W519TC-24-R-2001 Amendment 0001.pdf
PDF 388 KB Posted
- Attached to
- Replace Roofing - Building 66 & 67 Federal contract opportunity
- Solicitation number
- W519TC-24-R-2001
About this file
This document is an amendment to a solicitation for replacing roofing on Buildings 66 and 67 at the Rock Island Arsenal. The amendment provides answers to contractor questions about the project, including confirming roofing licensing requirements in Illinois, acceptable means and methods for accessing the work areas and installing materials, load limits on floors, and responsibilities for protecting interior areas from debris and overspray. An attachment includes the site visit sign-in sheet from November 13, 2023. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 0010 Structural Initial for Stone Shops.pdf | ||
| Attachment 0011 Floor Study Report.pdf | ||
| W519TC-24-R-2001 Amendment 0002.pdf | ||
| Attachment 0009 B66 67 Site Visit Sign in 13 November 2023.pdf | ||
| Attachment 0003 Appendix B_2023-755_Drawing Set.pdf | ||
| Attachment 0004 Appendix C_2023-0755 Submittal Register.pdf | ||
| Attachment 0007 B66 67 Roof Site Visit Map.pdf | ||
| Attachment 0001 2023-755 - SOW - 2023.09.28.pdf | ||
| Attachment 0005 Appendix D_2023-755 CD DEBRIS SUBMITTAL FORM.pdf | ||
| W519TC24R2001.pdf | ||
| Attachment 0006 DB Wage Determination.pdf | ||
| Attachment 0008 VENDOR GUIDE Contract Opportunities All Topics.pptx | PPTX presentation | |
| Attachment 0002 Appendix A_2023-0755 Specs.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR 2023-755
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Summary of Changes
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Nov-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W519TC24R2001
X 9B. DATED (SEE ITEM 11)
07-Nov-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Nov-2023
CODE
ARMY CONTRACTING COMMAND - ROCK ISLAND
3055 RODMAN AVE
ROCK ISLAND IL 61299
W519TC 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W519TC24R2001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001
The purpose of this amendment is to:
1. Answer the following Contractor questions:
a. Is there a freight elevator that can be used to get a man-lift or scaffolding to the top floor for installation of the spray insulation?
Answer: The elevator is not in service. If Contractor removes window sash, it needs to be reinstalled to current operable condition. Contractor has option to utilize existing roof hatches for access.
b. Section 2.4 of the SOW states: Contractors and sub-contractors shall be licensed in the State of
Illinois according to the work they are performing. If applicable to a trade or profession, workers shall be licensed as required by local municipality or by the State of Illinois. Will the successful bidder be required to hold a roofing license in Illinois?
Answer: Yes. The required licensing applies to actual onsite work the Prime contractor/subcontractor would be performing. Per FAR 52.236-7 Permits and Responsibilities, the Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary license and permits, and for complying with any Federal, State, and municipal laws, codes and regulations applicable to the performance of the work.
c. Can lifts be used inside if they meet the low live load requirements or, should all bids include the complete erection and removal of scaffolding inside the 3rd floor space?
Answer: Contractor means and methods of construction. See Attachment 0003 General Demolition/Repair Note #3 and #4 on G-003. Take into consideration the Safe Floor Limits on the 3rd floor not to exceed 45lbs per square foot.
d. Please confirm if a temporary support and / shoring system is needed to support live loads on the attic floor in order to install the spray Foam.
Answer: Contractor can bring temporary load distribution material to distribute live loads.
e. Can it be confirmed that elevator #7 is not in service? If elevator does not work. Should all bids include labor and equipment on debris removal of the 1 by material out of the attic, through a window opening or attic hatch?
Answer: Elevator is not in service. If Contractor removes window sash, it needs to be reinstalled to current operable condition. Contractor has the option to utilize existing roof hatches for access. See Attachment 0003, Note #1 under General Demolition/Repair.
W519TC24R2001
f. Should bids include plastic masking of the entire floor, walls, sprinkler system and any other equipment inside the building, for protection from insulation overspray?
Answer: As noted in Attachment 0003, G-003 in General Note #5 and General Demolition/Repairs Note #9, Contractor is responsible for protecting the job site, including interior and exterior areas subject to falling debris from roofing activities. See Keynote #14 in A-101 (Protect Fire & Electrical Equipment as needed to insulate the roof without over spray or drip of insulation on the or onto any other surface.)
g. Is the 1x material tongue and groove?
Answer: Yes, 90% of the material is tongue and groove and the remaining is regular planks, but all material is to be removed.
2. Attach the site visit sign in sheet. Please see Attachment 0009, dated 13 November 2023.
3. All other terms and conditions remain unchanged.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .