DRAFT Statement of Work- Fort Belvoir Roofing SATOC IDIQ
Solicitation number
W5168W-24-R-0022
Issued by

About this file

This document is a draft Statement of Work (SOW) for a firm fixed price Indefinite Delivery/Indefinite Quantity (ID/IQ) Single Award Task Order Contract (SATOC) for roofing services at Fort Belvoir, Virginia and surrounding satellite facilities. The contractor shall provide all labor, equipment, and materials to perform roof removal, installation, repair, sealing, and replacement as needed. Key requirements include:

The contractor must have a Virginia Class A Contractor's License and a local office within 2 hours of Fort Belvoir. Work will be ordered through task orders, with varying amounts of calendar days allowed for completion based on the dollar value. The contractor must submit various plans and meet security requirements for accessing the installation. The SOW details extensive safety, health, and environmental requirements the contractor must comply with, including activity hazard analyses, fall protection, hazardous energy control, and inspection/reporting procedures. The government plans to publish this draft SOW, and an official solicitation is forthcoming.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Fort Belvoir

Single Award Task Order Contract(SATOC)

Indefinite Delivery/Indefinite Quantity (ID/IQ)

As of 19 September 2024

TABLE OF CONTENTS

1.0 Contract Description

1.1 General Requirements

1.2 Description of Services/Introduction

2.0 Objective

3.0 Scope

4.0 General

5.0 Location

6.0 Principal Features

7.0 Rate of Work Performance

8.0 Submittals

9.0 Security Requirements

10 Supervision

11.0 Basis for Payment and Cost Loading

12.0 Project Schedule Detailed Requirements

13.0 Project Schedule Submissions

14.0 Governmental safety Requirements

15.0 Definitions

16.0 Accident Prevention Plan (APP)

17.0 Activity Hazard Analysis (AHA)

18.0 Display of Safety Information

19.0 Emergency Medical Treatment

20.0 Notification and Reports

21.0 Hot Work

22.0 Confined Space Entry Requirements

23.0 Severe Storm Plan

24.0 Products

25.0 Execution

26.0 Utility Outage Requirements

27.0 Fall Protection Program

28.0 Work Platforms

29.0 Equipment

Addendum: Sample Statement of Work (SOW)

1.0 CONTRACT DESCRIPTION

This is a Firm Fixed Price (FFP) Indefinite Delivery-Indefinite Quantity (IDIQ) Single Award Task Order

(SATOC) contract for roofing services as defined under NAICS 238160. The Contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the SATOC as defined in this Statement of Work (SOW). The

Contractor shall perform to the standards in this contract.

1.1 GENERAL REQUIREMENTS:

This is a non-personal services contract to provide Single Award Task Order (SATOC) Indefinite

Delivery/Indefinite Quantity (ID/IQ) procurement options to Fort Belvoir (Installation) and satellite camps/facilities. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.2 DESCRIPTION OF SERVICES/INTRODUCTION:

The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the JOC as defined in this

Performance Work Statement (PWS), except for those items specified as government furnished property and services. The Contractor shall perform to the standards in this contract.

2.0 OBJECTIVE

This contract is for a broad range of maintenance, repair, sustainment, and minor construction projects on real property at Fort Belvoir. During the contract period, the Government will identify roofing tasks required to complete each specific project. These tasks will include roof removal, installation, repair, sealing and or replacements to buildings.

The Contractor shall furnish site work as required per the line item in the Construction Task Catalog

(CTC), commonly referred to as a Unit Price Book (UPB). The Contractor shall use the site-specific

Gordian Construction Task Catalog as the basis for pricing all task order for this contract. The site-specific Gordian catalog is specifically formulated for the Ft. Belvoir area. The Contractor shall perform in accordance with (IAW) local policies, National Fire Protection Association (NFPA) codes, and industry and trade organization standards.

