TKWR2123202_SOW_Demo_Existing _Underground_Diesel_Tank_DRAFT_FINAL.pdf
PDF 251 KB Posted
- Attached to
- Underground Diesel Tank Demolition Federal contract opportunity
- Solicitation number
- W50S9321B9981
- Issued by
- Department of the Army National Guard
About this file
This document outlines a federal solicitation for underground diesel tank demolition services. The Puerto Rico Air National Guard intends to issue an invitation for bid to award a firm fixed-price contract to demolish and dispose of an underground diesel tank at their Punta Borinquen installation in Aguadilla, Puerto Rico. The scope of work includes removing the residual product, excavating soil, purging vapors, collecting samples, and disposing of soil in accordance with Puerto Rico regulations. The period of performance is 180 calendar days with work to be performed onsite. The estimated value is between $100,000 and $250,000. The NAICS code is 238910 and it is set aside for small businesses. Interested parties should attend the scheduled site visit on July 30, 2021 and submit bids electronically by August 27, 2021. The evaluation will be based on price with the intent to award without discussions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Industry Questions Demolition Diesel Tank Aguadilla.docx | DOCX document | |
| Industry Questions Demolition Diesel Tank Aguadilla.docx | DOCX document | |
| Solicitation.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Demo Existing Underground Diesel Tank TKWR 2123202
Air National Guard Base (ANGB), Puerto Rico (PR)
1.0 GENERAL
1.1 Scope. This statement of work (sow) consists in demolition of Punta Borinquen Fuel
Service station to include removal and disposition of existing underground storage tanks, furnishing all plant, labor, equipment, appliances, materials and performing all operations in strict accordance with the specifications and the applicable drawings, and subject to the terms and conditions of the contract. The work considers detailing UST tank removal procedures including the removal of residual product, soil excavation, purging of volatile vapors, field screening criteria, sample collection, and soil disposal, following the “Guía de Cierre
Permanente para Sistemas de Tanques de Almacenamiento Soterrados” from the Department of Natural and Environmental Resources (formerly Junta de Calidad Ambiental).
1.2 Background: Punta Borinquen Air Control Squadron has an Underground Storage System
Tank (UST), which has past environmental non-compliance issues resulting in an order of consent and fines from the regulatory agency. In addition, the UST will be reaching its recommended 20 years lifespan. In addition, the UST has permit requirements that are a challenge to comply and fulfill due to limited resources (work force, funds and specialized contractor availability).
1.3 Period of Performance (PoP). The Period of Performance shall be 180 calendar days (6 months).
1.4 General Information.
1.4.1 Quality Control (QC). The contractor shall develop and maintain an effective QC Plan
(QCP) to ensure services are performed in accordance with this SOW. The contractor shall develop and implement procedures to identify, prevent, and ensure no recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements
Summary. A final QCP shall be submitted to the Contracting Officer Representative (COR)
NLT 10 days after contract award. After acceptance of the QCP, the contractor shall obtain the
Contracting Officer’s (KO) acceptance in writing of any proposed changes to its QCP.
1.4.2 Quality Assurance (QA). The Government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) (defect rate(s)).
1.4.3 Recognized Holidays: The following are recognized US holidays. The contractor shall not perform services on these days.
1.4.3.1 New Year’s Day
1.4.3.2 Martin Luther King Jr.’s Birthday
1.4.3.3 President’s Day
1.4.3.4 Memorial Day
1.4.3.5 Independence Day
1.4.3.6 Labor Day
1.4.3.7 Columbus Day
1.4.3.8 Veteran’s Day
1.4.3.9 Thanksgiving Day
1.4.3.10 Christmas Day
1.4.4 Place and Performance of Services. The contractor shall provide services between the hours of 0730-1600 on Monday through Friday, except on recognized US holidays or when the
Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at
Punta Borinquen Air Control Squadron, Aguadilla, Puerto Rico 00604. The contractor, shall at all times, maintain an adequate work force for the uninterrupted performance of all tasks defined within this SOW when the Government facility/installation is not closed for the above reasons.
When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.
1.4.4.1 Reserved
1.4.4.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays.
Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.4.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance.
1.4.5 Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DOD and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes. The contractor shall coordinate all on-site activity, as required, in conjunction with the COR and the appropriate Punta Borinquen Squadron representatives. Installation Entry Access List (EAL) is required fifteen to thirty (15-30) calendar days ahead for processing, prior to base access approval being granted, along with DD
Form 369, Police Record Check and driver license copy.
1.4.5.1 Reserved.
1.4.5.2 For contractors that do not require a CAC, but require access to a DoD facility or installation: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures. Using the National Crime Information Center
Interstate Identification (NCIC-III) and Terrorist Screening Database (TSDB) (Army
Directive 2014- 05/AR 190-13), and applicable installation, facility and area commander installation/facility access, and local security policies and procedures (provided by a government representative).
1.4.5.3 COMSEC/IT Security. All communications with DOD organizations are subject to communications security (COMSEC) review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, the contractor is advised that any time contractor place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DOD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
1.4.5.4 Protection of Personally Identifiable Information (PII). The contractor shall protect all Personally Identifiable Information (PII) encountered in the performance of services in accordance with DFARS 224.103 and DoDD 5400.11, Department of Defense Privacy
Program, and DoD 5400.11-R. If a PII breach results from the contractor’s violation of the aforementioned policies, the contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals who’s PII has been compromised.
1.4.5.5 AT Level 1 Awareness Training (AT). All contractor employees requiring access to
Army Installations, facilities, and controlled access areas shall complete Level 1 AT within
10 calendar days after contract start date and within 10 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR, or to the KO if a COR is not assigned, within 10 calendar days after completion of training. Level 1 AT is available at http://jko.jten.mil/courses/atl1/launch.html.
1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.4.6.1 Key Control. This SOW does not require handling of keys or key cards issued by the government.
1.4.7 Special Qualifications. The contractor shall ensure all employees possess all required licenses for operating heavy equipment, welding licenses, Material Handling Equipment (MHE) i.e. Forklift and any others, in the performance of this contract. The Government does not http://jko.jten.mil/courses/atl1/launch.html provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified and qualified to provide services.
1.4.8 Post Award Conference/Periodic Progress Meetings. The contractor agrees to attend any post award conference convened by the KO in accordance with Federal Acquisition Regulations
Subpart 42.5. The KO, Contracting Officer’s Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the Contacting Officer will apprise the contractor of how the
Government views the contractor’s performance and the contractor shall apprise the
Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
1.4.9 Contract Manager (CM). The contractor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO within 3 calendar days after contract award. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, (or the KO if a COR is not assigned), to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.4.10 Identification of Contractor Employees. All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on email) and dealings with Government or non- Government entities/ Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed. The contractor shall retrieve all identification media (including vehicle passes) from their employees who depart employment for any reason. All identification media (i.e., badges and vehicle passes shall be returned to the
COR within the 10 days of an employee’s departure) or contract completion.
1.4.11 Combating Trafficking in Persons. The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in any forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the
United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The Contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.Contractor shall complete the following online training within 10 calendar days after contract award: Course number is N-
US189-HB; available at: http://jko.jten.mil/.
1.4.12 Reserved.
1.4.13 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the
Government with all rights and privileges of ownership /copyright belonging exclusively to the
Government. These documents and materials may not be used or sold by the contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. Provide a copy 10 calendar days after contract completion. This right does not abrogate any other Government rights.
1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive have access to or participate in the development of proprietary or source selection. In addition to substantial (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.). Perform evaluation services, which may create current or subsequent OCIs, as defined in FAR Subpart
9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to http://jko.jten.mil/ the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.4.15 Quality Assurance/Quality Control (QA/QC) Plan: Provide a QA/QC plan to the COR within 15 calendar days after contract award, in accordance with the “Guía de Cierre Permanente para Sistemas de Tanques de Almacenamiento Soterrados”.
