b 08 QA HEC Procedures 8SEP20.docx

DOCX document 14 KB Posted

Attached to
Hazardous Energy Control Procedures
Solicitation number
W50S9G20Q0010
Issued by

View the file

Other files

File Type Posted
B 04 SCA Wage Determination.pdf PDF
FAR Clause 52_204_25 Prohibition.docx DOCX document
A 02 Scope of Work - CE HEC_Final.pdf PDF
FAR 52.204-24 Offeror Representations.pdf PDF
A 02 CES HEC Equipment Survey_Nov_19_Safety.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hazardous Energy Control Procedures W50S9G-20-Q-0010 Questions & Answers

1. The boilers mentioned in lines 209 thru 214, are those large boilers or are they the smaller type similar to a large hot water heater?

a. All of the boilers mentioned are 1 Million BTU each.

2. Is there going to be a site visit for this project?

a. We are not anticipating holding a site visit at this time.

3. For CLIN 0005 Option 4, does this CLIN involve the labeling of energy sources for only CLIN 0001 or for CLINS 0001, 0002 and 0003?

a. Please separate out labeling for each CLIN. See adjusted CLIN structure to add two more option CLINs.

4. LOTO Policy – Has this already been developed or will contractor need to develop?

a. The Policy has already been developed

5. How many authorized employees are required the training?

a. About 25 individuals

6. Will the devices for labeling be given to contractor or will the contractor have to provide devices?

a. Contractor would provide the devices

7. When is this contract expected to begin?

This contract will begin prior to Sept 30 with a pre-performance meeting. The exact start date will be discussed at that time.