The services covered by this contract are for real property repair and construction. Construction and repair include, but are not limited to, the following systems and disciplines:

Asphalt roof shingle installation

Painting, spraying, or coating, roof

Roofing, built-up tar and gravel, installation

Steep slope roofing installation

Copper roofing installation

Roll roofing installation

Shake and shingle, roof, installation

Treating roofs (by spraying, painting or coating)

Corrugated metal roofing installation

Roof membrane installation

Sheet metal roofing installation

Galvanized iron roofing installation

Roof painting, spraying, or coating

Skylight installation

Low slope roofing installation

Roofing contractors Solar reflecting coating, roof, application

The Government will implement the processes set forth in the Scope of Work (SOW) to develop and issue individual Task Orders. Individual SOWs will vary in size depending on the nature of the work. The

Contractor shall provide sufficient technical support, project management, accurate estimates, and accommodate a number of concurrent active projects. The Contractor shall handle rapid increases in work volume, perform according to schedule without delay, and complete submittals and payrolls in a timely manner.

3.0 SCOPE: The Contractor shall provide all supervision, plant, labor, equipment, materials and appliances necessary to perform all operations in connection with the repair and replacement of existing roofs on various building structures located at Fort Belvoir, in accordance with this Statement of Work, specifications and drawings, and subject to the terms and conditions of the contract. Completed work shall result in each building or facility being watertight and impervious to the weather and its elements.

4.0 GENERAL: All work shall be completed by personnel skilled in the type of work involved. When new work adjoins, connects or abuts existing work or facilities, the existing work or facilities shall be altered as required and the connections made in an approved, workmanlike and professional manner. All existing work or facilities damaged by the Contractor’s operations, other than facilities specified to be removed in a task order, shall be repaired or replaced by the Contractor at no cost to the Government.

Prior to performance of work, a preconstruction orientation shall be held at Fort Belvoir unless waived by the Government. The Contractor shall have a representative attend who has authority to make decisions for and sign contractual documents on behalf of the Contractor. The Contractor must have or provide the following:

a. Hold and maintain a Virginia Class A Contractor’s License.

b. Have a local office within two (2) hours of Ft. Belvoir for on-site management.

c. Provide contact information for vetted subcontractors, if applicable.

5.0 LOCATION: The site of the proposed work is located in Fort Belvoir, Virginia and Area Garrisons which include Fort Walker (fka Fort A.P. Hill), Joint Base Myer Henderson Hall (JBMHH), Rivanna

Station, Arlington National Cemetery, and Fort McNair.

6.0 PRINCIPAL FEATURES: Each task order issued by the Government under this contract shall specifically identify the building(s) to receive roof repair and/or replacement work along with the associated Pricing Schedule items and quantities necessary to complete each building roof or portion thereof. Although the contract does not explicitly identify individual buildings, roofs or other structures to be constructed, repaired or replaced, the contract bid schedule is structured to order quantities of materials, rather than buildings, sufficient to complete all work required to provide a completed project. It is the Government’s intent that the Pricing Schedule items and quantities identified in a task order, with respect to a particular building, shall be sufficient to complete all work related to that building. All Pricing

Schedule items and quantities of material ordered to complete a particular building, to include within scope task order modifications, are a bona fide requirement of the Fiscal Year in which the task order is placed.

Unified Facilities Guide Specifications (UFGS) referenced within this Statement of Work is available at:

https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

Unified Facility Criteria (UFC) documents referenced within this Statement of Work is available at:

https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc

Roof work shall be performed on "BUILDINGS", which include warehouses, administrative and operation buildings, shops, barracks, mess halls, and other miscellaneous structures on Fort Belvoir. The work performed will include Pricing Schedule items in accordance with the contract documents, specifications, and drawings.

7.0 RATE OF WORK PERFORMANCE:

The period of time, in calendar days, allowed for completion of each task order shall be as follows:

counting of calendar days allowed for each task order shall start from the date of notice to proceed of the task order. The time allowed for submittals shall be added to the time allowed for the first task order.

Each Task Order Calendar Days to Complete

Under $10,000 20

$10,000 to $19,999 30

$20,000 to $99,000 45

Over $100,000 Will be negotiated

Note: Contractor's rate of performance for multiple task orders issued at the same time (within one week) shall be summed for aggregate total. This aggregate total will be compared to the rate of performance table in the contract for the number of days allowed to complete a group of task orders issued at the same time. For example, four task orders issued at same time worth $10,000 each for a total of $40,000 are given 45 days for completion of all four task orders.

8.0 SUBMITTALS:

Submittals shall be provided as required by the contract. Failure to furnish submittals may result in a suspension of work. Materials furnished and/or installed that do not meet the specifications may be rejected by the Contracting Officer or his/her duly appointed representative. The following electronic submittals shall be provided after contract award for review and approval.

