required for these tasks cannot be adequately estimated, request the USG provide this information.Att 0013 updated to reflect GFI
33Attachment 0013Page 5para 4.5Sample Order 2The USG lists 6 MWOs and/or installations to be applied for each of the 5 aircraft.Does the USG intend for these MWOs to be applied in conjunction with the EPMI scope or after the EPMI scope is complete (parallel or serial fashion)?The USG will not direct how the contractor schedule the work.

File details come from the government source that posted it. Updated .