STATEMENT OF WORK - LODGING FACILITY BLIND REPLACEMENT - UPDATED 7.2.2026.pdf

PDF 182 KB Posted

Attached to
VOLK FIELD BILLETING BLIND REPLACEMENT - MULTIPLE BUILDINGS
Solicitation number
W50S9H26QA018
Issued by

About this file

This is a Statement of Work (SOW) for a billeting blind replacement project at Volk Field Air National Guard Base in Camp Douglas, Wisconsin. The contractor must provide complete removal and disposal of existing window treatments and installation of new window treatments across multiple buildings, with the objective of providing privacy, energy efficiency, light control, and glare reduction.

The base requirement (Project Area 1) covers Buildings 140-149 with an estimated 100 windows requiring 1-inch bright white aluminum blinds with cordless lift and wand tilt mechanisms mounted on the left side. Six optional project areas are available: Project Area 2 (Building 449, 29 windows) requiring easy clean roller shades in grey with specific aluminum white blinds for kitchen and office areas; Project Area 3 (Building 475, 28 windows) requiring cellular shades in blue grey and burgundy with cordless operation; Project Area 4 (Buildings 429, 430, 431, 434, 436, 438, 440, 442, 446, 448 with 184 windows); Project Area 5 (Buildings 303, 305, 307, 310, 311, 312, 315 with 106 windows); Project Area 6 (Buildings 405-413, 417, 419-427 with 221 windows); and Project Area 7 (Buildings 125-132 with 152 windows). Each project area will be a separate Contract Line Item Number (CLIN) awarded based on funding availability. Pricing must remain valid through September 30, 2026, with unfunded CLINs held available for potential award if additional funding becomes available. The contractor is responsible for all labor, materials, equipment, delivery, and site cleanup, including repair of any damage caused by installation activities. Normal work hours are 7:00 AM to 4:00 PM Monday through Friday, with an estimated project duration of approximately 120 calendar days from Notice to Proceed. The contractor must comply with base security requirements, including background checks, AT Level I training completion within 10 calendar days, Form 1 Installation Entry Request submission 15 days prior to arrival, and adherence to all base access and security procedures.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

BILLETING BLIND REPLACEMENT

PROJECT LOCATION

Work is to be completed at multiple buildings on Volk Field Air National Guard Base (ANGB), Camp Douglas, WI 546518-5001.

SCOPE OF WORK

The objective of this project is to provide a full depth replacement of all billeting building blinds on Volk Field to provide privacy, energy ef�iciency, light control, and glare reduction.

ALUMINUM BLINDS INSTALLATION

Replacement shall include the removal and disposal of existing window treatments and hardware (if applicable), and the installation of new window treatments that meet the following speci�ications.

All buildings expect Bldg. 449 and 475 Material(s): 1 inch Aluminum Color: Bright White Mounting: Inside mount using standard brackets Lift Mechanism: Cordless Lift Tilt Mechanism: Wand tilt Tilt Position: Left Side

For Building 475 Type: Cellular Shades Color: Blue Grey and Burgandy Mounting: Inside Operating System: Cordless Operating Pole: No/ None

For Building 449 Type: Easy Clean Roller Shades Color: Grey

***NOTE: The Blinds for Building 449 kitchen and of�ice areas must be aluminum white in color blinds.

GENERAL REQUIREMENTS

Contractor is responsible for all labor, materials, and equipment necessary to complete the work, to include delivery and of�load of necessary supplies and equipment. Any damage to window frames, interior walls, �loors, or surrounding areas caused by equipment operation, installation, or material storage shall be repaired to original condition as part of the project.

PRICING & AWARD STRUCTURE:

Pricing shall be submitted for Project Area as outlined below. Each project area will be a separate Contract Line-Item Number (CLIN) and each will be awarded based on availability of funds at time of award. Pricing must be valid through 30 September 2026. Any CLINs not funded at time of award shall be held available for award through 30 September 2026, in the event additional funding becomes available.

BASE REQUIREMENT

• Project Area 1: Bldgs. 140-149 (Est. 100 Windows)

OPTIONS

• Project Area 2: Bldg. 449 (Est. 29 Windows)

• Project Area 3: (Est. 28 Windows) Bldg. 475

• Project Area 4: Bldgs. 429, 430, 431, 434, 436, 438, 440, 442, 446, 448 (Est. 184

Windows)

• Project Area 5: Bldgs. 303, 305, 307, 310, 311, 312 & 315 (Est. 106 Windows)

• Project Area 6: Bldgs. 405-413, 417 and 419- 427 (Est. 221 Windows)

• Project Area 7: Bldgs. 125-132 (Est. 152 Windows)

The contractor is responsible for verifying the site conditions and quantities prior to submitting quotes. The above quantities are estimates. Attendance at scheduled site visit is highly encouraged.