1.4.16 Waste Management Plan: The Contractor shall submit a preliminary Waste Management
Plan and a final Waste Management Plan. The preliminary waste management plan and final
Waste Management Plan should address key components, such as daily housekeeping practices, storage/accumulation procedures, disposal methods, recycling or landfill information, disposition documentation, etc. The contractor shall submit to the COR for approval prior to commencement of demolition services, IAW UFGS 01 74 19, para 1.6 and UFGS 02 81 00, para 3.1.2. The project waste diversion goal is 60%. Approval of the contractor’s plan will not relieve the contractor of responsibility for compliance with applicable environmental regulations or meeting project cumulative waste diversion requirement. This plan shall be coordinated with the installation waste management plan so there are no conflicts. This plan may be incorporated with the work plan. Disposal slips from landfill and/or recycler must be submitted to the Base Environmental Management Office to report amounts of debris landfilled or recycled.
1.4.18 Health and Safety Plan (HSP): The Contractor shall prepare a site-specific HSP to comply with Air Force, Occupational Safety and Health Administration (OSHA), United States
Environmental Protection Agency (USEPA), state PR-OSHA, and local health and safety regulations regarding the proposed work. HSP also has to comply with “Guía de Cierre
Permanente para Sistemas de Tanques de Almacenamiento Soterrados” from the DNRE. Provide a copy of the HSP plan to the COR within 15 calendar days after contract award. The Contractor shall notify the KO and COR within 3 calendar days if a change is required to the HSP. The
Contractor shall adhere to USEPA guidelines for designating the appropriate levels of protection needed at the demolition site(s) as applicable. The Contractor shall maintain and have readily available written certification that the approved HSP has been reviewed and briefed with all personnel that work at the project site prior to the employee’s start date.
1.4.19 Site Closure Report. The contractor shall prepare and submit to the Base Environmental
Management Office and COR, for review and approval, a draft and final closure report as required for UST Closure permits. Typical processing time is 21 calendar days for the initial review/approval and, if necessary, 14 calendar days for resubmittal review/approval.
2.0 Definitions and Acronyms
2.1 Definitions.
2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or services to the government. The term used in this contract refers to the prime. 2.1.2
CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S.
Government designated by the KO to monitor contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5 DELIVERABLE. Anything that can be physically delivered and includes no manufactured things such as meeting minutes or reports.
2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key
Personnel listed in the SOW. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.8 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The
Government does not have privity of contract with the subcontractor.
2.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.
2.2 Acronyms
AEI Army Enterprise Info Structure
AFARS Army Federal Acquisition Regulation Supplement
ANG Air National Guard
AR Army Regulation
AUP Acceptable Use Policy
BBP Better Business Practice
CDM Concept Development Meeting
CFR Code of Federal Regulations
CM Contract Manager
COMSEC Communications Security
CONUS Continental United States
COR Contracting Officer Representative
COTS Commercial-Off-the-Shelf
CUI Controlled Unclassified Information
DA Department of the Army
DD250 Department of Defense Form 250 (Receiving Report)
DD254 Department of Defense Contract Security Requirement List
DFARS Defense Federal Acquisition Regulation Supplement
DMDC Defense Manpower Data Center
DNER Puerto Rico Department of Natural Resources and Environment
DOD Department of Defense
FAR Federal Acquisition Regulation
FEMA Federal Emergency Management Agency
FPCON Force Protection Condition
FPM Final Planning Meeting
HQDA Headquarter Department of Army
IA Information Assurance
IPM Initial Planning Meeting
IT Information Technology
JTR Joint Travel Regulation
JTF Joint Task Force
KO Contracting Officer
MHE Material Handling Equipment
MOA Memorandum of Agreement
MPM Mid-Planning Meeting
MSR Monthly Status Report
NACI National Agency Check Inquires
NGB National Guard Bureau
NLT Not Later Than
OCI Organizational Conflict of Interest
OCONUS Outside Continental United States
ODC Other Direct Costs
OPSEC Operations Security
PCO Procuring Contracting Officer
PII Protection of Personally Identifiable Information
POC Point of Contact
PRS Performance Requirements Summary
SOW Scope of Work
QA Quality Assurance
QAP Quality Assurance Program
QASP Quality Assurance Surveillance Plan
QC Quality Control
QCP Quality Control Program
SME Subject Matter Experts
TAR Travel Authorization Request
TE Technical Exhibit
WWAF-RA Wide Area Workflow-Receipt and Acceptance
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S). The
Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract.
3.1 Property: Government will authorize contractor to an area for material storage and temporary office.
3.2 Materials: None.
3.3 Equipment: None.
3.4 Services: None.
3.5 Utilities: None.
4.0 Contractor Furnished Property, Materials, Equipment and Services (GFP/M/E).
4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph
3.0, the contractor shall furnish everything required to perform these services as indicated in
Paragraph 1.1.
4.2 Bathrooms: The contractor shall provide portable bathrooms for their employees during the period of performance accompanied by its periodical maintenance.
5.1 Requirements.
5.1.1 Contractor is responsible to complete all environmental documentation, forms, permits and reports for the removal of the UST System as required by Federal and state regulations, including the “Guía de Cierre Permanente para Sistemas de Tanques de
Almacenamiento Soterrados” from DNER.
5.1.2 Contractor is responsible to perform all testing, sample collection, analysis, documentation, and decontamination as required by Federal and state regulations, and
DNER’s “Guía de Cierre Permanente para Sistemas de Tanques de Almacenamiento
Soterrados”. Testing work will include:
5.1.2.1 An independent laboratory will perform laboratory analysis and a Puerto
Rico chemist will certify laboratory analysis.
5.1.3 Contractor is responsible for all notification of field activities and scheduling as required by DNER. A DNER technician may be present during the activities and contactor is responsible to make all necessary coordination with agency technicians.
5.1.4 Contractor is responsible for all demolition work, including but not limited to:
5.1.4.1 Extract diesel fuel from UST tank with a vacuum pump and transfer to 10K
AST Tank
5.1.4.2 Demolish, remove and properly dispose according with Federal and state regulations approximately 3840 SF of concrete and asphaltic surface pavement above and around the UST as per construction drawings and specifications. Clean all affected areas and dispose of debris;
5.1.4.3 Degassing and cleanup up tanks before removal.
5.1.4.4 Removal of two (2) USTs, and related dispensing units and piping;
5.1.4.5 Cutting of tanks.
5.1.4.6 Transportation and disposal of steel tanks as scrap metal. The contractor will provide a tank destruction certification.
5.1.4.7 Remove all existing electrical, data, conduits and fuel piping to the greatest extent possible.
5.1.4.8 Excavate and temporarily store soils surrounding the tanks on a soil pile covered with polyethylene liner. Characterize this material to determine the final disposal method. If detected hydrocarbon constituents above regulatory levels, provide disposal at an approved industrial landfill.
5.1.4.9 Provide adequate crane or lifting equipment not remove tanks
5.1.5 Furnish material, personnel and equipment to backfill excavated area
5.1.5.1 Remove contaminated and unsuitable material and dispose
5.1.5.2 Contractor is responsible for designing and constructing stable excavations as mandated by OSHA 29 CFR 1926.
5.1.5.3 Prepare and grade area for backfill complying with minimum compaction requirement and densities in accordance with ASTM D1557.
5.1.5.4 Fill excavated area with backfill material equal to AASHTO “A-2-4” or similar soil characteristic and gradation.
5.1.5.5 Compaction must be done in 8” to 12” layers with a 95% soil compaction or more. Provide third party geotechnical testing/inspection firm for soil classification and field compaction test and certification.
5.1.5.6 Complete backfill area to match existing lines and grade.
5.1.5.7 Disturbed area shall be restore to original condition with sod placement.
5.1.6 Contact water and/or sludge within the tanks will be stored in 55-gallon UN-approved containers and dispose of appropriately.
5.1.7 If there is evidence that a subsurface release has occurred, a subsurface investigation of the site should be evaluated/performed and the suspected release informed to DNER according to current regulations.
5.1.8 A Closure Report will be prepared for the UST closure activities detailing the activities, as per “Guía de Cierre Permanente para Sistemas de Tanques de Almacenamiento
Soterrados”.
5.1.9 As applicable, take a soil sample and groundwater samples to determine TOTAL
LEAD concentrations.
5.2 The Contractor must be responsible for the installation of any electrical, plumbing and any other required utilities in order to complete the tasks specified on this SOW.
5.3 This statement of work does not supersede any Federal Acquisition Regulation stipulations that may appear in this contract.
5.4 The Contractor is subject to all Installation Fire, Safety, Security, Civil Engineer, OPSEC, Traffic Regulations and all applicable Federal and State regulations.
5.4.1.1 Fire Safety: The Contractor shall comply with all local fire regulations and NFPA
241 during all demolition and construction work. All fire extinguishers required shall be provided and maintained by the contractor, but must be approved for use by the contracting officer prior to use. “Hot-work” operations, those involving welding, soldering, brazing, or torch heating shall not commence before an AF Form 592 is completed and signed by the Fire
Inspector. The contractor shall contact the Fire Department’s inspection section at least one work day prior to hot-work operations for assistance and completing the Form 592. There shall be no open burning of waste materials or debris during this contract.
5.5 The Government contracts on the understanding that the Contractor is complying with applicable laws concerning workplace safety.
5.6 The Contractor is subject to all citations and penalties for violation of applicable workplace safety laws. The burden of compliance rests with the Contractor.
5.7 The Contracting Officer may notify the Contractor of hazards in Contractor operations that endanger Government personnel or property and require appropriate abatement action. This provision does not constitute assumption of liability for Occupational Safety and Health compliance on the part of the Government or negate other agency responsibility for enforcement of applicable laws.
5.8 Accident prevention principles must be thoroughly integrated into all operations. Unsafe
Conditions and practices, as identified by the Contracting Officer or designated representative, must be corrected immediately.
5.9 Any and all debris generated by the Contractor’s operations shall be removed from the base.
Solid Waste Management: All waste materials and debris generated by work under this contract shall be processed, handled, transported, stored, and disposed of by the contractor in accordance with all federal, state, local, regulations, and laws. All waste streams will be quantified and reported to the Base Environmental Manager. The Contractor shall be responsible for any permit or fees associated with the use of off-base disposal locations.
5.10 The Contractor shall be liable for any loss, destruction or damage and deterioration to
Government property, including vegetation and landscaping, resulting from Contractor operations. Any damage to government or personal property shall be repaired or replaced to the Contracting Officer’s satisfaction at the Contractor’s expense.
5.11 All work under this project shall meet applicable County, Territorial, Federal and Air National
Guard construction codes, regulations and policies.
5.12 Contractor shall coordinate with Contracting Officer to verify the existing site and facility conditions. Any differing conditions shall be notified in writing to request clarification.
5.13 Equipment or fixtures Government Furnished Contractor Installed (GFCI): None anticipated.
5.14 Comply with all Specifications applicable found and included by reference in the www.wbdg.org site. This will include all UFC and UFGS.
5.15 For additional information on drawings and specifications, and for entering the Site premises contact the Base Civil Engineer (BCE) office in Building 25, Muñiz ANG Base telephone
(787) 253-5172, or fax (787) 253-5226 or 7415. Must request Digging Permit before work start.
5.16 For additional contracting issues will be directed to the Contracting Officer in Building 29, Muñiz ANG Base at telephone (787) 253-5238 or 7438. Must fill out Base Access Letter before project start.
5.17 For additional Environmental information contact the Environmental Manager Office in
Building 25, Muñiz ANG Base telephone (787) 253-5192, or fax (787) 253-5226 or 7415.
5.18 For additional Safety information contact the Safety Office in Building 22, Muñiz ANG Base telephone at (787) 253-5275Must request Confine Space Entry AF Form 1024 before work start.
5.19 For additional Bioenvironmental information contact the Bioenvironmental Office in
Building 16, Muñiz ANG Base telephone at (787) 253-5265.
5.20 For additional Fire information contact the Fire Department in Building 3, Muñiz ANG Base telephone at (787) 253-5222. Must request permit to use open flame equipment or grinders.
5.21 For additional Security information, contact the Base Defense Operation Center in Building
2, Muñíz ANG Base telephone at (787) 253-5204.
5.22 Contractors must be registered (current) in the System for Award Management (SAM) internet program at: http://www.sam.gov.
file://///Rckb-fs-001v/156aw-erm%20(r)/32-014%20Hazardous,%20Toxic%20Waste%20and%20Storage%20Tanks%20Management/AST_10K_gallons_Punta_Borinquen/www.wbdg.org%20site http://www.sam.gov/
5.23 All invoices must be submitted using Wide Area Workflow (WAWF) internet program at:
https://wawf.eb.mil.
5.24 Contractor will verify status of all invoices My Invoice link at: https://wawf.eb.mil.
5.25 Contractor Manpower Reporting Application (CMRA): The contractor shall completely fill in all required data fields using the following web address: http://www.ecmra.mil/ Reporting inputs shall be for the labor executed during the period of performance during each
Government fiscal year (FY), which runs October 1 through September 30.
5.26 Every day all refuse and remaining materials related to the work will be taken to a refuse container provided by the Contractor.
5.27 Only company cars with distinctive logos posted at passenger and driver doors will be authorized inside Base premises.
5.28 All personnel are required to show a valid not expired ID in the main entrance gate before entering the Base premises.
5.29 At the end of each working day all areas will be clear from equipment, tools and materials.
5.30 Special precautions will be taken at no cost to government to protect base property during the project execution.
5.31 The use of Personal Protective Equipment is mandatory at all time while working on the project.
6.0 Applicable Publications: Publications applicable to this SOW are listed below https://wawf.eb.mil/ https://wawf.eb.mil/
Technical Exhibit 1 Performance Requirements Summary (PRS)
This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).
Performance
Objectives
Performance
Standards
Acceptable
Quality Levels AQL
Surveillance Method / By
Whom
Safety Standards Compliance with safety requirements
Contractor shall have available all records as required on the SOW.
COR / Monthly.
Publication
(Chapter/Page)
Date of
Publication
Mandatory or
Advisory
Website
Federal Acquisition
Regulation
Mandatory https://www.acquisition.gov/?q=browsefar or http://farsite.hill.af.mil/
Defense Federal
Acquisition
Regulation
Supplement http://www.acq.osd.mil/dpap/dars/dfarspgi/cu rrent/index.html or http://farsite.hill.af.mil/
AR 190-13 The Army
Physical Security
Program
25 February
Mandatory http://www.apd.army.mil/ProductMaps/PubFo rm/AR.aspx
AR 530-1 Operations
Security
26 Sep 2014 OK http://armypubs.army.mil/ProductMaps/PubF orm/AR.aspx
DoD 5220.22-M
National Industrial
Security Program
Operating Manual
18 May
OK http://www.dtic.mil/whs/directives/corres/pub
1.html
DG 415-5 General
Facilities Design
Guide
1 June 2011 Advisory https://www.wbdg.org/FFC/ARMYCOE/NATL
GUARD/dg_415_5.pdf
UFC 4-010-01 1 Oct 2013 Mandatory https://pdc.usace.army.mil/library/ufc/4-010- 01/
DOD Min. AT/FP
Standards for
Buildings
29 CFR 1926 OSHA
Construction
January
Mandatory www.OSHA.gov
AR 385-10 Chapter 4
Safety Program http://www.ngbpdc.ngb.army.mil/pubs/385/ngr38
5_10.pdf http://www.acquisition.gov/?q=browsefaror http://www.acquisition.gov/?q=browsefaror http://www.acquisition.gov/?q=browsefaror http://farsite.hill.af.mil/ http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html http://farsite.hill.af.mil/ http://www.apd.army.mil/ProductMaps/PubForm/AR.aspx http://www.apd.army.mil/ProductMaps/PubForm/AR.aspx http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx http://www.dtic.mil/whs/directives/corres/pub1.html http://www.dtic.mil/whs/directives/corres/pub1.html http://www.wbdg.org/FFC/ARMYCOE/NATL http://www.wbdg.org/FFC/ARMYCOE/NATL http://www.wbdg.org/FFC/ARMYCOE/NATL http://www.osha.gov/ http://www.ngbpdc.ngb.army.mil/pubs/385/ngr385_10.pdf http://www.ngbpdc.ngb.army.mil/pubs/385/ngr385_10.pdf
A. SUBMITTAL LIST
DESCRIPTION TYPE QTY DUE REMARKS
Material Approval Submittals:
(all materials used on project)
AF Form 300 1 NLT 7 days after final shop drawings and 7 days before NTP
Must be signed by:
Contracting COR
Contractor (return copy)
Environmental Permit
(including application forms, laboratory results, closure report, agency acceptance/clearance letter etc.)
