QA Renovate Bldg 307 for Squadron Operations - Question Sheet C.pdf

PDF 642 KB Posted

Attached to
Renovate B307 for Squadron Operations Federal contract opportunity
Solicitation number
W50S8V-22-B-0001
Issued by
Department of the Army National Guard

About this file

This document contains questions and answers regarding a solicitation to renovate Building 307 for squadron operations. Key details include that the project involves renovating the building, including new millwork, overhead doors, and controls systems. Responses provide clarification that battery backup is not required for overhead doors, NEMA-1 enclosures are sufficient, and padlocks are only needed for door 117B. The solicitation number is W50S8V-22-B-0001 and is set aside for small businesses. The project NAICS is 236220 with a size standard of $39.5 million, and the estimated value is between $5-10 million. Davis Bacon wage rates apply and funds are expected to be available by 30 September 2022. Award will be made based on the most advantageous price.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers for Project No:

PJVY 172102

Renovate Bldg 307 for Squadron Operations W50S8V-22-B-0001

QUESTION SHEET “C”

25 April 2022

Questions:

1. Controls: On page M-701 in the general notes it stipulates that the controls vendor has responsibility for power wiring and low-voltage wiring and conduits for the controls system.

Please confirm that the electrician shall not run conduit or any electrical wiring for items connected to or for the controls system.

a. RESPONSE: Bid as shown. This note places the responsibility with the controls contractor (with the full involvement of the general contractor) to provide all the information needed (location, power requirements) to the electrical contractor in order for them to provide power wiring for the controls system. Thus for the controls power connections work, the project electrical contractor would basically be a sub to the control contractor. All low voltage controls wiring and conduit would be provided by the controls contractor.

2. Millwork: The 2 Plam colors from Pionite are discontinued. Please identify an acceptable alternate PL-1/PL-2

a. RESPONSE: The bid pricing for both PL-1 and PL-2 shall be based on the Basis of Design product called out in the finish Schedule on A-607: Pionite, Abstracts, Suede. The specific color shall be selected after award, from the current active (in production) color options.

3. Overhead Doors: Specs call for 4-hour battery backup. This is not available by many brands like Liftmaster or Overhead door. Please confirm the requirement of a 4-hour battery backup.

a. RESPONSE: Eliminate the battery backup.

4. Overhead Doors: Specs call for explosion-proof motors and controllers. Is there additional information for this specification?

a. RESPONSE: Eliminate the requirement for explosion-proof motors and controls in the

OH door spec

5. Overhead Doors: Specs also call for controllers to be NEMA-13 and NEMA-9, and later NEMA-4 with keyed lock-out. (NEMA-1 is standard with the operator, interior mounted. Others as an option.) Which one(s) is needed?

a. RESPONSE: NEMA - 1

6. Overhead Doors: Specs call for pneumatic (non-monitored) and electric wireless (monitored) sensing edges. Which one? (Monitored safety system is required if the momentary-contact-to-close operation or remote transmitter is required.)

a. RESPONSE: Provide the electric wireless sensing edges.

Questions & Answers for Project No: QUESTION SHEET “C” PJVY 17210220 April 2022 Renovate Bldg 307 for Squadron Operations Response 22 April 2022

7. Overhead Doors: Specs call for operators to have grease fittings with dust caps. Most operators have sealed bearings. Please confirm grease fittings are necessary.

a. RESPONSE: Grease Fittings are not required. Operators are allowed to use sealed bearings.

8. Millwork: For rooms 123A, 106, 208, and 111 sinks are shown, please confirm the countertop material, SS1 or laminate.

a. RESPONSE: The countertops for all new Cabinets and Counters on this project shall be ½" Solid surfacing (SS-1 - Finish Schedule) with a 1 ½" SS-1 edge.

9. Millwork: SS1 Corian Canvas is called to be installed on the restrooms countertops with sinks and all service countertops, but on the millwork details drawings it does not call for the restrooms and there is no details. Please advise if the SS1 is for the restrooms also even if there is no detail.

a. RESPONSE: This project does not include any Architectural/Interiors work in the building’s toilet rooms. Disregard any references to finishes in bathrooms.

10. Millwork: On page A301/ detail 4 and 5 calls for service counter, where exactly are the service counters located on the plans, and in which areas?

a. RESPONSE: There is one service counter in this project, located in the wall between Rooms 123 C & 123.

Questions & Answers for Project No: QUESTION SHEET “C” PJVY 17210220 April 2022 Renovate Bldg 307 for Squadron Operations Response 22 April 2022

11. Overhead Doors: Door spec asks for 10 cycles per day rating. Need to know how many cycles the door’s torsion will be rated for overall: 20,000, 50,000, 75,000 or 100,000? Also, the warranty spec says “Torsion for 2 years”. Torsion springs are warranted for # of cycles, not the time period.

a. RESPONSE: Warranty Torsion Springs for 50,000 cycles.

12. Overhead Doors: Door 117 Spec calls for dual pad-lockable slide locks. Is that spec for 117B and

117C? Or for just one of them?

a. RESPONSE: The pad –lockable side lock is only required on one side of the door and is required for 117B. 117 C is a double swing door with a removable center mullion. One door leaf gets an exit d3evice and the other gets top and bottom flush bolts

13. Overhead Doors: Are doors #117B, 123-4, and 126-2 to be motorized or chain operated?

a. RESPONSE: Provide both Motor control with wall switches and chain operator for electrical outages.

14. Overhead Doors: Specs call for operators to auto-close by fire/smoke detection and have fail-safe-close upon power outage. This is possible with a fire-rated operator, but the door would also have to be fire-rated. No specs for a fire door. Please advise

a. RESPONSE: The doors with the smoke detection and fail safe operation do not require a fire rating, but models that have fire rating will be acceptable.

15. Is this project Tax Exempt?

a. RESPONSE: Contractor is responsible for all Federal, State, and Local Taxes in accordance with FAR 52.229-3.

16. Will doors and operators be subject to “Buy American?”

a. Reference FAR 52.225-9, Buy American – Construction Materials

17. Warranty spec says “Torsion for 2 Years.” Torsion springs are warranted for # of cycles, not time period. See above question about how many cycles is desired.

a. See response to question #11