Installation methods and materials shall be in accordance with standard commercial practices.

VOLK FIELD GENERAL INFORMATION

1. Smoking on Volk Field premises is allowed only in designated areas.

2. Seat belts must be worn, and cell phones may only be used in stationary vehicles and equipment.

Note: You may not talk or text with phones while driving on Volk Field premises.

3. No one will be allowed access without of�icial prior arrangement and representation by a prime contractor.

4. Individuals are not allowed access to any restricted areas once on base. Access is allowed “Only” in areas required to conduct the work of this project.

5. All vehicles and persons are subject to search at the discretion of security personnel.

6. Persons interested in viewing the project site shall have a current picture I.D & provide full name

(including full middle name), valid Driver’s License number and date of birth at least three (3) business workdays prior to scheduled arrival.

7. Volk Field is a secure installation and background checks of contractor employees will be conducted once a contract has been awarded.

8. Volk Field hours of operation are from 6:30 am to 4:00 pm, Monday-Friday

WORK SCHEDULING

1. Normal base work hours for the Contractor are de�ined as 7:00-4:00 Monday-Friday, excluding

Saturdays, Sundays, and Federal Holidays.

2. If the Contractor desires to work during periods other than above, they must coordinate with the

Volk Field Contracting Of�icer in advance of his intention to work during other periods.

a. If the Contracting Of�icer determines that they are reasonably available, the Contracting

Of�icer may authorize the Contractor to perform work beyond normal duty hours/days.

3. The project work duration is estimated to be approximately 120 calendars days from the date the contractor is provided Notice to Proceed.

a. Additional coordination will be required after the completion of work to facilitate project closeout requirements.

GENERAL CONDITIONS

The contractor shall comply with all applicable local, State and Federal laws and regulations. The contractor shall provide supervision overseeing all work. The contractor shall �ield verify all site conditions, quantities, measurements, and requirements. The contractor shall protect and barricade all work areas to ensure safety. The contractor shall protect all structures, utilities, vegetation, sidewalks, and vehicles from damage. The contractor shall be responsible to replace any damaged materials with new materials, at no additional cost to the Government.

DISPOSAL OF MATERIALS AND CLEANUP

The contractor shall not use any Government disposal bins, dumpsters or trash receptacles for any reason at any time. The contractor shall provide appropriate disposal bins/trash receptacles.

Approval of disposal bins/trash receptacle location(s) shall be coordinated through the customer.

The contractor shall clean up after each work period and dispose of all debris at the close of each day.

MATERIAL & EQUIPMENT ACCOUNTABILITY

The contractor shall notify the Government prior to delivery of any material or equipment to the site. The contractor shall ensure someone is available to receive delivered materials and able to store them safely in an area designated by the Government. Any materials delivered without prior coordination and without having someone to take receipt, shall not be accepted and turned away.

ANTITERRORISM / OPERATIONS SECURITY / INFORMATION PROTECTION INFORMATION

1. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Of�icer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Of�ice. The contractor shall ensure compliance with all personal identity veri�ication requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

2. For Contractors that do not require CAC but require access to a DoD Facility and/or Installation.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identi�ication Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), Contractors are required to be veri�ied prior to Installation access. To facilitate faster installation entry; Form 1 Installation Entry Request must be submitted 15 days prior to the contractor’s arrival through the main gate. Entry may be denied if the Form 1 Installation Entry Request is not received. Please use the attached Installation Entry / Access spreadsheet, when complete email to: usaf.wi.wi-crtc.list.entry-request@mail.mil

3. AT Level I Training. All contractor supervisors, job site lead employees, to include subcontractor supervisor and job site lead employees, requiring access to Government Installations, Facilities and Controlled access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certi�icates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT Level I Awareness training is available through https://jko.jten.mil/courses/AT-level1/launch.html by completing JS-US007: Level I Anti- Terrorism Awareness Training.

Questions concerning this SOW can be directed to Volk Field Contracting at 608-427-1235 or by email at WI.CRTC.VF.Contracting@us.af.mil mailto:WI.CRTC.VF.Contracting@us.af.mil