AF Form 300 1 Approved 7 days before
NTP
Must be signed by:
Contracting COR
Contractor (return copy)
Quality Assurance Plan AF Form 300 1 Approved 7 days before
NTP
Must be signed by:
Contracting COR
Contractor (return copy)
Safety Plan AF Form 300 1 Approved 7 days before
NTP
Must be signed by:
Contracting COR
Contractor (return copy)
Waste Management Plan AF Form 300 1 Approved 7 days before
NTP
Must be signed by:
Contracting COR
Contractor (return copy)
Warranty Certificates
AF Form 300
1 Before final invoice is certified
Must be signed by:
COR CE
B. DESIGN AND CONSTRUCTION STANDARDS AND REFERENCES:
ASTM (American Society for Testing and Materials) – Latest Edition
UL (Underwriter’s Laboratories) – Latest Edition
National Electric Code (NEC) – Latest Edition
Local, Federal, and International (IBC) Codes: ICC - IBC 2018
AFI 91-203, Chapter 18.4
ANG ETL 01-1-1 (Air National Guard Engineering Technical Letter)
Applicable UFCs – Latest Edition
Applicable NFPA– Latest Edition
J-STD-607-A– Latest Edition
ANSI EIS-TIA 607, Commercial Building Grounding (Earthing) and Bonding
Requirements for Telecommunications 5, 6, 7 and Annex B
MIL-STD 188-124B, Grounding, Bonding, Shielding
MIL-HDBK-1004.6, Lightning Protection, May 88
UFC 3-460-01 Chapter 8, Petroleum Fuel Facilities Atmospheric Storage Tanks Design
UFC 3-520-01, Interior Electrical Systems
UFC 3-580-01, Telecomm Building Cabling System Planning and Design, 2-7
MIL-HDBK 419A Grounding, Bonding & Shielding for Electronic Equipment, Appendix B Fig 10 & 11
UL 142, Std for Steel Aboveground Tanks for Flammable and Combustible Liquids
UL 2085, Std for Protected Aboveground Tanks for Flammable and Combustible Liquids
NFPA 30, Flammable and Combustible Liquids Code
NFPA 30A, Code for Motor Fuel Dispensing Facilities and Repair Garages
NFPA 70/NEC Article 250 and Section III and 250.66
NESC C2-2002, Section 9, Grounding Methods for Electric Supply and
Communications Facilities
UFGS 13100A, Lightning Protection System
UFGS 13100N, Lightning Protection System
Unified Facilities Guide Specification (UFGS) Web Site:
http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs
SECTION 32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES
All federal applicable UFC, UFGS and ANG ETL’s must be verified at www.wbdg.org
C. INVOICE REQUIREMENTS:
Electronic pictures of work to be invoiced (Before and After)
Breakdown for Payment
Monthly Report from: Contractor Manpower Reporting Application (CMRA)
Progress Report of activities.
Project Schedule (CPM): Baseline Vs Update
D. CLOSEOUT DOCUMENTATION:
Contractor workmanship letter of warranty up to one year.
Equipment Original Warranty
Equipment (ACU/AHU) Original purchase receipt
ADSIL Treatment Certificate
DNER Environmental Permit, Closure Report and Agency Acceptance/Clearance letter
Recycling or landfill proof of disposition document.
Contractor certificates of no debts to suppliers and vendors.
Contractor workmanship letter of warranty up to one year.
Contractor certificates of no debts to suppliers and vendors.
Commissioning and acceptance of system.
Completed DD Form 1354.
Certification of work by a professional refrigeration provider in accordance with Puerto
Rico Law 416 http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs http://www.wbdg.org/