DEPARTMENT OF THE ARMY
UNITED STATES ARMY GARRISON ITALY - DARBY MILITARY COMMUNITY
PUBLIC WORKS OFFICE
APO AE 09613
PROJECT
ES 00092-1P
Modification of Depot Waste Water Treatment Plant
BLDG 5672
Depot AREA
STATEMENT OF WORK
Consisting of 16 pages
Prepared by: ________________________________ _________________
GIANLUCA LUCETTI, P.E.
DMC Chief Engineering Division
Date
Approved by: ________________________________ _________________
MARIA LOPEZ, P.E.
DMC DPW Manager
Date
INDEX
1. PROJECT DATA
1.1. Project Number and Title
1.2. Basic Project and Options
1.3. Project Phases
2. SCOPE OF WORK
2.1. Summary of the scope of work
2.2. Existing conditions
2.3. Required works – Architectural
2.4. Required works – Mechanical systems
2.5. Required works – Electrical systems
2.6. Required works – Control system
2.7. Required works – Additional works for code compliance
3. DESIGN REQUIREMENTS
3.1. Designer requirements and qualifications
3.2. Applicable codes
3.3. Reference documents
3.4. Site investigation
3.5. Design contents
3.6. Design submittals
3.7. Certification of Compliance with Italian norms
3.8. Contractor Statement of design acceptance
3.9. Design review meetings and Government review comments
3.10. Materials disposal
3.11. Safety and Coordination Plan
4. CONSTRUCTION REQUIREMENTS
4.1. General requirements
4.2. Safety
4.3. Interferences with occupants activities or facility operations
4.4. Emergency situations
4.5. Project identification sign
4.6. Final cleaning
4.7. Documents to be provided at the completion of the works
5. WORKS SCHEDULE
5.1. Contract performance period
5.2. Phase I (Design) Management
5.3. Phase II (Construction) Management
5.4. Notice To Proceed
5.5. Installation access
5.6. Milestones Plan
1. PROJECT DATA
1.1. Project Number and Title
ES-000092-1P “Modification of Depot Waste Water Treatment Plant ”
1.2. Basic Project and Options
The project consists of one basic project only. No optional work is included.
1.3. Project Phases
The project is composed by two phases:
- Phase 1 - Design Phase: the work in this phase consists of designing the details, providing calculations and whatever necessary to define in scale all parts of work required to fulfill the scope of work.
- Phase 2 - Construction Phase: provide construction of all features of the project as designed in phase 1, in accordance with proposed and approved design and progress plan.
Construction will start upon final approval of design, and will last as per the reported works schedule.
- Phase 3- testing and commissioning: perform all necessary tests to demonstrate the completion of the works in accordance with this scope of the work and preparation of the as built and final documentation and certifications.
2. SCOPE OF WORK
2.1. Summary of the scope of work
The scope of work consists in the modification of the existing sewage treatment plant by inserting a denitrification phase after the oxygenation phase for ammonia / nitrite / nitrate abatement.
Contractor is responsible for preparing the documentation necessary for communications and requests for authorization to the Regione Toscana (Tuscany Region) and ARPAT (Tuscany Region Environmental Authority) for changes to the treatment plant referred to in this scope of work and update of the “Autorizzazione agli scarichi” (Discharge Authorization) included in the USAG Italy DMC “Autorizzazione Unica Ambientale” (AUA), including the costs for any bulletins or revenue stamps. The transmission of the documentation must always take place through the Contracting Officer Representative (COR): Contractor shall not directly get in contact with the Italian Authorities without the authorization of the Government.
2.2. Existing conditions
The sewage treatment plant is sized for 1520 equivalent inhabitant and the wastewater can be classified as industrial. The discharge into the canal “fossa chiara” is authorized by the Tuscany Region and the real average flow rate of the discharge is 304 cubic meters/day, but the flow rates recorded between October 2018 and September 2019 are highly lower than the project flow rates of the plant (Average flow rate of 40 cubic meters/day, minimum of 20 cubic meters/day, maximum of 98 cubic meters / day) The treatment plant consists of fine screening, equalization basin (342 cubic meters), suspended biomass oxidation (on three lines, each 77.4 cubic meters) secondary sedimentation (on three lines, each of 15.7 cubic meters), final disinfection (n .2 basins with a volume of 12 cubic meters each).
