NCC Comm Racks Statement of Work 31Mar26.pdf
PDF 219 KB Posted
- Attached to
- 156th CS - Communication Racks with Installation
- Solicitation number
- W50S9326QA004
- Issued by
-
Department of the Army National Guard
About this file
This is a Statement of Work (SOW) for communications rack and cable management installation at the Puerto Rico Air National Guard's 156th Wing, Muñiz Air National Guard Base, issued on 31 March 2026.
The contractor shall furnish and install fourteen (14) PANDUIT R4P 4-post communications racks and sixteen (16) PANDUIT PE2VD06 vertical cable managers in the Network Control Center room of the new Communications Squadron building. The racks shall be arranged in two parallel rows of seven racks each, with the back row installed flush with existing overhead cable management racks and a minimum four-foot clearance maintained between rows. One vertical cable manager shall be installed between each of the seven racks within each row, plus one at both ends of each row. All racks and cable managers must be securely anchored to the concrete floor using stainless steel anchor/expansion bolts and grounded in accordance with applicable local, state, and federal codes and standards. Additionally, the contractor shall install a new ceiling-mounted cable management tray spanning seven feet in length, connecting the terminus of existing overhead cable management trays to the back wall of the room. The new tray section must be twenty-four inches wide and identical in width, depth, and material to the currently installed cable management trays to ensure a seamless pathway. All work must comply with applicable local, state, and federal codes and standards. The point of contact is SMSgt Eugenio R. Juarbe at 787-253-7500 or eugenio.juarbe@us.af.mil.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFIs.pdf | ||
| COMMUNICATIONS ROOM RACK AND CABLE TRAY LAYOUT.pdf | ||
| PXL_20260428_111435119.jpg | JPG image | |
| PXL_20260428_111417460.jpg | JPG image | |
| RFQ_CommRacks W50S9326QA004.pdf | ||
| PXL_20260407_144044412.jpg | JPG image | |
| PXL_20260407_144039373.jpg | JPG image | |
| RFQ_CommRacks W50S9326QA004.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PUERTO RICO AIR NATIONAL GUARD
156TH WING
MUÑIZ AIR NATIONAL GUARD BASE
200 JOSE A SANTANA AVE, CAROLINA, PR 00979-1502
31 March 2026
MEMORANDUM FOR 156MSG/MSC
FROM: 156CS/SCX
200 Jose (Tony) Santana Ave Carolina, PR 00979
SUBJECT: Statement of Work (SOW) for Communications Rack and Cable Management Installation
1. Purpose. This memorandum outlines the requirements for the installation of new communications racks, associated cable management, and a new overhead cable tray section. The contractor shall provide all necessary labor, materials, and equipment to complete the project as defined herein.
2. Scope of Work. The contractor shall perform the installation in accordance with all applicable local, state, and federal codes and standards. The work includes the installation of fourteen (14) new 4-post communications racks, associated vertical cable management, and a new overhead cable tray section.
All equipment will be installed in the Network Control Center room of the new Communications Squadron building.
3. Required Materials. The contractor shall furnish and install these specific components:
a. Rack, 4-Post, PANDUIT R4P: 14 ea.
b. Manager, Vertical Cable, PANDUIT PE2VD06: 16 ea.
4. Rack and Cable Management Installation.
a. a. The fourteen (14) communications racks shall be arranged in two (2) parallel rows of seven
(7) racks each. The back row shall be installed flush with existing overhead cable management racks, and a minimum clearance of four (4) feet shall be maintained between the two rows.
b. One (1) vertical cable manager shall be installed between each of the seven (7) racks within each row, and one (1) shall be installed at both ends of each row.
c. All racks and cable managers shall be securely anchored to the concrete floor using stainless steel anchor/expansion bolts. All communications racks shall be grounded in accordance with all applicable local, state, and federal codes and standards.
5. Overhead Cable Management. The contractor shall install a new, ceiling-mounted cable management tray. The new tray must connect the terminus of the existing overhead cable management trays to the back wall of the room, a span seven (7) feet long). The new tray section's must be twenty-four
(24) inches wide and must be identical in all other characteristics (width, depth, and material) to the currently installed cable management trays to ensure a seamless and contiguous pathway.
6. Point of Contact. For further information for this requirement, contact SMSgt Eugenio R. Juarbe at 787-253-7500 | Email: eugenio.juarbe@us.af.mil
EUGENIO R. JUARBE, SMSgt, PRANG Plans & Programs Superintendent
| 2026-03-31T11:37:19-0400 | |
| JUARBE.EUGENIO.1297026298 |