Q_A W50S9J25BA015 Boiler and Chiller.pdf
PDF 40 KB Posted
- Attached to
- W50S9J-25-B-A015 Boiler and Chiller Maintenance
- Solicitation number
- W50S9J-25-B-A015
- Issued by
-
Department of the Army National Guard
About this file
This document is a Questions and Answers (Q&A) file for a Boiler and Chiller Maintenance federal contract opportunity, solicitation number W50S9J-25-B-A015. The Q&A addresses a specific technical requirement regarding glycol usage in the maintenance project. The document specifies that the contractor shall fully refill boiler and chiller systems with 30% propylene glycol, directly answering a contractor's question about whether the glycol needs to be inhibited and at what percentage.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q & A for Boiler and Chiller Maintenance
W50S9J-25-B-A015
The new glycol that is to be put in the loops- Does that glycol need to be inhibited? If so, at what percentage?
The contractor shall fully refill boiler and chiller systems with 30% propylene glycol.