DPEZ202109 Repair Flooring in Building 30

Question: What is the classification code for Soft Floor or Carpet, Linoleum Layers?

ANSWER: 47-2041 found on https://www.bls.gov/soc/2018/major_groups.htm#47-0000

Question: What is the classification code for Tile Setter?

ANSWER: 47-2044 found on https://www.bls.gov/soc/2018/major_groups.htm#47-0000

Please note in accordance with the WY20200023 the following:

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii)

Question: What is the Bid Amount?

ANSWER: Bid amount will be the amount that the contract is awarded for. Depending on if funding allows for ABIs to be funded.

Question: Can you put the dumpster out front when we are doing demo?

ANSWER: Yes, we can find a location that will be best for the contractor

Question: Do you have a set of the PDF drawing to scale that you can provide?

ANSWER: Yes, they have been added to the solicitation.

Question: Is there a base bid for Zone 2?

ANSWER: No, there is only an ABI for Zone 2

Question: For the demo of the wall is there any electrical inside the walls?

ANSWER: There is no electrical in the wall and there is also no plumbing.