Submittal Date Due

Anti-Terrorism (AT) Level 1 Training 60 calendar days after contract award

TARP Training 60 calendar days after contract award

OPSEC Training 60 calendar days after contract award

Insurance Certificate 30 calendar days after contract award

Generic Site Safety & Health Plan 30 calendar days after contract award

Environmental Protection Plan 30 calendar days after contract award https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc

Contractor Quality Control Plan 30 calendar days after contract award

Waste Management Plan 30 calendar days after contract award

Material (all materials required for the contract)

30 calendar days after contract award

9.0 SECURITY REQUIREMENTS

Contract Clause FAR 52.204-2 Security Requirements and Alternate II and the following apply:

a. The Contractor shall ensure that all contractor and sub-contractors employees who require physical access to Army Bases provide all information required for a check of records through databases including, but not limited to, the National Crime Information Center

(NCIC) Interstate Identification Index (III) and the Terrorist Screening Database. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force

Protection Condition (FPCON) at the installation change, the Government may require changes in contractor security matters or processes.

b. All contractor and associated sub-contractor employees who require physical access to Army

Bases for contract performance shall present an Acceptable Identity Source Document, as identified in Section 2 of Attachment 4 of DoD Directive-Type Memorandum 09-012, “Interim Policy Guidance for DoD Physical Access Control” (available at http://www.dtic.mil/whs/directives/corres/pdf ), filename “DTM-09-012.pdf” to access the installation.

c. The Contractor shall maintain awareness of all Prime and Sub-Contractor employees who are vetted and approved for access onto the Base. Contractor shall notify the KO and COR in writing within 48 hours of any contractor or sub-contractor employees who resigns, is terminated, or for any other reason and no longer authorized to access Army Base for the purpose of performance of this contract. For contracts with a performance period longer than three months, the Contractor shall reconcile his roster of approved personnel with the Base

Visitor Control Center (VCC) to ensure that both the Contractor and Contract Officer

Representative maintain accurate awareness of the contractor and subcontractor employees who are authorized to access the installation.

i. All contractor and all associated sub-contractors employees requiring physical access to

Army Base for contract performance shall be pre-screened by the Contractor using the

E-verify Program at http://www.dhs.gov/E-Verify website to meet the established employment eligibility requirements and shall provide only eligible employees for contract performance while on the installation.

ii. All contractor and all associated sub-contractors employees requiring physical access to

Army Base for contract performance shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer if a COR is not assigned, within 10 calendar days after completion of training by all employees and subcontractor personnel.

http://www.dtic.mil/whs/directives/corres/pdf

AT level I awareness training is available at https://jkodirect.jten.mil/Atlas2/faces/page/login/Login.seam .

iii. All contractor and sub-contractor employees shall attend a briefing on the local iWATCH program provided by the JBM-HH ATO or Security Office. This locally-developed briefing will be used to inform employees of the types of suspicious behavior to report to the COR or the Base Police Department. This briefing shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees' commencing performance with the results reported to the COR no later than

30 days after contract award and new employees' commencing performance.

iv. All contractor and all associated sub-contractors employees requiring physical access to

Army Base for contract performance shall complete Operations Security (OPSEC) training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer if a COR is not assigned, within 10 calendar days after completion of training by all employees and subcontractor personnel. OPSEC training is available at http://cdsetrain.dtic.mil/opsec/ .

v. The Contractor shall ensure that all contractor and sub-contractors employee Common

Access Cards (CACs), badges, passes or other access credentials which were issued under this contract are surrendered to the COR upon completion of the contract. CACs, badges, passes and other access credentials are DoD property and failure to surrender them may be punishable under 18 USC § 701.

10. SUPERVISION

10.1 Minimum Communication Requirements

The Contractor shall have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the jobsite at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.

10.2 Superintendent Qualifications

The project superintendent must have a minimum of 6-years of experience in construction with at least 3 of those years as a superintendent on projects similar in size and complexity of the task order. The individual must be familiar with the requirements of EM 385-1-1 (current version) and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the altern ate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project .

10.3 Duties

The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on -site at all times during the performance of the contract until the work is completed and accepted.

https://jkodirect.jten.mil/Atlas2/faces/page/login/Login.seam http://cdsetrain.dtic.mil/opsec/

10.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non -compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

10.5 Preconstruction Conference

After award of the contract but prior to commencement of any work at the site, a meeting with the

Contracting Officer will be conducted to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.