The four pumps that pump the water from the equalization basin to the oxidation basin are model Flygt 3045.181.2110394, 1.2 kW. The sludge line consist of static thickening sludge line and drying beds. The system is controlled and supervised by the management system of the Base, Siemens Desigo type.
The treatment system is currently unable to properly treat the sewage and it is necessary to increase the abatement efficiency. The modifications included in this scope of the work are therefore necessary to constantly respect:
- the fixed limits for the discharge on the surface water body from tab. 3 annex 5 to the third part of Legislative Decree 152/2006 and subsequent amendments, and
- the values other than the limits pursuant to art. 21 paragraph 2 of Regional Law 20/2006 according to the following tab for the following parameters:
- PH – limit to discharge: 5.5-9.5
- SST– limit to discharge: 80 mg/l
- COD– limit to discharge: 160 mg/l
- Ammonia nitrogen- limit to discharge: 15 mg/l
- Nitrous nitrogen- limit to discharge: 0.6 mg/l
- Sulfates – limit to discharge: 1000 mg/l
- Total surfactants– limit to discharge: 2 mg/l
- Total hydrocarbons– limit to discharge: 5 mg/l
- Escherichia Coli – limit to discharge: 5000 UFC/100 ml
2.3. Required works – Architectural
Convert the existing oxidation basin (central basin-process line #2) into a post-denitrification section. Convert one of the existing basins for the disinfection into lift station. The denitrification basin will receive the wastewater from the two existing oxidation basins, downstream of the setter via the new lifting station. Work includes:
o Cleaning of the chlorination basin #2, dimensions 4,5x1.5x1.9 (H) m, to allow the conversion to lift station. Extend the walls of the weir well in order to raise the level of the weird and allow the discharge into the sewer in the event of failure of both pumps.
o Install a new Thomson profile made of AISI 316 stainless steel on the perimeter of the three existing settlers line n.1, n.2 and n.3. The profile must be suitably designed and sized to reduce the presence of "suspended" sludge leaving the plant for a better outlet of the clarified to the final chlorination compartment.
All the temporary works necessary to assure the operation of the Waste Water Treatment Plant during the execution of the project are included in the contractor’s burdens. Currently the treatment system uses only one oxidation basin. The basin #3 will be used as oxidation basin while the works will be carried out in the basin #1 and #2. The basin #1 and #2 will be emptied and cleaned in order to allow the works, including the corresponding sedimentation section. Wastewater disposal possibly necessary shall be performed by the Contractor without any additional burden for the Government.
2.4. Required works – Mechanical systems
Mechanical system works shall include:
- Removal of the existing submersible pump in the oxidation basin #2 (central basin) for the aerated mixture. All pipes and accessories will remain on place. The pump shall be cleaned and delivered to the COR.
- Installation of a new submersible mixer in the new denitrification section (central basin) for the agitation of the sewage in the denitrification area without oxygen supply. For maintenance reasons, the agitator must be of the same type as the agitators installed in the treatment plant.
The submerged agitator will be Xylem Mixer type, reference value for the installed power 1.2 KW, complete with extraction system with stainless steel guides and chains, insulated motor in class F in oil bath, seals mechanics in carbon-ceramic, wear ring in bronze and shaft in stainless steel, external body in cast iron, three-blade propeller and protective casing, sliding fixing system with lifting winch. The mixer must be interfaced with the existing DDC control system in order to allow timed operation.
- Installation of two new submersible pump (one spare) into the former chlorination basin to pump the water coming from the two oxidation basins, downstream the settlers, into the new denitrification basin. The pumps shall be complete with coupling foot, extraction system with stainless steel guides and chains, with vortex impeller for sewage water. For maintenance reasons, the pump must be of the same type as the pumps installed in the treatment plant, brand Flygt (Xylem). Install a ultrasonic level probe to remote overflow alarm to the DDC system.
The pumps shall be interfaced with the existing DDC control system in order to remote alarms and controls. In case of failure of both pumps the pumps of the equalization tank must stop.
The chlorination in the lift station will have to be activated automatically to disinfect the water that will go into the sewer through the weir.
- Pipes to connect the two lift pumps with the denitrification basin, including all accessories such as valves, check valves. Steel pipes are not allowed, except stainless steel. The pipe will run preferentially above ground. All modifications to existing structures and walkways are included. The discharge of the water into the denitrification tank must take place in the north side without wrinkling the surface of the water, in order to limit oxygenation as much as possible. If the pipes are submerged, they must be equipped with a flow monitoring system such as meters etc.
