W519TC26RA026 0001 SF30.pdf
PDF 729 KB Posted
- Attached to
- Concrete Pads B230
- Solicitation number
- W519TC26RA026
About this file
This is Amendment 0001 to Solicitation W519TC26RA026, issued by the Army Contracting Command - Rock Island (ACC-RI) on April 20, 2026, for concrete pad construction work in Building 230 at the Rock Island Arsenal - Joint Manufacturing and Technology Center (RIA-JMTC). The amendment provides updated descriptions for seven contract line items (CLINs 0001-0007), clarifying which work areas of the Statement of Work (SOW) correspond to each CLIN, and includes contractor and government questions and answers. The underlying solicitation seeks a single Firm Fixed Price (FFP) contract award to the lowest price, responsive, and responsible contractor in accordance with FAR Part 36 (Construction and Architect-Engineer Contracts). Cost data submission is not required unless price competition does not materialize. A mandatory pre-construction site visit is scheduled for April 16, 2025, at 10:00 AM Central Time at RIA-JMTC, with attendees required to wear steel-toed safety shoes and safety glasses and obtain reservations at least 24 hours in advance.
The work involves concrete pad construction across multiple work areas designated as Pads 1 through 8, with descriptions revised from the original format (e.g., "Concrete Work for B230 E4000-6071-LGC1" changed to "Concrete Work IAW SOW 26-4-14 B230 Concrete Work Pad-1"). The Davis-Bacon Act Wage Determination #IL20260001 Modification 3 applies. Key solicitation documents include Attachment 0001 (26-4-14 Concrete Work B230 SOW) and Attachment 0002 (26-4-14 Quality Assurance Surveillance Plan). Government points of contact are Contract Specialist Brandy Huesmann (brandy.m.huesmann.civ@army.mil) and Contracting Officer Sophia Muckenfuss (Sophia.l.muckenfuss.civ@army.mil). All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Contractor Questions W519TC26RA026 B230 Government Answers.xlsx | XLSX spreadsheet | |
| 26-4-14 Concrete Work B230 (26-03-12) SOW.pdf | ||
| W519TC26RA026.pdf | ||
| 26-4-14 Quality Assurance Surveillance Plan.xls | XLS spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of theoffer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
J 1 4
0001 20 APR 2026 NA
W519TC
W6QK ACC-RI
ACC ROCK ISLAND BLDG 60, 3055 RODMAN AVE
ROCK ISLAND, IL 61299-0000
UNITED STATES
BRANDY HUESMANN, EMAIL: BRANDY.M.HUESMANN.CIV@ARMY.MIL TELEPHONE:
5206930087
SCD: PAS:
W519TC26RA026
13 APR 2026
SEE SECTION G - CONTRACT ADMINISTRATION DATA
Amendment 0001 provides updated CLIN descriptions
SOPHIA L. MUCKENFUSS
20 APR 2026
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section B - Supplies or Services & Prices or Costs
The following CLIN(s) / SLIN(s) / ELIN(s) were modified:
Section C - Description/Specifications/Statement of Work
Miscellaneous text in this section has been modified to:
AMENDMENT 0001 NARRATIVE
Amendment 0001 to solicitation W519TC26RA026 provides updated CLIN descriptions to call out which work areas of the SOW go with each CLIN.
Amendment 0001 provides Contractor and Government Q&A's as follows (see Q&A spreadsheet).
All other terms and conditions remain the same.
SOLICITATION NARRATIVE
1. The Army Contracting Command - Rock Island (ACC-RI), CCRI-AIH hereby issues Solicitation W519TC26RA025 for Concrete Pads in Building 230 at the Rock Island Arsenal - Joint Manufacturing and Technology Center (RIA-JMTC). This solicitation is issued in accordance with Federal Acquisition Regulation (FAR) Part 36 (Construction and Architect - Engineer Contracts).
The Government intends to award one (1) Firm Fixed Price (FFP) contract to the lowest price, responsive, and responsible contractor whose quote conforms to the terms and conditions of the solicitation and represents the lowest total evaluated price. Contractors are responsible for providing their best price at the time of the quote submission. Contractor's responsibility will be determined as outlined in FAR 9.104-1.
WAGE DETERMINATIONS
Davis-Bacon Act WD #IL20260001 Modification 3 applies to this action
2. The Government anticipates price competition, therefore, cost data is not required to be submitted with the offeror's proposal. However, the Government reserves the right to request cost data in the event price competition does not exist.
3. SITE VISIT INFORMATION:
A pre-construction site visit is scheduled at 10:00 AM Central Time, 16 Apr 2025, at the Rock Island Arsenal - Joint Manufacturing and Technology Center (RIA-JMTC). Attendees will park in lot B212 then meet Government representatives at the turnstile.
All attendees will be required to wear steel-toed safety shoes and safety glasses. Reservations for this site visit are mandatory for all attendees at least 24 hours prior to the site visit. If you currently have badge access, you still must make a reservation for the site visit in order for the Government to control the number of attendees at any given time. You will not be allowed to attend without a reservation regardless of installation access.
POC for this action is Contract Specialist, Brandy Huesmann, brandy.m.huesmann.civ@army.mil.
4. The following Attachments are a part of this solicitation:
Attachment 0001: 26-4-14 Concrete Work B230 (26-03-12) SOW
Attachment 0002: 26-4-14 Quality Assurance Surveillance Plan
5. A Contracting Officer's Representative or a Performance Certifier will be assigned to this action upon award.
6. PHOTOGRAPHIC EQUIPMENT RETRICTIONS
There are restrictions on the use of photographic devices in all non-public areas fo Arsenal Island.
This includes digital cameras, cell phones and PDAs with cameras. You must get permission to use any type of photographic device in any non-public area on Arsenal Island. All requests must be coordinated with the Contracting Officer's Representative (COR) or designated Contracting Officer for this effort prior to using any photographic device.
7. Army Contracting Command - Rock Island Government Point of Contact
Contract Specialist, Brandy Huesmann, brandy.m.huesmann.civ@army.mil
Contracting Officer, Sophia Muckenfuss, Sophia.l.muckenfuss.civ@army.mil
File details come from the government source that posted it. Updated .