10.6 Electronic Mail (Email) Address

The Contractor must establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days working days after contract award, the contractor shall provide the Contracting Officer with a single (one only) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.

11.0 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

11.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading. Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

11.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

11.3 Correction of Deficiencies

In the event that a deficiency is found, additional measures shall be taken, as deemed necessary by the

Contracting Officer, to determine the extent of the deficiency. Corrective actions shall be taken as directed by the Contracting Officer to correct the deficiency.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10%

(ten percent) of the pay request amount from each payment period until such revisions to the project schedule have been made.

12.0 PROJECT SCHEDULE DETAILED REQUIREMENTS

12.1 Level of Detail Required

The Contractor shall develop the Project Schedule to show the appropriate level of detail to address all major milestones and to allow for satisfactory project planning and execution. Failure to develop the

Project Schedule to an adequate level of detail will result in its disapproval by the Contracting Officer and necessitate a meeting with the Contractor, requirement owner, and Contracting.

12.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2% (two percent) of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

12.2.a. Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

i. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

ii. Submission and approval of as-built drawings.

iii. Submission and approval of DD1354 data and installed equipment lists.

iv. Contractor's pre-final inspection.

v. Correction of punch list from Contractor's pre-final inspection.

vi. Government's pre-final inspection.

vii. Correction of punch list from Government's pre-final inspection.

viii. Final inspection.

12.3 CORRECTION OF DEFICIENCIES

Where any form of deficiency is found, the Contractor shall take additional measures, as deemed necessary by the Contracting Officer, to determine the extent of the deficiency and perform corrective actions as directed by the Contracting Officer.

12.4 Government Activities

The Contractor shall indicate any Government and other agency activities that could impact progress.

These activities include, but are not limited to: environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

12.5 Original Durations

Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.

12.6 Leads, Lags, and Start to Finish Relationships

Lags must be reasonable as determined by the Government and not used in place of realistic original durations. Lags must not be in place to artificially absorb float, or to replace proper schedule logic.

a. Leads (negative lags) are prohibited.

b. Start to Finish (SF) relationships are prohibited.

12.7 Retained Logic

Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out -of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.

12.8 Percent Complete

The Contractor shall update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete, except for any remaining minor punch list work, and which do not restrain the initiation of successor activities, may be declared 100 percent complete to allow for proper schedule management.

12.9 Remaining Duration

The Contractor shall update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.

12.10 Cost Loading of Closeout Activities

The Contractor shall cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).

12.11 As-Built Drawings

If there isn’t a separate contract line item (CLIN) for as-built drawings, the Contractor shall cost load the

"Submission and approval of as-built drawings" activity not less than $35,000 or 1 percent of the present contract value, whichever is greater, up to $200,000. The activity will be declared 100 percent complete upon the Government's approval.

12.12 Early Completion Schedule and the Right to Finish Early

An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.

a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded

(including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.

b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.

13.0 PROJECT SCHEDULE SUBMISSIONS

13.1 General Information

The Contractor shall provide the submissions as described below. The data CD/DVD, reports, and network diagrams required for each submission are contained in paragraph 13.5 SUBMISSION

REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.

The Contractor’s review of comments made by the Government on the schedule(s) does not relieve the

Contractor from compliance with requirements of the Contract Documents.

13.2 Preliminary Project Schedule Submission

Within 15 calendar days after the NTP is acknowledged, the Contractor shall submit the Preliminary

Project Schedule, defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. The Contractor shall completely cost load the Preliminary Project Schedule to balance the contract award CLINs shown on the Price Schedule. The Preliminary Project Schedule may be a summary in nature for the remaining performance period. The Preliminary Project Schedule must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control

Plan, Safety Plan, and Environmental Protection Plan) as well as design activities, planned submissions of all early design packages, permitting activities, design review conference activities, and other non -construction activities intended to occur within the first 90 calendar days. The Government’s acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities. The Contractor shall activity code any activities that are summary in nature after the first 90 calendar days with Bid Item (CLIN) code (BIDI), Responsibility Code (RESP) and Feature of Work code (FOW).

13.3 Initial Project Schedule Submission

The Contractor shall submit the Initial Project Schedule for approval within 42 calendar days after the notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represents all work through the entire contract performance period. No payment will be made for work items not fully detailed in the Project Schedule.