- Modification of the existing pipes downstream the settler. The discharge of the central settler (new denitrification settler) will be modified and connected with a new pipe to the chlorination basin. The new pipes can run above ground or underground and will be equipped with valve;
the existing one will be plugged at the height of the flange. The valve that allow the oxidation settlers to discharge into the chlorination basin will be closed; in this way the water coming from the oxidation settlers will be convoyed in the new lift station
- Modification of the inlet pipe and the sludge recirculation pipe in the central basin (new denitrification basin). The discharge of the water into the denitrification tank must take place without wrinkling the surface of the water, in order to limit oxygenation as much as possible.
If the pipes are submerged, they must be equipped with a flow monitoring system such as meters etc.
- Branch from the existing underground piping that allows the discharge from the sedimentation tanks to the drying tanks, a DN100 HDPE piping complete with shut-off valve and quick coupling for connection to DN100 vacuum track pipe, complete with support base in concrete.
The connection point will be made near the drying tanks in a suitable position to reach the nearby lifting station.
2.5. Required works – Electrical systems
Electrical system works shall include:
- Installation of new power cables feeding the new mechanical equipment (a cable for each new pump and mixer); new cables shall be connected to the existing electrical panel located in bldg 5672: various spare breakers are available; contractor shall connect each new cable to a proper spare breaker according to the equipment load. Depending on the load absorption, Contractor shall replace the spare breakers with new ones having the suitable amperage. New cables shall be FG16R16 type, routed inside the existing cable ducts, new cable ducts and into new galvanized steel conduits; In the proximity of the new pumps and the new mixer new IP55 disconnecting switches (one for each new load) shall be installed at wall to locally interrupt equipment feeding.
- Feeding of the new ultrasonic level probe connecting a new cable to the existing Controller in bldg 5672; install a proper module to be added to the Controller for the connection of the new probe. New cable shall be routed inside the existing cable ducts, new cable ducts and into new galvanized steel conduits.
2.6. Required works – Control system
Existing SIEMENS Desigo supervision and control system shall be updated in order to include in the system the new pumps, the mixer and the level probe. Designer shall provide the operating logic of the equipment. The graphic pages in the control workstations located in Bldg 5155 and Bldg 5140 shall be updated.
2.7. Required works – Additional works for code compliance
In addition to the above listed works, all other requirements to make the work totally in compliance with Italian and U.S. standards shall be identified, summarized in a report and included in the design.
In case Italian and US/Military codes or standards provide different requirements, the strictest requirements shall be applied. To be noted that in case there is conflict between a mandatory Code requirement and one or more work called for in the Scope, the Code requirement takes precedence.
3. DESIGN REQUIREMENTS
3.1. Designer requirements and qualifications
Designer is required to be a Professional Engineer enrolled in the professional Order of Engineers section A (5 years degree) in the sector pertaining the scope of the work.
3.2. Applicable codes
Design will be in compliance with all applicable Italian and US and Military Codes, in particular:
- D.M. Infrastrutture 7 Gennaio 2018, Aggiornamento Norme Tecniche per le Costruzioni
- Circolare 21 Gennaio 2019 n. 7/C.S.LL.PP. (Istruzioni per l’Applicazione dell’Aggiornamento delle Norme Tecniche)
- LAW 2 Febbraio 1974, n. 64, Provvedimenti per le Costruzioni con particolari prescrizioni per le zone sismiche.
- DPR 6 Giugno 2001, n. 380, Testo Unico dell’Edilizia.
- D. Lgs. 81, 9 Aprile 2008, e succ. mod. e integr.
- DPGR Toscana 62/R, 23 Novembre 2005, Regolamento di Attuazione dell’Art. 82, comma 16, della LR 1 del 3/1/2005
- DPR. 547 dated 27 april 1995, art. 303
- DM 37/08
- D. Lgs. 152/2006 e succ. mod. e integr.
- LR Toscana 20/2006 e succ. mod. e integr.
