FY22* FY23 FY24
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Final Proposals
Due Aug 23 Contract Award
Nov 23
Discussions (if needed)
Apr 23
Draft RFP Release Nov 21
Industry Day #3 Mar 22
Final RFP Release Sep 22
Initial Proposals
Due Dec 22
16 Mar 2022
Updated HSAAP Acquisition Milestones
*Government Fiscal Year is 1 Oct to 30 Sep
Subject to Change
One-on-one Sessions
Apr 22