13.4 Periodic Schedule Updates

The Contractor shall update the Project Schedule on a regular basis, monthly at a minimum. The

Contractor shall provide a draft Periodic Schedule Update for review at the schedule update meetings as prescribed in the paragraph 13.6.a PERIODIC SCHEDULE UPDATE MEETINGS. These updates will enable the Government to assess the Contractor's progress.

a. The Contractor shall update information including Actual Start Dates (AS), Actual Finish Dates

(AF), Remaining Durations (RD), and Percent Complete. These updates are subject to the approval of the Government at the meeting.

b. AS and AF dates must match the date(s) reported on the Contractor's Quality Control Report for an activity start or finish.

13.5 SUBMISSION REQUIREMENTS

The Contractor shall provide Periodic Schedule Updates throughout the life of the project stating either

On-target or Delay. If there is a Delay, then the Contractor shall provide a detailed explanation of the cause for the delay, and how long (in days) the Contractor estimates the delay will postpone the project.

13.6 PERIODIC SCHEDULE UPDATE

13.6.a Periodic Schedule Update Meetings

i. The Contractor shall conduct periodic schedule update meetings for the purpose of reviewing the proposed Periodic Schedule Update, Narrative Report, Schedule Reports, and progress payment.

ii. The Contractor shall conduct meetings at least monthly within five days of the proposed schedule data date.

iii. The Contractor shall provide a computer with the scheduling software loaded and a projector which allows all meeting participants to view the proposed schedule during the meeting.

iv. The Contractor's authorized scheduler must organize, group, sort, filter, and perform schedule revisions as needed and review functions as requested by the Contractor and/or Government.

v. The meeting is a working interactive exchange which allows the Government and Contractor the opportunity to review the updated schedule on a real time and interactive basis.

vi. The meeting will last no longer than 8 hours.

vii. The Contractor shall provide a draft of the proposed narrative report and schedule data file to the Government a minimum of two workdays in advance of the meeting.

viii. The Contractor's Project Manager and scheduler must attend the meeting with the authorized representative of the Contracting Officer.

ix. Superintendents, foremen and major subcontractors must attend the meeting as required to discuss the project schedule and work.

x. Following the periodic schedule update meeting, the Contractor shall make corrections to the draft submission. The Contractor shall include only those changes approved by the

Government in the submission and invoice for payment.

14.0 GOVERNMENTAL SAFETY REQUIREMENTS

14. 1 PART 1 GENERAL: REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred within the text by the basic designation only.

14.2 AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)

ASSP A10.22 (2007; R 2017) Safety Requirements for Rope-Guided and

Non-Guided Workers’ Hoists

ASSP A10.34 (2001; R 2012) Protection of the Public on or Adjacent to

Construction Sites

ASSP A10.44 (2014) Control of Energy Sources (Lockout/Tagout) for

Construction and Demolition Operations

ASSP Z244.1 (2016) The Control of Hazardous Energy Lockout, Tagout and Alternative Methods

