GOVERNMENT RESPONSE TO CONTRACTOR QUESTIONS 3

View the file

Other files

File Type Posted
Amendment_0006.pdf PDF
Amendment_0005.pdf PDF
Government_Response_to_Contractor_Questions_4.docx DOCX document
Amendment_0004.pdf PDF
FINAL__Revised_SATCOM_PWS_amend_0004_19SEP18.docx DOCX document
Government_Response_to_Contractor_Questions_2.DOCX DOCX document
Amendment_0003.pdf PDF
SATCOM_Price_Matrix_9_12_2018.xlsx XLSX spreadsheet
FINAL__Revised_SATCOM_PWS.docx DOCX document
Amendment_0002.pdf PDF
FINAL_Government_Response_to_Contractor_Questions.docx DOCX document
Amendment_01.pdf PDF
MASTER_INVENTORY.xlsx XLSX spreadsheet
DD_254.pdf PDF
Estimate_for_Camp_Carroll.xlsx XLSX spreadsheet
Terminals_Maint_List.xlsx XLSX spreadsheet
SATCOM_Support_Performance_Work_Statement.docx DOCX document
Small_Business_Participation_Form.docx DOCX document
GFE_Update.xls XLS spreadsheet
Pricing_Matrix.xlsx XLSX spreadsheet
Warranty_Part_List.xlsx XLSX spreadsheet
Warranty_Terms.docx DOCX document
RFP_W52P1J-18-R-0085.pdf PDF
PPI-002-M,_Past_Performance_Information.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Document
Page #
Para #
Quote
Issue / Question
Q19
Performance Work Statement
15

PWS Paragraph 1.6.8

The contractor is required, at a minimum, to be staffed in accordance with the following:

· 50% staffed 20 days after award

· 100% fully staffed 60 days after award

In Amendment 0002, the Government revised Section L, Volume 5, L, 3 to reflect a 90-day Transition-In Period.

Will the government revise PWS, page 15, paragraph 1.6.8, to align the staffing requirement with the 90 day Transition-In Period?

A:19
The Government revised the PWS paragraph 1.6.8, via amendment 0004, as follows:

· 50% staffed 30 days after award

· 100% staffed 90 days after award

Q20
RFP, Section L
52

Section L, Volume 5, Factor 5, #4

The proposal shall consist of:

· Electronic copy of the filled out Pricing Matrix/Attachment 0001.

· Any additional information considered necessary to explain the proposed pricing

The government does not provide instructions for subcontractor proposals.

Are subcontractors required to submit an unsanitized Cost proposal directly to the government?

A:20
The Government isn’t asking for cost proposals. Per the RFP Section L.2 and the price matrix column B, the offeror is to identify the company name and its proposed labor rate. If a subcontractor is being utilized for a specific labor category, the sub-contractors name will be placed in that column.