- Ente Unificazione Italiana (UNI), various standards, in particular:
- All applicable Italian Laws
- All applicable Italian CEI and European CEI EN norms
- All applicable NFPA Codes, in particular o NFPA 70 “National Electric Code” o NFPA 101 “ Life Safety Code”
- All Applicable Unified Facilities Criteria (UFC) and Unified Facilities Guide Specifications (UFGS) documents available on the Internet at http://www.wbdg.org, in particular:
o UFC 3-240-01, wastewater collection and treatment o UFC 3-450-01, Noise and vibration control o UFC 3-501-01, Unified Facilities Criteria, Electrical Engineering o UFC 3-520-01, Unified Facilities Criteria, Interior Electrical Systems
3.3. Reference documents
The following reference material is provided with the purpose of showing the consistency of the area where the work is planned and sharing the available information. With reference to the drawings there is however the possibility that some discrepancies exist between what depicted and the actual existing conditions. The documents are provided in .pdf or .tif format and will not be available in CAD format unless otherwise specified:
- Sheet W05/06/07/08-E01 of project DDC Upgrades and UMCS Integration WWTP (available also in CAD)
- Existing electrical panel WWTP Bldg 5672.
- Sheet C7 - sewage existing flow diagram
- Sheet C8 - sewage existing flow diagram
- Sheet C18 - grading and drainage plan
3.4. Site investigation
Designer is required to perform site investigations and measurements in order to ascertain the actual local conditions and extent of required work.
Designer is then required to prepare as-built drawings of the existing area to be used for design, based on the documents which will be provided by the Government and on the performed site investigations and measurements.
3.5. Design contents
Design shall be composed by the following documents as minimum:
1) DESIGN DRAWINGS
Design Drawings shall be on ISO A1 sheets and must contain the following, as minimum:
- Cover sheet and index of drawings including vicinity map, and a general location plan;
- Existing/Demolition plans;
- Future conditions plans;
- Sections/Details in the number and quantity to make the work description clear and the project fully constructible;
http://www.wbdg.org/
All drawings shall be to scale, with graphic scale indicated. Dimensions and material identifications shall be clearly indicated. Drawings shall include all necessary notes and legends. All wording shall be in both English and Italian.
Include a plan showing the overlapping layout of all fixtures installed on false ceilings or ceilings, if applicable. Include sections showing all distribution systems location over the false ceiling or at the ceiling.
Design drawings shall comply with the US Army Corps of Engineers “A/E/C Computer-Aided Design (CAD) Standard” (free download in https://www.wbdg.org/ffc/army-coe/cad-bim-technology-center)
2) BASIS OF DESIGN
Detailed technical report (in English and Italian) to include the following:
- Detailed description of all works to be accomplished;
- Method of accomplishment;
- Materials and finishing;
- Reference to applicable norms and laws (US, Military and Italian); designer is required to perform a comparison between the applicable codes/laws, clearly identifying the most stringent requirements, that will be applied. In case of conflict, if it is not possible to comply with both Italian and US codes, Italian codes take precedence.
3) DESIGN ANALYSIS
Detailed calculation of all the systems, structures and all other elements involved in the project, with reference to applied codes requirements listed in the basis of design. Calculation can be submitted in Italian only.
4) TECHNICAL SPECIFICATION
Technical Specifications are furnished to the Contractor to be used as the basis to prepare the design technical specification. Technical Specifications provided by the Government contain the minimum requirements for the project and Designer will be able to modify/expand/integrate the TS as applicable only upon authorization of the Design COR. Integrations will be however mandatory for sections which are not covered in what provided by the Government. Designer shall highlight the proposed modification/integration in order to allow the Government to easily identify and evaluate what submitted. Sections Ia, Ib, and Enclosure of Technical Specification are ruling for what attains construction management, quality control, anti-terrorism, physical security requirements and are not allowed to be modified by Contractor. Technical Specification shall be submitted in English only.
3.6. Design submittals
1) PREFINAL DESIGN SUBMITTAL (90% DESIGN COMPLETION).
The Prefinal design will be delivered as per Milestone Plan and will consist of the following elements in the quantities specified for the project:
ELEMENT QUANTITY
a. Print copies of drawings (drawings must be ISO A1 but print copies can be ISO A3) 2 double language copies (English and Italian)
b. Print copies of technical specifications 2 copies in English
c. Print copies of Basis of Design / Design Analysis 2 copies in English + 2 copies in Italian
d. Print copies of Documents to be submitted to Regione Toscana, including stamps and bulletins.