ASSP Z359.0 (2012) Definitions and Nomenclature Used for Fall

Protection and Fall Arrest

ASSP Z359.1 (2016) The Fall Protection Code

ASSP Z359.2 (2017) Minimum Requirements for a Comprehensive

Managed Fall Protection Program

ASSP Z359.3 (2017) Safety Requirements for Lanyards and Positioning

Lanyards

ASSP Z359.4 (2013) Safety Requirements for Assisted-Rescue and Self-

Rescue Systems, Subsystems and Components

ASSP Z359.6 (2016) Specifications and Design Requirements for Active

Fall Protection Systems

ASSP Z359.7 (2011) Qualification and Verification Testing of Fall

Protection Products

ASSP Z359.11 (2014) Safety Requirements for Full Body Harnesses

ASSP Z359.12 (2009) Connecting Components for Personal Fall Arrest

Systems

ASSP Z359.13 (2013) Personal Energy Absorbers and Energy Absorbing

Lanyards

ASSP Z359.14 (2014) Safety Requirements for Self-Retracting Devices for

Personal Fall Arrest and Rescue Systems

ASSP Z359.15 (2014) Safety Requirements for Single Anchor Lifelines and

Fall Arresters for Personal Fall Arrest Systems

14.3 ASME INTERNATIONAL (ASME)

ASME B30.3 (2016) Tower Cranes

ASME B30.5 (2014) Mobile and Locomotive Cranes

ASME B30.7 (2011) Winches

ASME B30.8 (2015) Floating Cranes and Floating Derricks

ASME B30.9 (2014; INT Feb 2011 - Nov 2013) Slings

ASME B30.20 (2013; INT Oct 2010 - May 2012) Below-the-Hook Lifting

Devices

ASME B30.22 (2016) Articulating Boom Cranes

ASME B30.23 (2011) Personnel Lifting Systems Safety Standard for

Cableways, Cranes, Derricks, Hoists, Hooks, Jacks, and

Slings

ASME B30.26 (2015; INT Jun 2010 - Jun 2014) Rigging Hardware

14.4 ASTM INTERNATIONAL (ASTM)

ASTM F855 (2015) Standard Specifications for Temporary Protective

Grounds to Be Used on De-energized Electric Power Lines and Equipment

14.5 INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 1048 (2003) Guide for Protective Grounding of Power Lines

IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National Electrical

Safety Code

14.6 NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2018; TIA 18-1) Standard for Portable Fire Extinguishers

NFPA 51B (2014) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work

NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2; TIA 17-3; TIA

17-4; TIA 17-5; TIA 17-6; TIA 17-7; TIA 17-8; TIA 17-9;

TIA 17-10; TIA 17-11; TIA 17-12; TIA 17-13; TIA 17-14;

TIA 17-15; TIA 17-16; TIA 17-17 ) National Electrical Code

NFPA 70E (2018; TIA 18-1; TIA 81-2) Standard for Electrical Safety in the Workplace

NFPA 241 (2013; Errata 2015) Standard for Safeguarding Construction, Alteration, and Demolition Operations

NFPA 306 (2019) Standard for the Control of Gas Hazards on Vessels

14.7 TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)

TIA-222 (2005G; Add 1 2007; Add 2 2009; Add 3 2014; Add 4 2014;

R 2014; R 2016) Structural Standards for Steel Antenna

Towers and Antenna Supporting Structures

TIA-1019 (2012; R 2016) Standard for Installation, Alteration and

Maintenance of Antenna Supporting Structures and Antennas

14.8 U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (Current Version) Safety and Health Requirements Manual

14.9 U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

10 CFR 20 Standards for Protection Against Radiation

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.146 Permit-required Confined Spaces

29 CFR 1910.147 The Control of Hazardous Energy (Lock Out/Tag Out)

29 CFR 1910.333 Selection and Use of Work Practices

29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous

Atmospheres in Shipyard Employment

29 CFR 1915.89 Control of Hazardous Energy (Lockout/Tags-Plus)

29 CFR 1926 Safety and Health Regulations for Construction

29 CFR 1926.16 Rules of Construction

29 CFR 1926.450 Scaffolds

29 CFR 1926.500 Fall Protection

29 CFR 1926.552 Material Hoists, Personal Hoists, and Elevators

29 CFR 1926.553 Base-Mounted Drum Hoists

29 CFR 1926.1400 Cranes and Derricks in Construction

49 CFR 173 Shippers - General Requirements for Shipments and

Packagings

CPL 02-01-056 (2014) Inspection Procedures for Accessing Communication

Towers by Hoist

CPL 2.100 (1995) Application of the Permit-Required Confined Spaces

(PRCS) Standards, 29 CFR 1910.146

15.0 DEFINITIONS

15.1 Competent Person (CP)

The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.

15.2 Competent Person, Confined Space

The CP, Confined Space, is a person meeting the competent person requirements as defined EM 385-1-1

Appendix Q, with thorough knowledge of OSHA’s Confined Space Standard, 29 CFR 1910.146, and designated in writing to be responsible for the immediate supervision, implementation and monitoring of the confined space program, who through training, knowledge and experience in confined space entry is capable of identifying, evaluating and addressing existing and potential confined space hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

15.3 Competent Person, Cranes and Rigging

The CP, Cranes and Rigging, as defined in EM 385-1-1 Appendix Q, is a person meeting the competent person, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the Crane and Rigging Program, who through training, knowledge and experience in crane and rigging is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

15.4 Competent Person, Excavation/Trenching

A CP, Excavation/Trenching, is a person meeting the competent person requirements as defined in EM

