26-4-14 Quality Assurance Surveillance Plan.xls

XLS spreadsheet 42 KB Posted

Attached to
Concrete Pads B230
Solicitation number
W519TC26RA026
Issued by

About this file

This is a Quality Assurance Surveillance Plan (QASP) for concrete work at Rock Island Arsenal under solicitation W519TC26RA026. The QASP outlines five key surveillance tasks for a concrete mounting pad project, each with specific performance standards and inspection methods. Security procedures require 100% visual verification that all personnel at the site maintain proper badges and roster documentation, with the work roster maintained daily at 90% acceptable quality level to ensure site safety and accountability. The contractor must submit a project timeline within one week of contract award showing the completion plan, subject to 100% visual or written verification and adjustable during performance if needed to meet the contracted completion date.

Material inspections will be conducted on a random basis to verify that contractor-provided materials meet the contracted scope of work and minimum industry standards, such as slump or temperature tests for incoming concrete, with 100% acceptable quality level. A final inspection will be performed once upon completion to verify all work is completed in accordance with the contracted scope of work, requiring 100% visual verification. Daily site inspections at 90% acceptable quality level will observe that work is being performed safely and in accordance with the contractor's provided timeline and the contracted scope of work. The QASP is dated March 12, 2026, and is associated with the Department of the Army Materiel Command Contracting Command at Rock Island Arsenal.

View the file

Other files

File Type Posted
Contractor Questions W519TC26RA026 B230 Government Answers.xlsx XLSX spreadsheet
W519TC26RA026 0001 SF30.pdf PDF
W519TC26RA026.pdf PDF
26-4-14 Concrete Work B230 (26-03-12) SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QASP

TaskContract ReferenceFrequencyPerformance StandardAcceptable Quality LevelSurveilance MethodSurveilance Date(s)Performance LevelNotes
Site ConferenceSheet 1 - Security NotesOnceEach individual working at the site must receive this information for safety and accountability purposes. May be updated if additional personnel come to the work site. May be performed as part of the badging process.100%Visual/Roster
Work RosterSheet 1 - Security NotesDailyMust be maintained for safety and security purposes. Must show who is at the work-site at any given time.90%Written Roster
Project TimelineDictated by contractOnceTo be provided within 1-week of award of the contract. Must show plan for completion prior to the date stated in the contract. May be adjusted during performance provided within project completion date.100%Visual/Written
Site InspectionSheet 1 - Security NotesDailyObserve work is being performed safely and in accordance with the contractor provided timeline and IAW the contracted Scope of Work90%Visual
Materials InspectionsSheet 1 - Notes 1-17RandomMaterials provided by the contractor may be inspected to ensure that they meet the contracted Scope of Work and minimum industry and design standards. (e.g. slump or temperature tests of incoming concrete)100%Visual/ Measurement
Final InspectionSheet 1 - Notes 1-17OnceVerify that all work is completed IAW the contracted Scope of Work100%Visual

&LRock Island Arsenal Quality Assurance Surveillance Plan&CConcrete Work (Concrete Mounting Pad)&RTARA-LGC-26-4-14 DATE: 12-Mar-26