2 copies in Italian
e. CD containing:
1. PDF copy of drawings
2. PDF copy of technical specification
3. PDF copy of Basis of Design / Design Analysis
4. PDF copy of Documents to be submitted to Regione
Toscana
5. PDF copy of Documents to be submitted to Regione
Toscana digitally signed by a professional engineer in PAdES format.
2 CDs
2) FINAL DESIGN SUBMITTAL (100% DESIGN COMPLETION).
The final design will be delivered as per Milestone Plan and will consist of the following elements in the quantities specified for the project:
ELEMENT QUANTITY
a. Print copy of ISO A1 drawings signed and stamped by a professional engineer Print copy of ISO A2 drawings (drawings must be ISO A1 but printed in ISO A2)
1 double language copy (English and Italian) 1 double language copy (English and Italian)
b. Print copy of technical specifications signed and stamped by a professional engineer.
1 copy in English
c. Print copy of certification of compliance with Italian norms (English and Italian) signed and stamped by a professional engineer.
1 double language copy (English and Italian)
d. Print copy of Contractor statement signed by a technically qualified representative of the construction contractor.
1 double language copy (English and Italian)
e. Print copy of the final documentation to be submitted to Regione Toscana.
1 copy in Italian
f. Compact disk, rewritable, containing:
1. The entire technical specifications (English) in
Microsoft Word .DOC or .DOCX format.
2. The entire technical specifications (English) in PDF format (compatible with Adobe Acrobat Reader).
3. All project drawings (English and Italian) in DWG format (compatible with Autocad Software)
4. All project drawings (English and Italian) in PDF format.
5. Final Basis of design / Design analysis (English and
Italian) in PDF format.
6. Scans of Certification of Compliance and Contractor statement, signed, in PDF format.
1 CD
7. Documentation submitted to Regione Toscana, signed, in PDF format, including bulletins and stamps
1. Compact disk, rewritable, containing:
2. The entire technical specifications (English) digitally signed by a professional engineer in PAdES format.
3. All project drawings (English and Italian) digitally signed by a professional engineer in PAdES format.
4. Final Basis of design / Design analysis (English and
Italian) digitally signed by a professional engineer in PAdES format.
5. Certification of Compliance with Italian norms (English and Italian) digitally signed by a professional engineer in PAdES format.
6. Documentation submitted to Regione Toscana, digitally signed in PAdES format, including bulletins and stamps
1 CD
Documents at points a., b., f. above will be delivered after the contents of point e. have been checked and approved, and will incorporate any further comment or discovered deficiency.
3.7. Certification of Compliance with Italian norms
The final submission shall include Certification of Compliance with Italian Norms. It will consist of the following statement, to be signed and stamped by the designer:
“Having reviewed the definitive and detailed project No. ES 000092-1P, pertaining to “Modification of the Waste Water Treatment Plant, Depot, Livorno, Italy”, I declare that I have ascertained that the structures and technological system included therein comply with the applicable Italian norms.
DATE SIGNATURE
Esaminato il progetto definitivo e dettagliato No. ES 000092-1P, relativo a “Modifiche all’impianto di trattamento reflui fognari, Depot, Livorno Italia”, dichiaro di aver accertato che strutture ed impianti tecnologici in esso contenuti rispondono alla vigente normativa italiana.
DATA FIRMA
3.8. Contractor Statement of design acceptance
The final design submittal shall also be accompanied by the following statement, signed by a technically qualified representative of the construction contractor:
“I, undersigned __________, in the vest of __________, have reviewed the final design submittal of project ES 000092-1P “Modification of the Waste Water Treatment Plant, Depot, Livorno, Italy”, prepared by __________, with particular reference to the drawings and technical specifications, and I have found it:
- complete;
- constructible;
- fully compliant with the Scope of Work;
- feasible within the terms of the contract.
I understand that the above mentioned design documents, once reviewed and accepted by the Government, will become contract documents. I also understand that if anything of the Scope of Work is missing in the design, my Company will still be obliged to perform.”
DATE SIGNATURE
3.9. Design review meetings and Government review comments
The Contractor is required to attend a pre-design meeting and a review meetings after the pre-final submittal; Contractor’s designer is required to attend these meetings too. All meetings will take place at the COR’s office, Bldg 5155, Supply and Maintenance Area, Livorno.
