MPF 1-1 Sessions w/Industry 17 April 17
Agenda
Introductions Admin – What level of information can be discussed Ground Rules Program Update Recap USG response to Industries questions Industry recap design approach Industry Questions on CDD/PSPEC USG Questions
Classified session (Must be read in for NATO to attend)
13-Jun-17
Ground Rules
1. This session will run no more than 3 hours.
2. Agenda
3. The USG may ask "clarifying" questions "during or after your presentation".
4. USG can clarify specifics of the CDD/PSPEC requirements, however not whether or not a solution will meet the requirement
5. The USG "may" answer your pre-submitted questions time permitted. "Any questions generated during the meeting" will be answered as time allows or at a later date.
*Note, all questions answered by the USG during this meeting are unofficial. Official responses will be answered on the FedBizOpps website. Any company specific information will be removed or made generic "before posting the question and answer to all interested parties.” If company specific information cannot be removed or made generic than an answer will not be given.
MPF Program Update (1 of 3) Strategy based on pursuing a Non-Developmental Item (NDI) combat vehicle with limited modifications Previous Market Survey responses indicated that some requirements needed adjustment to facilitate pursuing an NDI solution 14 Jul Fed Biz Ops (FBO) announcement – Called for White Papers and comments on draft MPF requirements 30 Dec FBO announcement – Intent to pursue a Fixed Price Contract 29 Mar FBO announcement – Updated documents & requested feedback:
Capability Development Document (CDD) (Updated IAW Industry feedback) Classified CDD Annex (Updated) Performance Specification (P-Spec) (New) Operational Mode Summary/Mission Profile (OMS/MP) (New)
MPF Program Update (2 of 3) MPF requirements AROC (end of Apr)
AoA is planned to be completed by May with final results approved in June
Request for proposal and source selection Draft RFP package (SOW, L&M language) release planned (Jun & Oct) RFP release planned (Dec/Jan) Proposals Due planned for April 2018 Planning to evaluate a Bid Sample and BH&T
Notional MPF Program Schedule (3 of 3) 13-Jun-17
ACAT 1C / EMD
PEO GCS / PM AFV
| Task | FY17 | FY18 | FY19 | FY20 | FY21 |
| MDD Approval | |||||
| AoA Development | |||||
| CDD Updates/Staff/Approval | |||||
| Draft RFP Release (JUN/OCT) | |||||
| RFP Release | |||||
| Contractor Proposal Development | |||||
| SSEB with Bid Sample Evaluation | |||||
| MS B DAB | |||||
| EMD Contract Award | |||||
| SOWM | |||||
| DMR (Design Maturity Review) | |||||
| First Prototype Delivery |