This amendment modifies a solicitation for a 150-gallon vertical high-shear mixer for explosives. It addresses a contractor question regarding proprietary design information by clarifying that the required 3D CAD model should show external features and port locations at scale, but not internal components. The amendment also extends the quote receipt deadline from November 15th to November 16th at 3:00 PM Central Time. The solicitation is being conducted by the Army Contracting Command - Rock Island on behalf of the McAlester Army Ammunition Plant and seeks one 150-gallon vertical high-shear mixer, one spare bowl, shipping, installation, field service, and support.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT 0002 dated 15 November 2023 Combined Synopsis/Solicitation Number: W519TC-24-Q-150GALMixer Agency: Army Contracting Command – Rock Island (ACC-RI) Title: One (1) 150 Gallon Vertical High Sheer Mixer (VHSM) for explosives to include One (1) Spare Bowl and Shipping, Installation, Field Service and Support
1. The purpose of this AMENDMENT 0002 is to address a contractor’s issue below and extend the receipt of quotes from 15 November 2023 to 16 November 2023 at 3:00 p.m. Central Time.
Q1: Regarding CAD, all parts of the machine are proprietary and the product is export controlled. There is concern about secured documents.
A1: Regarding Finalized Drawings, 3-D CAD Model, and Data (Reference Paragraph 7 in the Purchase Description), the 3-D CAD Model should provide a to-scale representation of the mixer’s external features, including all port locations. Modeling of the mixer’s internal components is not required. McAlester Army Ammunition Plant (MCAAP) Engineering will incorporate this model into its overall design model so all supporting equipment can be virtually arranged and located inside the production building before final assembly. This information will be used for MCAAP Engineering design layout purposes ONLY, and will NOT be shared with any outside source.
2. All other terms and conditions remain unchanged.