In general, design review comments will be returned to designers within 15 calendar days from the date of receipt of design submittal. Every submittal after the preliminary shall be accompanied by an annotated copy of the review comments.
3.10. Materials disposal
Verify and prepare documentation for special material disposal per current Italian regulation, if the case occurs. In designing and planning construction and/or demolition activities, waste produced will be identified and waste removal opportunities will be evaluated. The designer shall identify all reusable materials to be turned in and materials to be disposed off in landfill or to be delivered to recycling plant.
Prepare documentation for hazardous material handling and disposal, for ASL approval, if that kind of material is planned to be removed. To be noted that Asbestos Containing Material is not expected to be required to be demolished under this project.
3.11. Safety and Coordination Plan
The Government will award a separate contract for Safety Coordination in the Design Phase.
The project is performed assuming the possible presence of more than one firm, also not at the same time, on the work place, as per paragraphs 3 and 4 of art. 90 of Legislative Decree 81/2008.
A preliminary “Piano di Sicurezza e Coordinamento” (safety and coordination plan) is included in the contract documentation. The final “Piano di Sicurezza e Coordinamento” (safety and coordination plan) shall be prepared by the “Coordinatore per la Sicurezza in Fase di Progettazione” (safety coordinator during design) after the approval of the final project.
4. CONSTRUCTION REQUIREMENTS
4.1. General requirements
For general requirements, including in particular the mandatory antiterrorism trainings to be performed, see section Ia “General Requirements” of technical specification.
4.2. Safety
The Government will award a separate contract for Safety Coordination in the Construction phase.
The project is performed assuming the possible presence of more than one firm, also not at the same time, on the work place, as per paragraphs 3 and 4 of art. 90 of Legislative Decree 81/2008.
The Contractor shall provide his/her own “Piano Operativo di Sicurezza” (operational safety plan) to the Safety Coordinator during Construction considering the prescriptions of the Safety and coordination Plan and shall comply with the requirements of Legislative Decree 81/2008 in all applicable parts.
4.3. Interferences with occupants activities or facility operations
The treatment plant is operative and is required to remain operative during the construction works.
Contractor is required to submit a plan before starting the construction phase clearly indicating all the work activities involving utilities interruptions (like for example power outages or water supply interruption) and impacting on usability, including the proposed measures to minimize the such periods. Contractor will reduce at minimum the utilities interruptions (water, electricity etc.), coordinating the service interruptions with the COR at least 10 days in advance.
4.4. Emergency situations
Contractor will maintain the following documentation available and usable at the work site, to be provided by the COR:
- A copy of the Camp Darby Emergency Plan, to which contractor will refer in the case of the emergency conditions indicated in the plan itself.
- Base Grid Coordinates layout, with the work site highlighted.
- List of emergency telephone numbers.
4.5. Project identification sign
The contractor shall supply and install a sign identifying the project. The sign shall be of high-resistant plywood for outdoor installation, white painted. The dimensions shall be 1200x2400x12
mm. The letters of the wording shall be uppercase, black color, 5 cm high, except the letters of the project title which shall be 10 cm. The sign shall be fixed to a structure made of any material provided it is lasting and in compliance with all safety requirements. The sign shall be well visible, with the lower side at 1.2 m from ground level.
4.6. Final cleaning
At the completion of the construction works Contractor is required to provide an accurate cleaning of the areas involved by the construction works.
4.7. Documents to be provided at the completion of the works
At the completion of the work, the following documents will be provided to the COR:
ELEMENT QUANTITY AND FORMAT
a. Statement of Conformity
(Dichiarazione di conformita’) of each utility system, according to Italian D.M. 37/08 requirements;
1 paper copy + 1 electronic copy in PDF format created by scanning the original document, stamped and signed, attachments included.
b. Instruction manuals of each system or equipment.
1 paper copy + 1 electronic copy in PDF format created by scanning the original document
c. Certification of each item / element / equipment installed.
1 paper copy + 1 electronic copy in PDF format created by scanning the original document
d. Test reports. 1 paper copy + 1 electronic copy in PDF format created by scanning the original document
e. As built drawings. 1 electronic copy in CAD format (.dwg files) and in PDF format digitally stamped and signed in PAdES
f. Documentation for Regione Toscana 1 electronic copy in PDF format digitally stamped and signed in PAdES
g. DD Form 1354 (latest version) completely filled.