385-1-1 Appendix Q and 29 CFR 1926, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the excavation/trenching program, who through training, knowledge and experience in excavation/trenching is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

15.5 Competent Person, Fall Protection

The CP, Fall Protection, is a person meeting the competent person requirements as defined in EM 385-1-1

Appendix Q and in accordance with ASSP Z359.0, who has been designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment , is capable of identifying, evaluating and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

15.6 Competent Person, Scaffolding

The CP, Scaffolding is a person meeting the competent person requirements in EM 385-1-1 Appendix Q, and designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the scaffolding program. The CP for Scaffolding has enough training, knowledge and experience in scaffolding to correctly identify, evaluate and address existing and potential hazards and also has the authority to take prompt corrective measures with regard to these hazards. CP qualification s must be documented and include experience on the specific scaffolding systems/types being used, assessment of the base material that the scaffold will be erected upon, load calculations for materials and personnel, and erection and dismantling. The CP for scaffolding must have a documented, minimum of

8-hours of scaffold training to include training on the specific type of scaffold being used (e.g. mast -climbing, adjustable, tubular frame), in accordance with EM 385-1-1 Section 22.B.02.

15.7 Competent Person (CP) Trainer

A competent person trainer as defined in EM 385-1-1 Appendix Q, who is qualified in the material presented, and who possesses a working knowledge of applicable technical regulations, standards, equipment and systems related to the subject matter on which they are training Competent Persons. A competent person trainer must be familiar with the typical hazards and the equipment used in the industry they are instructing. The training provided by the competent person trainer must be appropriate to that specific industry. The competent person trainer must evaluate the knowledge and skills of the competent persons as part of the training process.

15.8 High Risk Activities

High Risk Activities are activities that involve work at heights, crane and rigging, excavations and trenching, scaffolding, electrical work, and confined space entry.

15.9 High Visibility Accident

A High Visibility Accident is any mishap which may generate publicity or high visibility.

15.10 Load Handling Equipment (LHE)

LHE is a term used to describe cranes, hoists and all other hoisting equipment (hoisting equipment means equipment, including crane, derricks, hoists and power operated equipment used with rigging to raise, lower or horizontally move a load).

15.11 Medical Treatment

Medical Treatment is treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even when provided by a physician or registered personnel.

15.12 Near Miss

A Near Miss is a mishap resulting in no personal injury and zero property damage, but given a shift in time or position, damage or injury may have occurred (e.g., a worker falls off a scaffold and is not injured; a crane swings around to move the load and narrowly misses a parked vehicle).

15.13 Operating Envelope

The Operating Envelope is the area surrounding any crane or load handling equipment. Inside this

"envelope" is the crane, the operator, riggers and crane walkers, other personnel involved in the operation, rigging gear between the hook, the load, the crane's supporting structure (i.e. ground or rail), the load's rigging path, the lift and rigging procedure.

15.14 Qualified Person (QP)

The QP is a person designated in writing, who, by possession of a recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.

15.15 Qualified Person, Fall Protection (QP for FP)

A QP for FP is a person meeting the requirements of EM 385-1-1 Appendix Q, and ASSP Z359.0, with a recognized degree or professional certificate and with extensive knowledge, training and experience in the fall protection and rescue field who is capable of designing, analyzing, and evaluating and specifying fall protection and rescue systems.

15.16 USACE Property and Equipment

Interpret "USACE" property and equipment specified in USACE EM 385-1-1 as Government property and equipment.

15.17 Load Handling Equipment (LHE) Accident or Load Handling Equipment Mishap

A LHE accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment; two-blocking;

overload; or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents, even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, or roll over). Document an

LHE mishap using the Crane High Hazard working group mishap reporting form.

16.0 ACCIDENT PREVENTION PLAN (APP)

16.1. General

A qualified person must prepare the written site-specific APP. The qualified person shall prepare the

APP in accordance with the format and requirements of EM 385-1-1, Appendix A, and as supplemented herein. The APP shall cover all paragraph and subparagraph elements in EM 385-1-1, Appendix A. The

APP must be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP must interface with the Contractor's overall safety and health program referenced in the APP in the applicable APP element, and must be site-specific. The APP shall describe the methods to evaluate past safety performance of potential subcontractors in the selection process. The APP must also describe innovative methods used to ensure and monitor safe work practices of subcontractors. The

Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. The Contractor is responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP must be signed by an officer of the firm (Prime Contractor senior person), the individual preparing the APP, the on-site superintendent, the designated Site safety and Health Officer

(SSHO), the Contractor Quality Control Manager, and any designated Certified Safety Professional (CSP) or Certified Health Physicist (CIH). The Site safety and Health Officer (SSHO) must provide and maintain the APP and a log of signatures by each subcontractor foreman, attesting that they have read and understand the APP, and make the APP and log available on-site to the Contracting Officer. If English is not the foreman's primary language, the Prime Contractor must provide an interpreter.

