Q_A W50S9J25BA015 Boiler and Chiller.pdf

PDF 40 KB Posted

Attached to
W50S9J-25-B-A015 Boiler and Chiller Maintenance
Solicitation number
W50S9J-25-B-A015
Issued by

About this file

This document is a Questions and Answers (Q&A) file for a Boiler and Chiller Maintenance federal contract opportunity, solicitation number W50S9J-25-B-A015. The Q&A addresses a specific technical requirement regarding glycol usage in the maintenance project. The document specifies that the contractor shall fully refill boiler and chiller systems with 30% propylene glycol, directly answering a contractor's question about whether the glycol needs to be inhibited and at what percentage.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q & A for Boiler and Chiller Maintenance

W50S9J-25-B-A015

The new glycol that is to be put in the loops- Does that glycol need to be inhibited? If so, at what percentage?

The contractor shall fully refill boiler and chiller systems with 30% propylene glycol.