1 electronic copy in PDF format
h. All the other documents required in the Technical Specification.
1 electronic copy in PDF format
In addition to the drawings pertaining the works performed within the project, the as built drawings shall include a new condition plan of the facility, in scale, showing only all the quotes of all the rooms, without any additional information.
In order to properly fill the DD Form 1354 the Contractor is required to interface with COR and the Government Real Property Office for the correct compilation of the Form.
All the electronic copies of the above documents must be delivered in a CD-ROM properly labeled.
Label shall include the following information:
- Number and title of the project
- Type and date of each document
5. WORKS SCHEDULE
5.1. Contract performance period
The contract performance period for the entire contract (Phase 1 plus Phase 2) is as follows:
- Design Phase: 90 calendar days (including days taken by the Government to review design submittals);
- Construction Phase: 90 calendar days.
Individual Notices to Proceed will be released for each of the two phases.
5.2. Phase I (Design) Management
This phase is managed by a Contracting Officer Representative (COR), from the Directorate of Public Works (DPW), Engineering Services, Design Branch. The US Government should not take longer than 15 days to provide review comments to the contractor for each planned submittal.
5.3. Phase II (Construction) Management
This phase will be controlled by the COR from the DPW, Engineering Services, Construction Branch, in accordance with documents approved in Phase 1. Normally, construction can begin once the contractor has made all changes identified during the Government design review.
However, the contractor may be allowed to proceed with construction while clarification and administrative comments are being incorporated into the design. The revisions can be approved by partial re-submittals.
5.4. Notice To Proceed
The Notice to Proceed (NTP) date for the Design Phase will be established at the Pre-Performance Conference. After the final design submittal has been approved and it is time to start construction, the first phase is closed and a new Notice to Proceed is issued by the Contracting Officer to the contractor.
5.5. Installation access
Once the contractor has been awarded the contract, he must apply for installation passes for each contract personnel requiring access for more than 60 calendar days to perform work. It takes a minimum of 30 working days from the date of application to the Security Office to be issued an installation pass.
5.6. Milestones Plan
Project phasing will be in accordance with the Milestones Plan. Overall number of Calendar Days allowed will be in accordance with paragraph 7.1.
Notes:
- Design NTP date is hypothetical. In case this date changes, the plan will vary.
- Passes for construction shall be obtained during design phase
Milestones Phase duration
Progressive Date
Design Phase NTP/Start Design 0 1-Sep-22 Submittal Prefinal Design 45 45 16-Oct-22 Comments 15 60 31-Oct-22 Submittal Final Design and Approval Requests 15 75 15-Nov-22 Comments and final corrections 15 90 30-Nov-22
Construction Phase NTP/Start Construction 15-Dec-22 Completion of construction 90 90 15-Mar-23
| 1. PROJECT DATA |
| 1.1. Project Number and Title |
| 1.2. Basic Project and Options |
| 1.3. Project Phases |
| 2. SCOPE OF WORK |
| 2.1. Summary of the scope of work |
| 2.2. Existing conditions |
| 2.3. Required works – Architectural |
| 2.4. Required works – Mechanical systems |
| 2.5. Required works – Electrical systems |
| 2.6. Required works – Control system |
| 2.7. Required works – Additional works for code compliance |
| 3. DESIGN REQUIREMENTS |
| 3.1. Designer requirements and qualifications |
| 3.2. Applicable codes |
| 3.3. Reference documents |
| 3.4. Site investigation |
| 3.5. Design contents |
| 3.6. Design submittals |
| 3.7. Certification of Compliance with Italian norms |
| 3.8. Contractor Statement of design acceptance |
| 3.9. Design review meetings and Government review comments |
| 3.10. Materials disposal |
| 3.11. Safety and Coordination Plan |
| 4. CONSTRUCTION REQUIREMENTS |
| 4.1. General requirements |
| 4.2. Safety |
| 4.3. Interferences with occupants activities or facility operations |
| 4.4. Emergency situations |
| 4.5. Project identification sign |
| 4.6. Final cleaning |
| 4.7. Documents to be provided at the completion of the works |
| 5. WORKS SCHEDULE |
| 5.1. Contract performance period |
| 5.2. Phase I (Design) Management |
| 5.3. Phase II (Construction) Management |
| 5.4. Notice To Proceed |
| 5.5. Installation access |
| 5.6. Milestones Plan |