Industry Questions Demolition Diesel Tank Aguadilla.docx
DOCX document 12 KB Posted
- Attached to
- Underground Diesel Tank Demolition
- Solicitation number
- W50S9321B9981
- Issued by
-
Department of the Army National Guard
About this file
This document contains an industry questions file and a related federal contract opportunity solicitation. The Puerto Rico Air National Guard intends to issue an Invitation for Bid to demolish and dispose of an underground 10,000 gallon diesel tank at their Punta Borinquen Installation in Aguadilla, Puerto Rico. The scope of work involves removing the underground storage tank and concrete slab approximately 6 inches thick, addressing any residual product or contaminated soil, and proper disposal. The contract value is estimated between $100,000 to $250,000 and the period of performance is 180 calendar days from notice to proceed. Questions are due by August 4th and bids will be accepted electronically with a formal bid opening scheduled for August 27th. This is a 100% small business set-aside administered by the Department of the Army National Guard.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry Questions Demolition Diesel Tank Aguadilla.docx | DOCX document | |
| Solicitation.docx | DOCX document | |
| TKWR2123202_SOW_Demo_Existing _Underground_Diesel_Tank_DRAFT_FINAL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Industry Questions Demolition Diesel Tank Aguadilla
1. What will be the allowance for contaminated soil extraction and disposal? None. No contaminated soil is expected.
2. Is there an estimated quantity of contaminated soil, so as to base our bids on? No. No contaminated soil is expected.
3. Can a unit price be included, given that we have no quantity to base our price on? No.
4. What is the size of the tanks? 10,000 gals.
5. How much fuel is anticipated to be left in the tanks? Which fuel (diesel/gas)? Almost nothing.
6. How thick is the concrete slab? Around 6”.
7. Is it possible to extend the proposed delivery time? Companies will have to complete testing and then suppliers will have to provide quotes. This process could take time. Is possible.
8. What job barrier type will be needed for the demo work at PRANG? Must be summited by the contractor. Shall comply with safety and erosion and sedimentation control.
9. Is there any preference for the disposal site to be used? No, as long it complies with proper disposal.