The Contractor shall submit the APP to the Contracting Officer 15 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP. Once the

APP has been reviewed and accepted by the Contracting Officer, the APP and attachments will be enforced as part of the contract. Disregarding the provisions of this contract or the accepted APP is cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified. The

APP shall be continuously reviewed and amended, as necessary, throughout the life of the contract.

Changes to the accepted APP must be made with the knowledge and concurrence of the Contracting

Officer, project superintendent, Site safety and Health Officer (SSHO) and Quality Control Manager.

The Contractor shall incorporate unusual or high-hazard activities not identified in the original APP as they are discovered. Should any severe hazard exposure (i.e. imminent danger) become evident, the

Contractor shall stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard. The Contractor shall notify the Contracting Officer within 24 hours of discovery and eliminate and remove the hazard. In the interim, the Contractor shall take all necessary actions to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by ASSP A10.34), and the environment.

16.2 Names and Qualifications

The Contractor shall provide plans in accordance with the requirements outlined in Appendix A of EM

385-1-1, including the following:

a. Names and qualifications (resumes including education, training, experience and certifications) of site safety and health personnel designated to perform work on this project to include the designated

Site Safety and Health Officer and other competent and qualified personnel to be used. Specify the duties of each position.

b. Qualifications of competent and of qualified persons. At a minimum, the Contractor shall designate and submit qualifications of competent persons for each of the following major areas: excavation;

scaffolding; fall protection; hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents; and personal protective equipment and clothing to include selection, use and maintenance.

16.2 Plans

The Contractor shall provide plans in the APP in accordance with the requirements outlined in

Appendix A of EM 385-1-1, including the following:

16.2.a Confined Space Entry Plan

The Contractor shall develop a confined or enclosed space entry plan in accordance with EM 385-1-1, applicable OSHA standards 29 CFR 1910, 29 CFR 1915, and 29 CFR 1926, OSHA Directive CPL

2.100, and any other Federal, state and local regulatory requirements identified in this contract. The

Contractor shall identify the qualified person's name and qualifications, training, and experience. The

Contractor shall delineate the qualified person's authority to direct work stoppage in the event of hazardous conditions. The Contractor shall include procedures for rescue by contractor personnel and the coordination with emergency responders. (If there isn’t confined space work, include a statement that no confined space work exists and none will be created.)

16.2.b Standard Lift Plan (SLP)

The Contractor shall develop a Standard Lif Plan to avoid situations where the operator cannot maintain safe control of the lift. The Contractor shall prepare a written SLP in accordance with EM

385-1-1, Section 16.A.03, using Form 16-2 for every lift or series of lifts (if duty cycle or routine lifts are being performed). The SLP must be developed, reviewed and accepted by all personnel involved in the lift in conjunction with the associated AHA. Signature on the AHA constitutes acceptance of the plan. The Contractor shall maintain the SLP on the LHE for the current lift(s) being made. The

Contractor shall maintain historical SLPs for a minimum of 3 months.

16.2.c Critical Lift Plan - Crane or Load Handling Equipment

The Contractor shall provide a Critical Lift Plan as required by EM 385-1-1, Section 16.H.01, using

Form 16-3. In addition, Critical Lift Plans are required for the following:

i. Lifts over 50 percent of the capacity of barge mounted mobile crane's hoist.

ii. When working around energized power lines where the work will get closer than the minimum clearance distance in EM 385-1-1 Table 16-1.

iii. For lifts with anticipated binding conditions.

iv. When erecting cranes.

16.2.d. Critical Lift Plan Planning and Schedule

Critical lifts require detailed planning and additional or unusual safety precautions. The Contractor shall develop and submit a critical lift plan to the Contracting Officer 30 calendar days prior to critical lift.