This document is a Contract Data Requirements List (CDRL) containing three separate data item requirements for a military contract at Pine Bluff Arsenal.

Data Item A002 - Test/Inspection Report: Requires submission of First Article Test Reports with a minimum 15-day notice to the Government Product Quality Manager and PCO. Reports must be submitted at the Factory Acceptance Test (FAT) stage, with distribution to JMPB-MMQ. The contractor must allow the Government to witness the FAT. Contact for submission is Mr. Kenny Daniel at Pine Bluff Arsenal (kenneth.g.daniel2.civ@army.mil, 870-540-3140).

Data Item A001 - Inspection Equipment Description Documentation: Requires an Acceptance Inspection Equipment Plan per tailored authority DI-QCIC-81006. Submission deadline is 60 days prior to FAT or start of production if FAT is not applicable, with Government review and response within 30 days. Revisions must be submitted within 10 days of Government feedback. Critical, Special, and Major Characteristics must be included in the specification/TDP. Contact is Kenny Daniel at Pine Bluff Arsenal (kenneth.g.daniel2.civ@army.mil, 870-540-3140).

Data Item A004 - Management Plan: Requires a Quality Manual to be submitted 30 days before FAT, with Government review allowing only 3.2.E applicability where other equals Quality System Plan. The plan must be submitted prior to first article submission or production initiation, with 30-day Government review period. Distribution is to JMPB-MMQ. Contact for submission is Mr. Kenny Daniel at Pine Bluff Arsenal. All documents were prepared and approved on September 16, 2025, by A. Darn Pecanty.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A03 - delay, slider, booster-burster assy QAR 25-023.pdf

File details come from the government source that posted it. Updated .